Center for Biological Diversity v. U.S. Office of Surface Mining Reclamation and Enforcement
This text of Center for Biological Diversity v. U.S. Office of Surface Mining Reclamation and Enforcement (Center for Biological Diversity v. U.S. Office of Surface Mining Reclamation and Enforcement) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA
CENTER FOR BIOLOGICAL DIVERSITY, et al.,
Plaintiffs, Civil Action No. 23 - 3343 (SLS) v. Judge Sparkle L. Sooknanan U.S. OFFICE OF SURFACE MINING RECLAMATION AND ENFORCEMENT, et al.,
Defendants.
MEMORANDUM OPINION
The Endangered Species Act of 1973 entrusts federal agencies with the critical task of
identifying and preserving endangered and threatened species across our country. This case is
about whether the Act permits those agencies to delegate certain authorities and responsibilities to
state regulators in the field of coal mining. The Plaintiffs in this case are two environmental
groups—the Center for Biological Diversity and Appalachian Voices—that are concerned about
the risks that coal mining activities pose to threatened species living in Appalachian streams and
rivers, including the Guyandotte River crayfish, Big Sandy crayfish, and candy darter. They claim
that the dwindling number of streams and rivers where these creatures live are at risk of pollution
by displaced sediment, chemical run-off, and other aftereffects of mining. And they contend that
even brief lapses in regulatory oversight could cause significant harm to these threatened species,
including their complete elimination.
The Plaintiffs brought this lawsuit to challenge a written Biological Opinion by the U.S.
Fish and Wildlife Service finding that the mining regulatory program administered by the U.S. Office of Surface Mining Reclamation and Enforcement is unlikely to jeopardize the continued
existence of threatened species. The Plaintiffs assert that the Biological Opinion flouts carefully
designed procedures in the Endangered Species Act and impermissibly approves entrusting state
regulators with responsibilities that lie with the federal Defendants. The Parties now cross-move
for summary judgment. For the reasons below, the Court concludes that the Biological Opinion is
arbitrary and capricious and must be set aside.
BACKGROUND
A. Statutory and Regulatory Background
1. The Endangered Species Act (ESA)
The ESA is “the most comprehensive legislation for the preservation of endangered species
ever enacted by any nation.” Tenn. Valley Auth. v. Hill, 437 U.S. 153, 180 (1978). It “seeks to
protect species of animals against threats to their continuing existence caused by man.” Lujan v.
Defs. of Wildlife, 504 U.S. 555, 558 (1992). Congress tasked two agencies with administering the
ESA: the Fish and Wildlife Service (FWS) and the National Marine Fisheries Service (NMFS).
Nat’l Ass’n of Home Builders v. Defs. of Wildlife, 551 U.S. 644, 651 (2007). “The NMFS
administers the ESA for protected marine and anadromous species (ones that migrate between
freshwater and saltwater); and the FWS administers the ESA with respect to all other protected
species.” Ctr. for Biological Diversity v. Zeldin, 171 F.4th 356, 365 (D.C. Cir. 2026) (citing
50 C.F.R § 402.01(b)).
“[A] species can be ‘listed’ as either ‘endangered’ or ‘threatened’” under the ESA. Id. at
364–65 (quoting 16 U.S.C. § 1533). The Act defines an endangered species as “any species which
is in danger of extinction throughout all or a significant portion of its range” and a threatened
species as “any species which is likely to become an endangered species within the foreseeable
future throughout all or a significant portion of its range.” 16 U.S.C. § 1532(6), (20). Once a
2 species has been “listed,” it gains “significant protections” under the ESA, WildEarth Guardians
v. U.S. Fish & Wildlife Serv., 749 F. Supp. 3d 26, 36 (D.D.C. 2024), which “provide[s] a means
whereby the ecosystems upon which endangered species and threatened species depend may be
conserved” and “a program for the conservation of such endangered species and threatened
species,” 16 U.S.C. § 1531(b).
Section 9 of the ESA makes it unlawful for “any person,” including private parties, States,
and federal agencies, to “take” an endangered species. Id. § 1538(a)(1)(B). The term “take” means
“to harass, harm, pursue, hunt, shoot, wound, kill, trap, capture, or collect, or to attempt to engage
in any such conduct.” Id. § 1532(19). And “Congress intended ‘take’ to apply broadly to cover
indirect as well as purposeful actions.” Babbitt v. Sweet Home Chapter of Cmtys. for a Great Or.,
515 U.S. 687, 704 (1995). Violators of this prohibition may face civil or criminal penalties. See
16 U.S.C. § 1540.
“Recognizing that some take can occur as a result of otherwise lawful activities, Congress
created two paths to ensure that ‘incidental take’ does not jeopardize protected species or adversely
modify or destroy critical habitat: The first path, under Section 7, applies to federal agency actions,
and the second, under Section 10, applies to non-federal actions.” Ctr. for Biological Diversity v.
Regan, 734 F. Supp. 3d 1, 15 (D.D.C. 2024) (first citing 16 U.S.C. § 1536; and then id. § 1538),
aff’d sub nom., Zeldin, 171 F.4th 356. Both Section 7 and Section 10 “offer the promise of liability
protection for incidental take” if certain requirements are met. Id. (first citing 16 U.S.C.
§§ 1536(o)(2), 1539(a); and then 50 C.F.R. § 402.14(i)(5)).
a. Section 7 Consultation
Section 7 of the ESA “prescribes the steps that federal agencies must take to ensure that
their actions do not jeopardize endangered wildlife and flora.” Nat’l Ass’n of Home Builders,
3 551 U.S. at 652. Section 7(a)(2) provides that “[e]ach Federal agency shall, in consultation with
and with the assistance of [the FWS or the NMFS], insure that any action authorized, funded, or
carried out by such an agency . . . is not likely to jeopardize the continued existence of any
endangered species or threatened species or result in the destruction or adverse modification of
habitat of such species.” 16 U.S.C. § 1536(a)(2); see 50 C.F.R. § 402.02. “Action” is defined to
cover “all activities or programs of any kind authorized, funded, or carried out, in whole or in part,
by Federal agencies,” including “the granting of licenses, contracts, leases, easements, rights-of-
way, permits, or grants-in-aid.” 50 C.F.R.
