Central Kansas Power Co. v. State Corporation Comm.

316 P.2d 277, 181 Kan. 817, 21 P.U.R.3d 157, 1957 Kan. LEXIS 414
CourtSupreme Court of Kansas
DecidedOctober 9, 1957
Docket40,371
StatusPublished
Cited by17 cases

This text of 316 P.2d 277 (Central Kansas Power Co. v. State Corporation Comm.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Central Kansas Power Co. v. State Corporation Comm., 316 P.2d 277, 181 Kan. 817, 21 P.U.R.3d 157, 1957 Kan. LEXIS 414 (kan 1957).

Opinion

The opinion of the court was delivered by

Fatzer, J.:

These two appeals are from a judgment of the district court of Ellis County vacating and setting aside as unreasonable two orders of appellant State Corporation Commission, hereafter referred to as the commission, entered on the application of appellant Kansas-Nebraska Natural Gas Company, Inc., hereafter referred to as Kansas-Nebraska, insofar as those orders affected appellee Central Kansas Power Company, hereafter referred to as Central.

Roth Kansas-Nebraska and Central are Kansas corporations and are public utilities engaged in the production, purchase, sale, transmission and distribution of natural gas in Kansas. Kansas-Nebraska’s principal office is in Phillipsburg, Kansas, and Central’s principal office is in Abilene, Kansas.

A brief background of each utility will be helpful. Kansas-Nebraska produces and purchases gas in Kansas, Oklahoma, Colorado and Nebraska, and transmits and distributes it through its pipe line system to wholesale and retail customers in Kansas, Nebraska, and to a limited extent in Colorado. It has two main pipe lines: the first, originating in the Hugoton field and extending northward to serve principally cities, which is termed the Oakley line, thence into Nebraska; the second, which is referred to as its predominant line, reaches the Hugoton field south from Kearny County and *819 runs northeasterly from a point in that county to WaKeeney, thence to Phillipsburg and Stockton where it is joined with a line that procures gas from the Pawnee-Unruh area. Since April 1944 Kansas-Nebraska has purchased approximately 96 percent of its gas, 84 percent of which was secured from the Hugo ton field in Kansas. Of the gas purchased and produced in Kansas, approximately 36 percent was sold and distributed in Kansas, while approximately 64 percent was sold and distributed in Nebraska. Kansas-Nebraska serves 50 communities in western Kansas — ten at wholesale, either directly from its transmission line to a purchaser who transports the gas in its own pipe lines to points of distribution, or by delivery to the distribution system of the purchaser at the "town border”; and 40 in which it makes sales of gas to retail customers in the community through its own distribution system. During 1953 Kansas-Nebraska served gas in Kansas to an average of 12,384 residential, 2,446 commercial, and 148 industrial customers. It also made direct sales from its transmission system to industrial and institutional customers in Kansas.

Central owns a gas pipe-line system in central and western Kansas and is engaged in the transmission, distribution and resale of gas which it purchases from Kansas-Nebraska. In addition, it owns and operates electric generating plants located at Colby, Atwood, Hoxie and Hill City, interconnected to permit transmission of electric power from each plant to cities in the areas served.

On April 3, 1944, Kansas-Nebraska, having contracts for a supply of gas from the Hugoton field and desiring to construct a second pipe line from a point in Kearny County northeasterly to WaKeeney and Stockton, entered into a contract whereby it agreed to sell and deliver, and Central agreed to purchase, all of the gas Central might require for resale to customers then or thereafter connected to its distributing system at a price of 6 cents per M. c. f. to be delivered to Central’s transmission system at WaKeeney, or at an emergency delivery point at Toulon, Kansas. This agreement is referred to as the WaKeeney contract and was effective until September 1, 1959. It was amended by supplemental agreements of April 4, 1946, and May 22, 1950, and also by orders of the commission entered February 18, 1949, and December 2, 1953. Together with its supplements, it was filed with the commission pursuant to G. S. 1949, 66-108, and remained in effect until abrogated by the commission as hereafter detailed.

