Agricultural Products Corp. v. Utah Power & Light Co.

557 P.2d 617, 98 Idaho 23, 1976 Ida. LEXIS 263
CourtIdaho Supreme Court
DecidedDecember 2, 1976
Docket11927
StatusPublished
Cited by31 cases

This text of 557 P.2d 617 (Agricultural Products Corp. v. Utah Power & Light Co.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Agricultural Products Corp. v. Utah Power & Light Co., 557 P.2d 617, 98 Idaho 23, 1976 Ida. LEXIS 263 (Idaho 1976).

Opinion

McFADDEN, Chief Justice.

Utah Power and Light Company is a public utility serving customers in Utah, Wyoming and Idaho. Agricultural Products Corporation, now Beker Industries, operates the phosphate reduction fertilizer facility at Conda, Idaho. On December 28, 1973, Utah Power filed an application for approval of proposed electric service rates with the Idaho Public Utilities Commission, IPUC File No. U-100962. Permission was granted for Agricultural Products to intervene on March 5, 1974. On January 13, 1975, the IPUC issued Order No. 11736 granting rate charge increase relief to Utah Power for all customers. On January 16, 1975, Order No. 11746 was issued amending Order No. 11736 as it dealt with the amount of the rate contract increase approved for Agricultural Products. Agricultural Products and other intervenors filed motions for rehearing, which were denied. Only Agricultural Products has appealed. We set aside the order of the Idaho Public Utilities Commission insofar as it is applicable to appellant.

Two issues are raised on appeal: (1) whether the figures submitted by Utah Power to substantiate the claimed revenue deficiency upon which the rate increases were premised were “budget” figures and were adequate to support the increase granted by the Commission, and (2) whether there is competent evidence to support findings by the Commission of need for a different and higher contract rate charge increase for Agricultural Products. The facts and arguments relevant to each of the two issues are discussed separately below.

I

USE OF BUDGET FIGURES TO ESTABLISH REVENUE DEFICIENCY

In attempting to document projected revenue deficiencies and establish the need for a rate increase, Utah Power offered financial exhibits termed “actual operating expenses for 1973, adjusted for 1974 operations in anticipated revenues and for actual and contracted or scheduled increases in expenses.” Those figures were used to establish a test year and project revenue deficiencies. Based on that test year, and a determination that a rate of return of 8.-4% was reasonable, the Commission concluded that Utah Power would experience a $4,879,888.00 revenue deficiency. Rate charge increases were then granted sufficient to produce the revenues needed. 1 All *25 conclusions of the Commission were based on the use of the adjusted 1974 test year figures.

Appellant contends that those figures were really “budget” figures and were inadequate to establish a need for a rate charge increase. Use of budget figures has been discouraged because budgets are designed for and used for administrative purposes and do not illustrate need for rate relief, especially when actual results are available. Re Idaho Telephone Co., 76 P.U.R.3d 520 (1968). Utah Power executive Stott testified that the figures presented were in effect the company’s budget for the year 1974. Stott admitted that the purpose of preparing a budget was to control expenditures and that the company had control over many of the expenses listed. Another economic expert, Mr. Marshall, testified that there was a difference of approximately four million dollars in net operating revenue between the respondent’s projected 1974 figures and actual operating results for the portion of 1974 which had elapsed at the time of the testimony. Appellant maintains that there is a lack of competent evidence to support a conclusion that the 1974 budget figures reflect a real revenue deficiency.

We disagree. The Public Utility Commission must find that rate charge increases are necessary before a rate increase is granted. I.C. § 61-622. When the Commission finds that rates charged are unjust, unreasonable, discriminatory or preferential, or are insufficient, it must set those rates at a just and reasonable level. I.C. § 61-502. Idaho Public Utilities Commission findings are conclusive on appeal if the overall effect of the rate charge fixed is reasonable and just. Intermountain Gas Co. v. IPUC, 97 Idaho 113, 540 P.2d 775 (1975). The question presented is whether the adjusted 1974 test year resulted in a reasonable and just finding that a rate charge increase was necessary.