Free access — add to your briefcase to read the full text and ask questions with AI
UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA
CENTER FOR BIOLOGICAL DIVERSITY, et al.,
Plaintiffs, Civil Action No. 23 - 3343 (SLS) v. Judge Sparkle L. Sooknanan U.S. OFFICE OF SURFACE MINING RECLAMATION AND ENFORCEMENT, et al.,
Defendants.
MEMORANDUM OPINION
The Endangered Species Act of 1973 entrusts federal agencies with the critical task of
identifying and preserving endangered and threatened species across our country. This case is
about whether the Act permits those agencies to delegate certain authorities and responsibilities to
state regulators in the field of coal mining. The Plaintiffs in this case are two environmental
groups—the Center for Biological Diversity and Appalachian Voices—that are concerned about
the risks that coal mining activities pose to threatened species living in Appalachian streams and
rivers, including the Guyandotte River crayfish, Big Sandy crayfish, and candy darter. They claim
that the dwindling number of streams and rivers where these creatures live are at risk of pollution
by displaced sediment, chemical run-off, and other aftereffects of mining. And they contend that
even brief lapses in regulatory oversight could cause significant harm to these threatened species,
including their complete elimination.
The Plaintiffs brought this lawsuit to challenge a written Biological Opinion by the U.S.
Fish and Wildlife Service finding that the mining regulatory program administered by the U.S. Office of Surface Mining Reclamation and Enforcement is unlikely to jeopardize the continued
existence of threatened species. The Plaintiffs assert that the Biological Opinion flouts carefully
designed procedures in the Endangered Species Act and impermissibly approves entrusting state
regulators with responsibilities that lie with the federal Defendants. The Parties now cross-move
for summary judgment. For the reasons below, the Court concludes that the Biological Opinion is
arbitrary and capricious and must be set aside.
BACKGROUND
A. Statutory and Regulatory Background
1. The Endangered Species Act (ESA)
The ESA is “the most comprehensive legislation for the preservation of endangered species
ever enacted by any nation.” Tenn. Valley Auth. v. Hill, 437 U.S. 153, 180 (1978). It “seeks to
protect species of animals against threats to their continuing existence caused by man.” Lujan v.
Defs. of Wildlife, 504 U.S. 555, 558 (1992). Congress tasked two agencies with administering the
ESA: the Fish and Wildlife Service (FWS) and the National Marine Fisheries Service (NMFS).
Nat’l Ass’n of Home Builders v. Defs. of Wildlife, 551 U.S. 644, 651 (2007). “The NMFS
administers the ESA for protected marine and anadromous species (ones that migrate between
freshwater and saltwater); and the FWS administers the ESA with respect to all other protected
species.” Ctr. for Biological Diversity v. Zeldin, 171 F.4th 356, 365 (D.C. Cir. 2026) (citing
50 C.F.R § 402.01(b)).
“[A] species can be ‘listed’ as either ‘endangered’ or ‘threatened’” under the ESA. Id. at
364–65 (quoting 16 U.S.C. § 1533). The Act defines an endangered species as “any species which
is in danger of extinction throughout all or a significant portion of its range” and a threatened
species as “any species which is likely to become an endangered species within the foreseeable
future throughout all or a significant portion of its range.” 16 U.S.C. § 1532(6), (20). Once a
2 species has been “listed,” it gains “significant protections” under the ESA, WildEarth Guardians
v. U.S. Fish & Wildlife Serv., 749 F. Supp. 3d 26, 36 (D.D.C. 2024), which “provide[s] a means
whereby the ecosystems upon which endangered species and threatened species depend may be
conserved” and “a program for the conservation of such endangered species and threatened
species,” 16 U.S.C. § 1531(b).
Section 9 of the ESA makes it unlawful for “any person,” including private parties, States,
and federal agencies, to “take” an endangered species. Id. § 1538(a)(1)(B). The term “take” means
“to harass, harm, pursue, hunt, shoot, wound, kill, trap, capture, or collect, or to attempt to engage
in any such conduct.” Id. § 1532(19). And “Congress intended ‘take’ to apply broadly to cover
indirect as well as purposeful actions.” Babbitt v. Sweet Home Chapter of Cmtys. for a Great Or.,
515 U.S. 687, 704 (1995). Violators of this prohibition may face civil or criminal penalties. See
16 U.S.C. § 1540.
“Recognizing that some take can occur as a result of otherwise lawful activities, Congress
created two paths to ensure that ‘incidental take’ does not jeopardize protected species or adversely
modify or destroy critical habitat: The first path, under Section 7, applies to federal agency actions,
and the second, under Section 10, applies to non-federal actions.” Ctr. for Biological Diversity v.
Regan, 734 F. Supp. 3d 1, 15 (D.D.C. 2024) (first citing 16 U.S.C. § 1536; and then id. § 1538),
aff’d sub nom., Zeldin, 171 F.4th 356. Both Section 7 and Section 10 “offer the promise of liability
protection for incidental take” if certain requirements are met. Id. (first citing 16 U.S.C.
§§ 1536(o)(2), 1539(a); and then 50 C.F.R. § 402.14(i)(5)).
a. Section 7 Consultation
Section 7 of the ESA “prescribes the steps that federal agencies must take to ensure that
their actions do not jeopardize endangered wildlife and flora.” Nat’l Ass’n of Home Builders,
3 551 U.S. at 652. Section 7(a)(2) provides that “[e]ach Federal agency shall, in consultation with
and with the assistance of [the FWS or the NMFS], insure that any action authorized, funded, or
carried out by such an agency . . . is not likely to jeopardize the continued existence of any
endangered species or threatened species or result in the destruction or adverse modification of
habitat of such species.” 16 U.S.C. § 1536(a)(2); see 50 C.F.R. § 402.02. “Action” is defined to
cover “all activities or programs of any kind authorized, funded, or carried out, in whole or in part,
by Federal agencies,” including “the granting of licenses, contracts, leases, easements, rights-of-
way, permits, or grants-in-aid.” 50 C.F.R. § 402.02. And an action “jeopardize[s] the continued
existence of” an endangered or threatened species if it “reasonably would be expected, directly or
indirectly, to reduce appreciably the likelihood of both the survival and recovery of a listed species
in the wild by reducing the reproduction, numbers, or distribution of that species.” Id. The agency
proposing the action is known as the “action agency,” and the agency providing consultation—
either the FWS or the NMFS—serves as the “consulting agency.” Oceana, Inc. v. Pritzker, 75 F.
