Centex Construction Co. v. United States

162 Ct. Cl. 211, 1963 U.S. Ct. Cl. LEXIS 111, 1963 WL 8553
CourtUnited States Court of Claims
DecidedJune 7, 1963
DocketNo. 342-60
StatusPublished
Cited by11 cases

This text of 162 Ct. Cl. 211 (Centex Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Centex Construction Co. v. United States, 162 Ct. Cl. 211, 1963 U.S. Ct. Cl. LEXIS 111, 1963 WL 8553 (cc 1963).

Opinion

Per Curiam :

This case was referred pursuant to Rule 45 to Wilson Cowen, a trial commissioner of this court, with directions to make findings of fact and his recommendation for conclusion of law. The commissioner has done so in a report filed September 4, 1962. Exceptions to the commissioner’s report were taken by the plaintiff, briefs were filed by both parties and the case was submitted to the court without argument of counsel. Since the court is in agreement with the findings and recommendation of the trial commissioner, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. See Beacon Construction Company of Massachusetts v. United States, 161 Ct. Cl. 1 (1963), 314 F. 2d 501. Plaintiff is therefore not entitled to recover and its petition is dismissed.

OPINION OF COMMISSIONER

Plaintiff brought this suit to recover compensation for extra work required in the performance of a contract for the installation and construction of certain utilities at McConnell Air Force Base in Kansas.

The Department of the Air Force awarded plaintiff two contracts in connection with the construction of a military housing project at McConnell Air Force Base. The first of these was a Capehart housing contract awarded to plaintiff on April 7, 1958, pursuant to the amendment of August 11, 1955, to the National Housing Act (69 Stat. 646), known as the Capehart Housing Act. The contract, herein referred to as the housing contract, covered the construction of 490 housing units for military personnel on three separate properties or mortgage areas, which were adjacent to each other and were located on the same Government-owned [214]*214project site. The second contract, herein called the off-site contract, was awarded to plaintiff on August 7, 1958, and called for the construction of sewer mains, the laying of water mains, the construction of storm drains, the installation of a street lighting system, the construction of streets and other utilities. It was an appropriated funds contract; it was written on the standard Government construction form, and was complementary to the housing contract. Both contracts were under the supervision of the same contracting officer.

The contract, specifications, and drawings for the housing contract required, in addition to the construction of the housing units, the installation and construction of certain utilities to service the houses but stated that the Department would separately provide for some utilities which would be furnished by others. The contract drawings indicated that the major portion of the utilities to be constructed under the housing contract was within the boundaries of the three mortgage areas. However, four of the contract drawings contained information which, with the specifications, showed that certain utilities, including (1) sewer connections, (2) some water mains and appurtenances, (3) some gas lines and appurtenances, (4) driveway approaches and (5) public walks and street intersections were to be constructed on or across Arnold Boulevard, one of the streets serving the project and in locations which the contract drawings showed to be outside the mortgage boundary lines of the three housing areas or tracts. With the exception of the sewer connections which were deleted from the housing contract and made a part of the off-site contract by an addendum thereto, these are the items of work which are the subject matter of this action.

At the time its bid for the housing contract was submitted, plaintiff was, because of previous experience on similar projects, familiar with the regulations and procedures adopted for carrying out the provisions of the Capehart Housing Act. Plaintiff’s chief engineer, who prepared its bid for both contracts, noted when he examined the contract drawings for the housing contract that they called for the construction of certain utilities in Arnold Boulevard and out[215]*215side the mortgage boundary lines. However, it was his understanding that plaintiff could not be paid under the housing contract for such work, and he assumed that it would be included in the off-site contract soon to be let by the Department of the Air Force. As a result, plaintiff’s bid for the housing contract did not include any amount for the work in controversy.

Although the invitation for bids directed plaintiff to call the contracting officer’s attention to any discrepancies in the drawings and specifications, plaintiff did not call the matter to the attention of the contracting officer until after the housing contract had been awarded and until May 27, 1958, when the invitation for bids and contract drawings for the off-site contract were made available to plaintiff. Upon Observing that these drawings did not provide for the work on Arnold Boulevard, plaintiff telephoned the contracting officer, called his attention to the omission, and urged him to add these items to the off-site contract. Plaintiff’s representative stated that its bid on the housing contract did not cover such work, that plaintiff did not propose to include the work in its bid for the off-site work, and that if such construction was not made a part of the off-site contract, a dispute would arise between the parties. After the contracting officer had consulted with his architect engineer, plaintiff was informed that the work in question was required by the plans for the housing contract. Plaintiff’s bid of May 27, 1958, for the off-site contract did not include any amount for the construction of the utilities on Arnold Boulevard.

The work on the housing contract was scheduled to begin on June 16, 1958, and on June 13, 1958, about three days prior thereto, amendment No. 1 to the invitation for bids on the off-site contract was issued. By that amendment, the sewer connections, lying outside the mortgage boundary lines but previously included in the contract drawings of the housing contract, were deleted from that contract and made a part of the off-site contract. However, no change was made with respect to the four items of work in dispute. As previously stated, plaintiff was awarded the off-site contract on August 7, 1958, signed the contract on August 15, 1958, and was notified to proceed with the work on August 27, [216]*2161958. Before the work under the off-site contract started, plaintiff again called defendant’s attention to the fact that the utilities in issue were not covered by the plans and specifications of that contract. Nevertheless, the contracting officer required plaintiff to complete the work and it did so at a fair and reasonable cost of $11,018.15.

By letter of October 17, 1958, plaintiff requested the contracting officer to grant an addition to the off-site contract for the cost of installing the disputed utilities on Arnold Boulevard. Plaintiff’s letter called attention to the fact that its bid on the housing contract did not include the cost of the work because of plaintiff’s understanding that work performed outside the mortgage boundary lines could not be paid for or included in that contract and reiterated plaintiff’s assumption that such work would be included in the off-site contract. Plaintiff’s letter further stated:

*****
Upon receipt of the plans for the offsite contract, we discovered that these items were not indicated. At that time, we advised Capt. Kelly, who was then the Contracting Officer, of this condition and an addendum was issued requiring the installation of the sewer crossings and to omit the cost of all of the attached items.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
162 Ct. Cl. 211, 1963 U.S. Ct. Cl. LEXIS 111, 1963 WL 8553, Counsel Stack Legal Research, https://law.counselstack.com/opinion/centex-construction-co-v-united-states-cc-1963.