Traditionally, public utility commissions have relied upon historical data to determine the need for rate increases. Although this procedure necessarily entails the use of antedated information, the method has been generally accepted as fair and accurate during non-inflationary times. In an inflationary and volatile economy, however, revenue and expense levels experienced in a prior year may be badly outdated 12 months later, and may fail to reflect real needs. The result may be that a utility is granted a lower rate charge increase which does not support current needs. Gibbons, “Some Legal Aspects of the Future Test Period in Utility Rate Regulations,” 16 Ariz.L.Rev. 947, 948 (1974). Consequently, numerous utilities commissions have come to accept the future test year as a necessary and valid method for determining just and reasonable rates. See, e. g., Re Florida Power and Light Co., 98 P.U.R.3d 441, 443 (Fla.Pub.Serv.Comm’n 1973); Re Hawaiian Elec. Co., 96 P.U.R.3d 80 (Ha.Pub.Util.Comm’n 1972); City of New York v. New York Pub. Serv. Comm’n, 42 A.D.2d 259, 346 N.Y.S.2d 6 (1974); Re Mountain States Tel. and Tel. Co., 73 P.U.R.3d 30 (Mont.Pub.Serv.Comm’n 1958); Gibbons, supra.

We hold that the use of an historical test-year, adjusted prospectively for anticipated changes, is a proper method to establish need for a rate change increase, where it is shown that the use of historical data will inadequately demonstrate real revenue needs, and where the future-year projections are shown by the applicant utility to be reasonably reliable and certain. 2 *26 The court approves the procedure set forth by the Commission in In Re Idaho Tel. Co., 76 P.U.R.3d 520, 525 (1969): 3

“The Company, in preparation of its case, should have taken the test year actual, which could have been the latest twelve-months available at the time the case was prepared, and then adjusted these actual figures for all known changes that could affect the results of the test year. The Commission could then have examined the test year and the adjusted test year and determined whether or not it agreed with the adjustments and make any alterations that it deemed proper under the circumstances.”

In the instant case, the Commission found that use of an historical test-year would not adequately reflect the revenue needs of Utah Power:

“[T]he test year to be used in this proceeding to test the reasonableness of the proposed increased rates and charges should be the year ended December 31, 1973, adjusted for 1974 operations.”

Finding No. IV.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Idaho Power Co. v. Cogeneration, Inc.
921 P.2d 746 (Idaho Supreme Court, 1996)
United Telephone Co. v. Public Service Com'n
496 So. 2d 116 (Supreme Court of Florida, 1986)
Afton Energy, Inc. v. Idaho Power Co.
693 P.2d 427 (Idaho Supreme Court, 1984)
Idaho State Homebuilders v. Washington Water
690 P.2d 350 (Idaho Supreme Court, 1984)
FMC Corp. v. Idaho Public Utilities Commission
658 P.2d 936 (Idaho Supreme Court, 1983)
Utah Power & Light Co. v. Idaho Public Utilities Commission
629 P.2d 678 (Idaho Supreme Court, 1981)
Idaho Power Co. v. Idaho Public Utilities Commission
582 P.2d 720 (Idaho Supreme Court, 1978)
Citizens Utilities Co. v. Idaho Public Utilities Commission
579 P.2d 110 (Idaho Supreme Court, 1978)
Grindstone Butte Mutual Canal Co. v. Idaho Power Co.
574 P.2d 902 (Idaho Supreme Court, 1978)
United States v. Utah Power & Light Co.
570 P.2d 1353 (Idaho Supreme Court, 1977)
Bunker Hill Co. v. Washington Water Power Co.
561 P.2d 391 (Idaho Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
557 P.2d 617, 98 Idaho 23, 1976 Ida. LEXIS 263, Counsel Stack Legal Research, https://law.counselstack.com/opinion/agricultural-products-corp-v-utah-power-light-co-idaho-1976.