Supp. 3d 469, 474 n.3 (D.D.C. 2014).
The action agency must first determine whether formal consultation is required. To do this,
“[e]ach federal agency shall review its actions at the earliest possible time to determine whether
any action may affect listed species or critical habitat.” 50 C.F.R. § 402.14(a). “If the action agency
determines—and the consulting agency concurs—that ‘the proposed action is not likely to
adversely affect any listed species or critical habitat,’ then no formal consultation is required.”
Ctr. for Biological Diversity, 734 F. Supp. 3d at 16 (quoting 50 C.F.R. § 402.14(b)(1)). But if the
action agency “concludes after an initial review that its action ‘may affect listed species or critical
habitat,’ that agency must engage in ‘consultation’ with [the FWS or the NMFS].” Id. (quoting
50 C.F.R. § 402.14(a)); see also 50 C.F.R. § 402.02 (defining “Service” as either the FWS or the
4 NMFS, “as appropriate”). A formal consultation under Section 7 is triggered for a discrete federal
agency action or “an agency’s multiple actions on a program, region, or other basis.” 50 C.F.R.
§ 402.02.
b. Biological Opinion
The first step of a Section 7 formal consultation requires the consulting agency to prepare
a written Biological Opinion (BiOp) that evaluates whether the planned agency action is “likely to
jeopardize the continued existence” of a protected species or result in the “destruction or adverse
modification” of its critical habitat. See 16 U.S.C. § 1536(a)(2)–(4). “The process of preparing a
BiOp is a rigorous endeavor.” Zeldin, 171 F.4th at 365. The consulting agency must:
(1) Review all relevant information provided by the Federal agency or otherwise available. Such review may include an on-site inspection of the action area with representatives of the [action] agency and the applicant. (2) Evaluate the current status and environmental baseline of the listed species or critical habitat. (3) Evaluate the effects of the action and cumulative effects on the listed species or critical habitat. (4) Add the effects of the action and cumulative effects to the environmental baseline and in light of the status of the species and critical habitat, formulate the Service’s opinion as to whether the action is likely to jeopardize the continued existence of listed species or result in the destruction or adverse modification of critical habitat.
50 C.F.R. § 402.14(g). Additionally, the consulting agency must “[f]ormulate a statement
concerning incidental take, if such take is reasonably certain to occur.” Id. § 402.14(g)(7).
The D.C. Circuit has referred “to the third BiOp requirement as the ‘effects analysis.’”
Zeldin, 171 F.4th at 366 (citing 50 C.F.R. § 402.14(g)(3)). And it has described that analysis as
“encompass[ing] two types of effects.” Id. “First, the ‘effects of the action’ include ‘all
consequences to listed species . . . that are caused by the proposed action, including the
consequences of other activities that are caused by the proposed action.” Id. (alteration in original)
5 (quoting 50 C.F.R. § 402.02). Such effects “may occur later in time and may include consequences
occurring outside the immediate area involved in the action.” 50 C.F.R. § 402.02. “Second, the
‘cumulative effects’ on the listed species include ‘those effects of future State or private activities,
not involving Federal activities, that are reasonably certain to occur within the action area of the
Federal action subject to consultation.’” Zeldin, 171 F.4th at 366 (emphasis in original) (quoting
50 C.F.R. § 402.02).
Once the consulting agency has completed the effects analysis, it must “[a]dd the effects
of the action and cumulative effects to the environmental baseline” and then, “in light of the status
of the species and critical habitat,” formulate its “opinion as to whether the action is likely to
jeopardize the continued existence of listed species or result in the destruction or adverse
modification of critical habitat.” 50 C.F.R. § 402.14(g)(4). “In other words, the [consulting
agency] must determine whether the planned action ‘reasonably would be expected, directly or
indirectly, to reduce appreciably the likelihood of both the survival and recovery of a listed species
in the wild by reducing the reproduction, numbers, or distribution of that species.’” Zeldin, 171
F.4th at 366 (quoting 50 C.F.R. § 402.02). Finally, the consulting agency must set forth its opinion
in a BiOp, summarizing the information on which its jeopardy determination is based, and
detailing “how the agency action affects the species or its critical habitat.” 16 U.S.C.
§ 1536(b)(3)(A); see also 50 C.F.R. § 402.14(h).
“In the event of a ‘jeopardy’ determination, the consulting agency ‘shall suggest those
reasonable and prudent alternatives which [it] believes would not violate [Section 7(a)(2)] and can
be taken by [the action agency].’” Zeldin, 171 F.4th at 366 (alterations in original) (quoting
16 U.S.C. § 1536(b)(3)(A)). “Following the issuance of a ‘jeopardy’ opinion, the [action] agency
must either terminate the action, implement the proposed alternative, or seek an exemption from
6 the Cabinet-level Endangered Species Committee pursuant to 16 U.S.C. § 1536(e).” Id. (alteration
in original) (quoting Nat’l Ass’n of Home Builders, 551 U.S. at 652). “Importantly, in ‘formulating
its biological opinion, any reasonable and prudent alternatives, and any reasonable and prudent
measures,’ the [consulting agency] [is] required to ‘use the best scientific and commercial data
available.’” Id. (quoting 50 C.F.R. § 402.14(g)(8)); see also 16 U.S.C. § 1536(a)(2) (“In fulfilling
the requirements of this paragraph each agency shall use the best scientific and commercial data
available.”).
c. Incidental Take Statement
If the consulting agency makes a “no-jeopardy” determination but concludes that incidental
take is nonetheless “reasonably certain to occur,” 50 C.F.R. § 402.14(g)(7), it must proceed to “the
second step of the Section 7 consultation process” and provide an “incidental take statement” or
ITS, Zeldin, 171 F.4th at 366; see also 50 C.F.R. § 402.14(i); 16 U.S.C. § 1536(b)(4). This step is
necessary where a proposed action “may still cause some harm to the [listed] species” “[e]ven if
[it] will not ‘jeopardize the continued existence’ of [the] listed species.” Shafer & Freeman Lakes
Env’t Conservation Corp. v. FERC, 992 F.3d 1071, 1080 (D.C. Cir. 2021).