*820 The WaKeeney contract was beneficial to both utilities. Central held franchises for the retail sale of gas in Hays, Ellis and Wa-Keeney. Although it owned producing gas wells, production was insufficient to insure performance of the franchises and the contract guaranteed Central adequate gas reserves. The contract assisted Kansas-Nebraska in financing the construction of the second pipe line: it provided a minimum return by requiring Central to pay a maximum demand charge on 5,000,000 c. f. deliveries, regardless of whether that amount was needed, but Kansas-Nebraska was obligated to deliver to Central only such gas as was available from its then source of supply. Central agreed to refrain from sale or delivery of gas to any additional customers for resale without Kansas-Nebraska’s approval. Lateral lines were not required to establish service to Central, and it (Central) provided a site for Kansas-Nebraska’s metering and regulation system at WaKeeney. The contract further provided that Kansas-Nebraska had the right, upon 60 days notice to Central, to require reconsideration of the price if the combined amount of its labor and tax costs were increased by 100 percent or more.

On May 22, 1950, a second supplement to the WaKeeney contract increased the price of gas to Central to 11 cents per M. c. f. and contained an escalator clause which provided that if the commission’s order of February 18,1949, establishing a minimum 8-cent wellhead price was sustained by the courts, Central would pay an additional 2 cents per M. c. f. for all gas produced after March 1, 1950. This order was sustained by this court October 7, 1950 (Kansas-Nebraska Natural Gas Co. v. State Corporation Commission, 169 Kan. 722, 222 P. 2d 704), and Central was billed from March 1, 1950, accordingly. The escalator clause further provided that in the event any other order be made by any authorized federal or state agency increasing the wellhead cost of gas in the Hugo-ton field in excess of 6 cents per M. c. f., Kansas-Nebraska could charge any or all cost to Central. On December 2, 1953, the commission established a minimum wellhead cost of 11 cents per M. c. f. as a condition for the withdrawal of gas from the Hugoton field. That order was sustained by this court December 8, 1956 (Cities Service Gas Co. v. Slate Corporation Commission, 180 Kan. 454, 304 P. 2d 528). However, Central was billed in accordance with this order from January 1,1954, its effective date.

In addition to the WaKeeney contract, the utilities entered into *821 what is referred to as the Colby contract of July 1, 1952, supplemented on August 1, 1952, whereby Kansas-Nebraska agreed to furnish Central’s gas fuel requirements for its electric generating plants at Colby, Atwood, Hoxie and Hill City. This contract contained a schedule of rates and an escalator clause providing that the price to Central was to be increased to reflect any increase in price at the wellhead above 8/2 cents per M. c. f. This contract and its supplement were filed with the commission pursuant to G. S. 1949, 66-108, and the rates therein prescribed were in effect when Kansas-Nebraska filed its application with the commission hereafter referred to.

The WaKeeney contract and its supplements and the minimum wellhead price in the Hugoton field established by the commission December 2, 1953, increased Central’s cost of gas approximately $103,600.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Attorney General Opinion No.
Kansas Attorney General Reports, 1997
Southwest Kansas Royalty Owners Ass'n v. State Corp. Commission
769 P.2d 1 (Supreme Court of Kansas, 1989)
H. Miller & Sons, Inc. v. Hawkins
373 So. 2d 913 (Supreme Court of Florida, 1979)
Agricultural Products Corp. v. Utah Power & Light Co.
557 P.2d 617 (Idaho Supreme Court, 1976)
Wycoff v. Quick Way Homes, Inc.
441 P.2d 886 (Supreme Court of Kansas, 1968)
Cities Service Gas Co. v. State Corporation Commission
440 P.2d 660 (Supreme Court of Kansas, 1968)
Kansas Public Service Co. v. State Corporation Comm.
433 P.2d 572 (Supreme Court of Kansas, 1967)
Kansas Power & Light Co. v. Mobil Oil Co.
426 P.2d 60 (Supreme Court of Kansas, 1967)
Tri-State Hotel Co. v. Londerholm
408 P.2d 864 (Supreme Court of Kansas, 1965)
Southwestern Bell Telephone Co. v. State Corp. Commission
386 P.2d 515 (Supreme Court of Kansas, 1963)
Class I Rail Carriers v. State Corporation Commission
380 P.2d 396 (Supreme Court of Kansas, 1963)
Missouri-Kansas-Texas Rld. Co. v. City of Savonburg
348 P.2d 1015 (Supreme Court of Kansas, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
316 P.2d 277, 181 Kan. 817, 21 P.U.R.3d 157, 1957 Kan. LEXIS 414, Counsel Stack Legal Research, https://law.counselstack.com/opinion/central-kansas-power-co-v-state-corporation-comm-kan-1957.