Central Louisiana Electric Co. v. Dolet Hills Mining Venture

116 F. Supp. 2d 710, 1999 U.S. Dist. LEXIS 22228, 1999 WL 33207984
CourtDistrict Court, W.D. Louisiana
DecidedJune 3, 1999
DocketCiv.A. 97-0728
StatusPublished
Cited by1 cases

This text of 116 F. Supp. 2d 710 (Central Louisiana Electric Co. v. Dolet Hills Mining Venture) is published on Counsel Stack Legal Research, covering District Court, W.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Central Louisiana Electric Co. v. Dolet Hills Mining Venture, 116 F. Supp. 2d 710, 1999 U.S. Dist. LEXIS 22228, 1999 WL 33207984 (W.D. La. 1999).

Opinion

MEMORANDUM RULING

STAGG, District Judge.

Before the court are two motions for partial summary judgment. The first of these motions was filed by the plaintiffs, Central Louisiana Electric Company, Inc. (“CLECO”) and Southwestern Electric Power Company (“SWEPCO”) (hereinafter collectively referred to as “Project”). The second motion was filed by the defendants and counter-plaintiffs, Dolet Hills Mining Venture, a joint venture mining partnership whose partners consist of defendants Mining Beteiligungs-GmbH & Co. KG and Mansfield Mining Company (hereinafter collectively referred to as “DHMV” or “Miner”). Based on the following, Project’s motion for partial summary judgment is GRANTED IN PART AND DENIED IN PART. DHMV’s motion for partial summary judgment is GRANTED IN PART AND DENIED IN PART.

I. BACKGROUND

A. Facts.

Central Louisiana Electric Company, Inc. and Southwestern Electric Power Company agreed in 1978 to jointly develop Louisiana’s abundant lignite reserves and construct a power plant. The companies pooled their resources and, after several years of studies and analyses, announced plans to build a 640,000 kilowatt lignite-fired electric generating plant at Dolet Hills.
Shortly thereafter, the Dolet Hills Mining Venture, jointly owned by The Costain Group PLC of England and Jones Group, Inc. of North Carolina, was contracted to mine and deliver lignite to the power plant. Mining lignite began in August 1985, and Louisiana lignite became a new source of electric energy.
The Dolet Hills Mining Venture recovers lignite by surface mining using a giant dragline to remove 20 to 140 feet of dirt and expose the lignite below. The dragline is as tall as a 20-story building. It weighs 8 million pounds and has a 77 cubic yard bucket. The *713 bucket holds enough dirt to fill a one-car garage.
******
Seams of lignite are uncovered by the dragline around the clock. Once exposed, the lignite, in layers 6-10 feet thick, is removed with a large backhoe and loaded into trucks. Each truck is capable of carrying 85 tons of lignite. After the lignite is removed, the drag-line fills the pit with dirt from the next pit that is being excavated, helping to return the area to its original contour. Trucks filled with lignite haul to a central collection site, and they dump their loads at the beginning of a seven-mile conveyor belt for transport to the power plant. The conveyor belt travels 800 feet per minute and delivers 1000 tons of lignite to the plant every hour. The Louisiana fuel source provides the energy of 6 million barrels of crude oil each year.

Record Document 22, Ex. 7.

CLECO and SWEPCO are regulated public utilities engaged primarily in the business of generating and selling electricity to the public in the states of Louisiana, Arkansas and Texas. The Dolet Hills Power Plant is located near Mansfield, Louisiana (“the Plant”), and is fueled primarily by lignite reserves that are controlled or intended to be controlled by Project, either as lessee under mineral leases or as owner. 1 The unit was to be a mine-mouth unit to take advantage of the adjacent lignite reserves while avoiding the necessity of transporting the lignite reserves any substantial distance from the point of extraction to the Plant.

Although Project planned to use the lignite as the primary fuel for the Plant, Project did not want to mine the lignite reserves. Instead, Project sought to contract with an independent contractor who would mine and deliver Project’s lignite reserves to the Plant for a fee based on the number of tons of lignite nominated by Project. In 1981, Project invited various mining companies “to submit -a proposal ... for a long-term lignite supply contract.” The invitation for bids further advised that the power plant would “require approximately 2.5 million tons of lignite per year” when it reached its purported design capacity; that the mining company would mine and supply this lignite “on a base-price (escalated) basis;” that the “primary term of the agreement [would] be 25 years with provisions for extension;” and that the proposed “mine should be designed to accommodate expansion to approximately double the initial size to support generation by a second unit if CLECO/SWEPCO should decide to install a second unit ht a later date.” After lengthy negotiations with various potential contractors, Project and DHMV 2 entered into a long-term contract comprised of a Lignite Mining Agreement (“LMA”), together with exhibits and other specified documents (collectively the “Contract”), effective as of March 16, 1982, pursuant to which DHMV agreed to mine and deliver lignite. 3 The 1982 LMA is a *714 long-term supply contract and has been amended numerous times. 4 Initial commercial operation of the Plant occurred in April, 1986.

Although there is a base price paid for lignite mined by DHMV, the price may escalate depending on both the quantity and quality of the lignite. Certain costs incurred by DHMV are passed through to ^Project. DHMV has supplied lignite to Project under the LMA. since 1985. Allocation of risk was expressly addressed by Project when it requested bids for the lignite supply contract: “[B]ids are to be proposed with the understanding that the Bidder will take the risk of production cost variability and Owners will take the risk of inflation.”

B. The Disputes.

In the original set of agreements of March 16, 1982, there was an Option and Security Agreement described as necessary to assure Project of a solvent Miner over the projected 25 year life of the mining agreement. Article 5.3 required DHMV to make an initial equity investment from its own cash reserves of not less than $25,000,000, and to maintain a debt to equity ratio of not more than 2.8 to 1.

Following the change of ownership of DHMV (involving a purchase price of $75,-000,000), the Third Amendment to the Option and Security Agreement became effective. For the first time since mining began, the contract required from DHMV a monthly statement setting forth the calculation of the debt to equity ratio “in such detail as reasonably required by PROJECT, certified by MINER’S chief financial officer, subject to year-end audit adjustments.” This provision became the subject of dispute. In addition, another dispute arose over the meaning of Section 24.2 of the LMA concerning the right of Project to vary delivery nominations and over the meaning of Article 22 of the LMA regarding Project’s ability to inspect the books and records of DHMV.

C. Procedural History.

On April 15, 1997, Project filed suit in this court against DHMV, requesting, inter alia,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth Edison Co. v. Illinois Commerce Commission
924 N.E.2d 1065 (Appellate Court of Illinois, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
116 F. Supp. 2d 710, 1999 U.S. Dist. LEXIS 22228, 1999 WL 33207984, Counsel Stack Legal Research, https://law.counselstack.com/opinion/central-louisiana-electric-co-v-dolet-hills-mining-venture-lawd-1999.