When an ITS is required, the consulting agency must include it as part of the BiOp,
16 U.S.C. § 1536(b)(4); 50 C.F.R. § 402.14(i)(1), and the ITS must “(i) specif[y] the extent of the
anticipated take, (ii) identif[y] any ‘reasonable and prudent measures’ that the wildlife agency
considers ‘necessary or appropriate to minimize such impact,’ and (iii) set[] forth detailed ‘terms
and conditions’ that the action agency or licensed private party must undertake to implement those
reasonable and prudent measures,” Shafer, 992 F.3d at 1080 (quoting 16 U.S.C. § 1536(b)(4)). The
ITS must specify “the impact of incidental taking as the amount or extent of such taking” on the
species. 50 C.F.R. § 402.14(i)(1)(i). And the ITS may do that through a “surrogate (e.g., similarly
7 affected species or habitat or ecological conditions)” so long as it adequately explains why it must
use a surrogate and it still “sets a clear standard for determining when the level of anticipated take
has been exceeded[.]” Id.
“[T]he action agency or applicant must ‘monitor the impacts of incidental take’ and ‘report
the progress of the action and its impact on the species to the [consulting agency] as specified in
the [ITS].’” Zeldin, 171 F.4th at 367 (second alteration in original) (quoting 50 C.F.R.
§ 402.14(i)(4)). “The action agency ‘must reinitiate consultation immediately’ if the ‘amount or
extent of incidental taking’ specified in the ITS, as required by the regulations, ‘is exceeded.’” Id.
at 367 (emphasis in original) (quoting 50 C.F.R. § 402.14(i)(5)); see also 50 C.F.R. § 402.16(a)(1).
The action agency must also reinitiate consultation under other circumstances, including: “[i]f new
information reveals effects of the action that may affect listed species or critical habitat in a manner
or to an extent not previously considered;” “[i]f the identified action is subsequently modified in a
manner that causes an effect to the listed species or critical habitat that was not considered in the
biological opinion or written concurrence;” or “[i]f a new species is listed or critical habitat
designated that may be affected by the identified action.” 50 C.F.R. § 402.16(a). Such reinitiation
“shall be requested” by the action agency. Id.
“Ultimately, if [a consulting agency] provide[s] a no-jeopardy determination and issue[s]
an ITS, then the ITS offers a safe harbor to those who participate in the planned agency action:
Parties that comply with the terms and conditions specified in the ITS are exempted from civil and
criminal liability under the ESA for any incidental takings, and they need not seek any other
authorization or permit under the ESA.” Zeldin, 171 F.4th at 367; see also 16 U.S.C. § 1536(o)(2);
50 C.F.R. § 402.14(i)(6).
8 d. Programmatic Consultation
A formal consultation under Section 7 is also necessary for “an agency’s multiple actions
on a program, region, or other basis.” 50 C.F.R. § 402.02. This “is known as a ‘programmatic
consultation,’” under which the consulting agency may “consult on the effects of programmatic
actions, such as ‘[m]ultiple similar, frequently occurring, or routine actions,’ and proposed
frameworks ‘for future proposed actions.’” Zeldin, 171 F.4th at 367 (alteration in original) (quoting
50 C.F.R. § 402.02). The ESA’s implementing “[r]egulations recognize that such ‘multiple
actions’ might not be ready for full Section 7 consultation at the outset and may need to defer the
required Section 7 analysis until a later time.” Id. For example, the regulations contemplate
authorization of federal programs for which “incidental take resulting from any action
subsequently authorized, funded, or carried out under the program will be addressed in subsequent
section 7 consultation, as appropriate.” 50 C.F.R. § 402.14(i)(7); see also id. § 402.02 (defining
“Framework programmatic action”). Importantly, however, “neither the statute nor any applicable
regulation provides that ‘programmatic’ consultations allow the [consulting agency] to avoid the
rigorous requirements of Section 7 consultation entirely.” Zeldin, 171 F.4th at 367.
e. Section 10 Consultation
Section 10 establishes a different pathway for “private parties, states, and other nonfederal
actors.” Id. at 367–68 (first citing 16 U.S.C. § 1539(a); and then 50 C.F.R. § 402.14(i)(5)). “Under
Section 10, a nonfederal actor may obtain a permit from the [FWS or the NMFS] that allows
incidental takings to occur without subjecting the actor to liability under the ESA.” Id. at
368 (citing 16 U.S.C. § 1539(a)(1)(B)). The permit process is significant. An applicant “must
submit a conservation plan that describes the impacts of potential incidental takings, the steps the
applicant will take to minimize and mitigate those impacts, alternatives to the planned activity,
9 why the applicant is not taking those alternatives, and any other measures that the [consulting
agency] ‘may require as being necessary or appropriate.’” Id. (citing 16 U.S.C. § 1539(a)(2)(A)).
“The [consulting agency] must publish notice of the Section 10 permit application in the Federal
Register and provide opportunity for public comment.” Id. (citing 16 U.S.C. § 1539(c), (a)(2)(B)).
“And the [consulting agency] must make certain findings before they can issue a permit that allows
incidental takings, including that the takings ‘will not appreciably reduce the likelihood of the
survival and recovery of the species in the wild,’ and that ‘the applicant will, to the maximum
extent practicable, minimize and mitigate the impacts of such taking.’” Id. (citing 16 U.S.C.
§ 1539(a)(2)(B)).
2. The Surface Mining Control and Reclamation Act (SMCRA)
The Court provided a more detailed summary of the SMCRA in an earlier opinion in this
case and assumes familiarity with that opinion. See Ctr. for Biological Diversity v. U.S. OSMRE,
No. 23-cv-3343, 2025 WL 1503802, at *3–4 (D.D.C. May 27, 2025), ECF No. 33. In short,
Congress enacted the SMCRA “to establish a nationwide program to protect society and the
environment from the adverse effects of surface coal mining operations.” Nat’l Mining Ass’n v.
U.S. Dep’t of the Interior, 105 F.3d 691, 693 (D.C. Cir. 1997) (quoting 30 U.S.C. § 1202(a)). The
Department of Interior’s Office of Surface Mining Reclamation and Enforcement (OSMRE)
“administers and enforces” the SMCRA. Id. (citing 30 U.S.C. § 1211(c)).
“As part of its comprehensive regulatory scheme, the SMCRA provides for federal
coordination with the states.” Coal River Mountain Watch v. U.S. Dep’t of the Interior, 146 F.
Supp. 3d 17, 20 (D.D.C. 2015). “After an interim period of direct federal regulation, states are
authorized by the [SMCRA] to assume a major regulatory role.” Nat’l Wildlife Fed’n v. Hodel,
839 F.2d 694, 701 (1988). “With the Secretary [of the Interior]’s approval, . . . state[s] [may]
10 assume[] primary responsibility for SMCRA enforcement and rulemaking.” Id. at 701. States that
have achieved this status are known as “primacy” states. Nat’l Mining Ass’n v. U.S. Dep’t of the
Interior, 70 F.3d 1345, 1347 (D.C. Cir. 1995). But the OSMRE must still ensure that these state
programs are properly administered and that violations of the SMCRA are corrected. See 30 U.S.C.
§§ 1211(c), 1267, 1271 (describing the Secretary of the Interior’s duties to oversee approved state
programs).
B. Factual Background
1. The Effects of Coal Mining
The Plaintiffs are both non-profit 501(c)(3) corporations committed to overlapping
environmental goals. See Am. Compl. ¶¶ 17–18, ECF No. 13. The Center for Biological Diversity
“works to secure a future for all species, great or small, hovering on the brink of extinction.”
Id. ¶ 17. And Appalachian Voices is “committed to protecting the land, air, and water of the central
and southern Appalachian region,” with “a focus on reducing coal mining’s impact on the region,
including to species listed under the ESA.” Id. ¶ 18. In this case, the Plaintiffs are particularly
concerned about the ways that coal mining has negatively impacted threatened and endangered
species in West Virginia, Kentucky, and Virginia. See id. ¶ 67.
The Plaintiffs allege that “coal mining activities have led to severe habitat degradation and
dramatic population declines across the ranges of the Guyandotte River crayfish, Big Sandy
crayfish, and candy darter.” Id. ¶ 70. According to the Plaintiffs, coal mining has had a particularly
negative impact on the Guyandotte River crayfish, which now survives in only two streams in
West Virginia. Id. They point to hundreds of SMCRA-related actions as evidence that “the coal
industry has a track record of chronic non-compliance with the requirements of [the] SMCRA
across the ranges of both the Guyandotte River crayfish and Big Sandy crayfish.” Id. ¶ 73. Both
11 species of crayfish, as well as the candy darter, are listed as endangered or threatened under the
ESA. See id. ¶ 69; FWS_36633–34, ECF No. 52.
2. The 2020 Biological Opinion
The OSMRE’s implementation of its regulatory program for overseeing surface coal
mining and reclamation operations has been subject to several ESA Section 7 consultations over
the past thirty years, including in 1996 and 2016. FWS_36606–07. The consultation at issue here
occurred in 2020, when the OSMRE requested that the FWS review its continued implementation
of the SMCRA, including its “direct implementation and enforcement” of SMCRA regulations “in
Federal program States and on Indian lands” and its “oversight of State regulatory programs with
primacy.” Id. With respect to the latter, the activities subject to consultation included the OSMRE’s
“oversight of State program compliance with requirements related to the protection and
enhancement of proposed or listed species and proposed or designated critical habitats.”
FWS_36605. And importantly, that oversight included “implementation of two documents
developed by [the] OSMRE in consultation with the [FWS].” Id. The first document detailed an
“SMCRA/ESA Coordination Process.” Id. And the second described a “Dispute Resolution
Process Relevant to Regulatory Authorities Coordinating SMCRA Permitting with the
USFWS.” Id.
a. Coordination Process
The Coordination Process, which was attached to the FWS’s BiOp as Appendix A,
prescribed four steps by which State regulatory authorities and the FWS would coordinate their
efforts regarding State permit issuance. First, “State regulatory authorities [would] approach the
Service as early as possible in the permit application development process to provide sufficient
time for the coordination and permit review and revision process as it relates to threatened or
12 endangered species or designated or proposed critical habitat.” FWS_36708. The State authority
would notify the FWS whenever it received complete applications to receive, renew, or
significantly revise a permit. Id. And upon request by the FWS, it would provide the Service with
any “fish and wildlife resources information in the permit application, as well as the fish and
wildlife protection and enhancement plan.” Id.
Second, the State authority would, “based upon [its] discretion,” provide the FWS with
“fish and wildlife resource information” necessary to facilitate the FWS’s “timely and efficient
review” of each permit application. Id. “[I]n most instances,” this information would include a
description of the action under consideration that addressed: “the areas to be disturbed by mining
activities”; “any listed or proposed species or designated critical habitat that may be affected by
the action”; the actions the operator and applicant would take to “minimize disturbance and adverse
impacts on fish and wildlife,” including on “listed or proposed species and designated critical
habitat”; and the actions proposed by the permit applicant “to enhance fish, wildlife and related
environmental values, where practicable.” FWS_36708–09.
Third, the FWS would review the materials provided, notify the State if any additional
information was needed, and evaluate “the State regulatory authority’s written findings that the
exploration, mining, and reclamation activities [would] not jeopardize the continued existence of
an endangered or threatened species.” FWS_36709. “If, in close coordination with the regulatory
authority, the Service and the State regulatory authority determine[d] there [was] a need for
additional species-specific protective measures (SSPMs), including reporting and monitoring, the
Service and the State regulatory authority [would] develop SSPM[s] to minimize anticipated
incidental take.” Id. “If no additional SSPMs [were] required, the Service [would] provide the
State regulatory authority with written confirmation that the technical assistance process ha[d]
13 been successfully completed.” Id. If, however, the FWS “unilaterally suggest[ed] additional
SSPMs” that the State regulatory did not accept, the State would explain why it rejected those
measures and the Service and the State would attempt to resolve the issue through the Dispute
Resolution Process described below. FWS_36709–10.
Fourth, and finally, the State regulatory authority would “issue a written notification to the
Service of its decision to approve or deny an application for a permit if the Service filed comments
or objections to the permit application.” FWS_36710. And “[b]efore approving any permit
application that may affect proposed or ESA-listed species or designated critical habitat, the State
regulatory authority [would] make a finding that ‘[t]he operation would not affect the continued
existence of endangered or threatened species or result in destruction or adverse modification of
their critical habitats, as determined under the [ESA].’” Id. (third and fourth alterations in original).
b. Dispute Resolution Process
The Dispute Resolution Process, which was attached to the FWS’s BiOp as Appendix B,
was designed to resolve disagreements that arose in step three of the Coordination Process about
what measures might be necessary “to minimize disturbances and adverse impacts” on species or
habitats caused by permitted activity. FWS_36711. The Dispute Resolution Process provided a
four-level “elevation process” if the State regulatory authority and the FWS could not agree on
measures that the FWS had recommended. In short, the dispute could be elevated: first, to an
OSMRE Field Office Director; second, to OSMRE and FWS Regional Directors; third, to OSMRE
and FWS Headquarters; and fourth, to the Secretary of the Interior. FWS_36712–13. At each stage
in the elevation process, the FWS officials involved would propose a resolution to the dispute. And
at each stage, the State would retain the authority to reject the proposed resolution. This was true
even at level four, where the State could either “require implementation of the proposed resolution”
14 offered by the Secretary of the Interior or “reject the proposed resolution and approve the permit.”
FWS_36713. At that point, the Dispute Resolution Process specified that “[f]urther elevations
[would] not be available.” FWS_36713.
c. Jeopardy Determination
In reviewing the OSMRE’s proposed action, the FWS ultimately concluded that the
OSMRE’s implementation of the SMCRA “through its existing regulations [was] not likely to
jeopardize the continued existence of proposed or listed species and or destroy or adversely modify
designated or proposed critical habitat.” FWS_36682. In reaching that conclusion, the FWS relied
on the additional protections that it believed would be provided by the Coordination and Dispute
Resolution Processes. It noted that “[i]mplementation of the performance standards required by
the SMCRA, on their own, [would] not necessarily eliminate adverse effects on ESA-proposed
and listed species and designated and proposed critical habitat.” FWS_36670. But the FWS found
that the Coordination Process would enable it to provide State regulatory authorities with
“additional site-specific and species-specific protective measures, monitoring, and reporting
recommendations to further enhance the protection of listed or proposed species or designated or
proposed critical habitat.” Id. And it concluded that the “OSMRE’s commitment to exercise its
oversight authority to resolve any issues that arise between regulatory authorities and the Service
further suggest[ed]” that adverse effects to ESA-protected species and habitats would be
“adequately minimized.” Id.
The FWS left it to subsequent technical assistance and coordination to address issues that
might otherwise be addressed during a standard Section 7 consultation. It concluded, for example,
that “it [was] not feasible, nor [was] it required, to conduct a meaningful site-specific and species-
specific effects analysis” in the BiOp. FWS_36662. This was because the SMCRA’s program was
15 “essentially nationwide” and “detailed information on the specific size, scope, and operation of
future mining activities” that might be permitted under the program was not available. Id. Instead,
the FWS noted that “site-specific and species-specific information [would] be available and
assessed through the technical assistance process.” Id.; see also FWS_36680.
d. Incidental Take Statement
The FWS took a similar approach in the ITS accompanying the BiOp. The Service noted
that “the paucity of information regarding future mining projects . . . available at the time of [the]
programmatic consultation [did] not allow the Service to identify the specific locations in which
future mining projects [would] occur, the specific activities associated with a particular mining
permit, and the number of individuals that might be affected by such activities in order for the
Service to conduct species and site-specific analyses.” FWS_36684. Accordingly, the ITS
provided that “[f]or proposed mining activities” in primacy states where “incidental take of ESA-
listed species [was] reasonably certain to occur, the amount and extent of incidental take
anticipated from [those] proposed actions [would] be quantified by the Service and evaluated on a
project-specific basis through the SMCRA Coordination Process.” Id. Consistent with this
approach, the ITS itself did not quantify or estimate a specific amount of incidental take that would
be permitted. FWS_36684–85.
The ITS nonetheless provided that the “OSMRE, State regulatory authorities, and mine
operators [would] be afforded an exemption from the prohibition against take resulting from
surface mining activities subject to regulation under” the SMCRA, so long as the mining activities
complied with the BiOp and the “Reasonable and Prudent Measures and associated Terms and
Conditions” of the ITS. FWS_36685. The applicable Reasonable and Prudent Measures were that
the OSMRE would “use its authorities to minimize impacts to listed species” by “evaluating and
16 assisting States and Tribes in the administration of SMCRA regulations, and the implementation,
enforcement, and maintenance” of their approved regulatory programs. Id. And the Terms and
Conditions required that, to be exempt from Section 9’s take prohibitions, the OSMRE and State
regulatory authorities needed to engage with the FWS in accordance with the SMCRA
Coordination Process in their review and approval of permit applications. FWS_36685-86. If a
State regulatory authority disagreed about the necessity of an SSPM recommended by the FWS
and, after completing the dispute resolution process, “issu[ed] [a] permit without Service
concurrence,” the permitted action would “not be exempted” from liability under the ITS.
FWS_36686. Finally, the OSMRE would provide an “annual evaluation report to the Service” on
“any known issues implementing the technical assistance or dispute resolution process.” Id.
e. Reinitiation
The BiOp concluded by noting that, consistent with 50 C.F.R. § 402.16(a), reinitiation of
formal consultation would be required if:
1. The amount or extent of incidental take for [the BiOp was] exceeded; 2. New information reveal[ed] effects of the action that may affect listed species or critical habitat in a manner or to an extent not considered in [the BiOp]; 3. The identified action [was] subsequently modified in a manner that cause[d] an effect to the listed species or critical habitat that was not considered in [the BiOp]; or 4. A new species [was] listed or critical habitat designated that may be affected by the action identified in [the BiOp].
FWS_36687. “Potential reinitiation scenarios” could also arise if certain assumptions in the BiOp
were “proven incorrect”—e.g., about how State authorities and the OSMRE would adhere to
SMCRA regulations and would engage with the FWS through the Coordination and Dispute
Resolution Processes. Id.; see also FWS_36662–64.
17 C. Procedural Background
The Plaintiffs filed their Amended Complaint on March 4, 2024, raising three claims. See
Am. Compl. ¶¶ 133–59. First, they allege that the OSMRE and the FWS violated the ESA and its
implementing regulations by failing to reinitiate consultation, which constitutes agency action
unlawfully withheld and unreasonably delayed in violation of the Administrative Procedure Act
(APA). Id. ¶ 142 (first citing 50 C.F.R. § 402.16; and then 5 U.S.C. § 706(1)). Second, they allege
that the OSMRE violated Section 7(a)(2) of the ESA by not providing sufficient oversight for state
implementation of the SMCRA programs as required by the 2020 BiOp, thereby failing to “insure
that SMCRA-regulated mining operations will not jeopardize the continued existence of listed
species or adversely modify their critical habitat.” Id. ¶ 150 (citing 16 U.S.C. § 1536(a)(2)). And
third, they allege that the 2020 BiOp opinion is facially invalid. Id. ¶¶ 151–59 (first citing
16 U.S.C. § 1536; and then 5 U.S.C. § 706(2)(A)).
The Defendants filed certified administrative record indices on July 10, 2024, ECF No. 20,
and later provided the Court with complete certified copies of the administrative record,
ECF No. 31. In May 2025, the Court denied a motion by the Plaintiffs to supplement the
administrative record. See Ctr. for Biological Diversity, 2025 WL 1503802, at *1, ECF No. 33.
And soon after, the Court granted an unopposed motion by the Plaintiffs to hold summary
judgment briefing in abeyance pending a decision by the D.C. Circuit that the Plaintiffs expected
would bear directly on this case. See Min. Order (June 13, 2025). In February—after the
Defendants reversed their position and asked that the case proceed, see ECF No. 36—the Court
lifted the stay, Min. Order (Feb. 11, 2026).
On March 4, 2026, the Plaintiffs moved for summary judgment. Pls.’ Mot., ECF No. 42.
On March 25, 2026, the Defendants opposed and cross-moved for summary judgment, Defs.’
18 Cross-Mot., ECF No. 45, while simultaneously moving to strike declarations and exhibits that the
Plaintiffs had attached to their summary judgment motion, Mot. Strike, ECF No. 44. On March
27, 2026, the D.C. Circuit issued Center for Biological Diversity v. Zeldin, 171 F.4th 356 (D.C.
Cir. 2026), and the Parties addressed the import of that decision in their final briefs. See Min. Order
(Mar. 27, 2026). The Parties’ motions are now ripe for decision. See Pls.’ Reply & Opp’n Summ.
J., ECF No. 48; Defs.’ Reply Summ. J., ECF No. 50; Opp’n Mot. Strike, ECF No. 49; Reply Mot.
Strike, ECF No. 51.
LEGAL STANDARD
“The APA sets forth the procedures by which federal agencies are accountable to the public
and their actions subject to review by the courts.” Franklin v. Massachusetts, 505 U.S. 788, 796
(1992). The D.C. Circuit has held that ESA findings are reviewed under the APA “because the
ESA does not specify a standard of review.” Zeldin, 171 F.4th at 376 (citing Union Neighbors
United, Inc. v. Jewell, 831 F.3d 564, 574 (D.C. Cir. 2016)).
The APA requires that the Court “set aside agency action, findings, and conclusions” that
are “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.”
5 U.S.C. § 706(2)(A). The same is true of agency action undertaken “without observance of
procedure required by law.” Id. § 706(2)(D). “The question of whether agency action is arbitrary
and capricious is a legal one generally made on the administrative record and resolved on summary
judgment.” Zeldin, 171 F.4th at 376 (citing Nat’l Ass’n of Home Builders v. U.S. Army Corps of
Eng’rs, 417 F.3d 1272, 1277, 1282 (D.C. Cir. 2005)).
“It is well settled that an agency must adhere to its own regulations, and an agency action
may be set aside as arbitrary and capricious if the agency fails to comply with its own regulations.”
Id. at 376 (cleaned up). “Moreover, an agency action that ‘violates [a statute] is ‘not in accordance
19 with law’ within the meaning of [the APA].” Id. (alterations in original) (quoting Chrysler Corp.
v. Brown, 441 U.S. 281, 318 (1979)).
DISCUSSION
The Plaintiffs contend that they are entitled to summary judgment for two reasons: (1) the
2020 BiOp violates the requirements of the ESA and is thus facially invalid (Claim 3); and (2) even
if the 2020 BiOp were not deficient, the Defendants have failed to comply with its express
requirements (Claims 1 and 2). The Court agrees that the 2020 BiOp is unlawful and should be
vacated and set aside. It thus declines to consider the Plaintiffs’ alternative theories.
A. Center for Biological Diversity v. Zeldin
The Parties’ arguments substantially revolve around the import of the D.C. Circuit’s recent
decision in Zeldin. So, the Court begins by summarizing that decision. In Zeldin, the state of
Florida applied to the U.S. Environmental Protection Agency (EPA) for authority to issue certain
permits under Section 404 of “the Clean Water Act that would allow permittees associated with
building and mining projects to discharge dredged or fill material into U.S. waters.” 171 F.4th at
368. The intended permit recipients “normally would have to obtain an additional permit from the
FWS or NMFS under Section 10 of the ESA if they wished to avoid liability for incidental takings
resulting from the planned discharges.” Id. But “Florida considered that extra step ‘burdensome,’
‘time consuming[,] and resource-intensive.’” Id. (alteration in original). It thus “proposed to
‘streamline’ the ESA’s permitting process and to obtain broad, up-front ESA liability protection
for all its future CWA permittees” by having the EPA “engage in a ‘programmatic’ Section 7
consultation with the FWS” aimed at approving Florida’s application to assume Section 404
permitting authority. Id.
The EPA agreed to consider Florida’s proposal and “submitted a request for a formal
consultation with the FWS under Section 7 concerning [its] consideration of Florida’s Section 404
20 application.” Id. at 370. After completing its consultation, the FWS published a programmatic
BiOp determining “that the EPA’s approval of Florida’s Section 404 permitting application would
not jeopardize protected species or harm critical habitats.” Id. In reaching this conclusion, “the
FWS stated that it was ‘not feasible, nor [was] it required, to conduct a meaningful site-specific
and species-specific effects analysis in [the] BiOp.’” Id. (alterations in original). Instead, it found
that site-specific and species-specific effects would be sufficiently assessed and addressed through
a “technical assistance” and coordination process in which Florida would have primary
responsibility for reviewing and approving Section 404 permit applications and the FWS “would
play a largely advisory role.” Id. at 370-71.
Under the technical assistance process, Florida would receive and review material provided
by Section 404 permit applicants that included “a description of the proposed activity, the ‘specific
areas’ affected by the activity, a description of protected species and habitats in the area and ways
in which they might be affected, analysis of any cumulative effects, and other ‘relevant
information,’ including, ‘[w]hen needed, proposed project designs and . . . conservation measures
that would avoid and minimize the expected impacts to listed species and their habitats.’” Id. at 371
(alterations in original). Based on that information, Florida “would decide whether protected
species or habitats would be adversely affected if the permit were granted.” Id. The FWS,
meanwhile, would receive and review all the Section 404 permit applications (which would be
sent to the FWS by Florida) and “could . . . participate in the approval process if it chose to do so.”
Id. If, for example, the FWS “found that an application ‘may cause an adverse effect to [a]
species,’” it could require that the project “include additional protective measures or Florida
[would] reject the permit.” Id. (alteration in original). The FWS could also, “if it wished, provide
21 Florida with technical information and recommend measures that would avoid or minimize
effects.” Id. (cleaned up).
In formulating its BiOp, “[t]he FWS reasoned that the ‘assum[ed]’ coordination between
the FWS and Florida in the technical assistance program was ‘as protective as the section 7
interagency consultation process.’” Id. (second alteration in original). And based on that supposed
efficacy, the Service concluded “that Florida’s program was ‘sufficiently structured’ to avoid
jeopardy to ESA-listed species.” Id. In formulating the BiOp’s accompanying ITS, the FWS found
that “some incidental take was ‘reasonably certain’” to occur from Florida’s permitting program.
Id. But much like the effects analysis, the FWS determined that it could not estimate the incidental
take amount “because it was ‘not possible for [the] FWS to know what permits would issue and
where throughout the life of the program, let alone specific amounts of take resulting from those
permits.’” Id. at 372. “Instead, the FWS stated that Florida would estimate incidental-take amounts
on a permit-by-permit basis and that the FWS would track anticipated take amounts of listed
species on a permit-by-permit basis.” Id. The ITS further provided “that Florida (not the EPA)
would reinitiate consultation with the FWS if Florida found that its own permit-level incidental-
take estimates were exceeded.” Id. And it conferred “ESA liability protection for incidental takings
of protected species” on all permittees so long as Florida complied with the ITS and the technical
assistance program. Id.
A coalition of environmental groups filed suit alleging that the EPA’s approval of Florida’s
Section 404 permitting application was unlawful. Id. The district court granted summary judgment
in the plaintiffs’ favor, holding, among other things, “that the FWS’s BiOp and ITS must be set
aside” because they “failed to comply with applicable standards under the ESA.” Id. at 372-73. On
appeal, the D.C. Circuit affirmed, similarly concluding that both the BiOp and the ITS violated
22 critical ESA requirements. Id. at 382–83. While all three judges on the panel wrote separately to
explain their reasoning (and Judge Henderson dissented from some of the majority’s conclusions),
a majority of the Zeldin panel agreed on three points pertinent here.
First, the panel unanimously concluded that the programmatic ITS issued by the FWS
violated several Section 7 regulations. See id. at 377, 379–81. Most notably, the ITS did “not
quantify ‘the amount or extent’ of incidental take of ESA-listed species, due to an asserted
‘inability to anticipate the locations of future State 404 permit applications,’ which ‘did not allow
the [FWS] to conduct site-and species-specifi[c] analyses to estimate the number of individuals
that might be affected by the permitted activities.’” Id. at 380 (first alteration in original). Instead,
the ITS left the amount of incidental take to be quantified through the “technical assistance
process” conducted between the FWS and Florida. Id.
The Circuit viewed this as a critical error. It rejected the FWS’s explanations for why it
could not estimate an incidental-take amount, noting that the ESA requires the FWS to “use the
‘best available information’” and that the “FWS had ‘reams’ of information about protected
Florida species at its disposal” that it could have used. Id. at 380–81. The Circuit further noted that
providing an “initial estimate of ‘the amount or extent’ of incidental take is an important feature
of any ITS because that take amount triggers immediate reinitiation of consultation between the
[consulting agency] and the action agency under Section 7.” Id. at 380 (citing Am. Rivers v. FERC,
895 F.3d 32, 48-49 (D.C. Cir. 2018)). As Judge Wilkins noted in his concurrence, the “ESA
regulations mandate that the parties must monitor the impact of [an] action on protected species,
and if the amount of take exceeds the limit set forth in the ITS, ‘the Federal agency must reinitiate
consultation immediately.’” Id. at 385 (Wilkins, J., concurring) (quoting 50 C.F.R.
§§ 402.14(i)(4)–(5)). Complying with that requirement is impossible if the ITS does not even
23 estimate a take limit that can potentially be exceeded. Id. (noting that an ITS that lacks “a clear
and enforceable incidental take limit . . . violates the ESA”). The Zeldin court thus concluded that
the FWS’s failure to include such a limit in its programmatic ITS governing Florida’s permitting
program was “arbitrary and capricious” because it “openly violate[d] applicable regulations
regarding take amounts and the reinitiation of consultation.” Id. at 381. 1
Second, both Judge Pan and Judge Wilkins agreed that the BiOp approving Florida’s
permitting program was unlawful and must be set aside. See id. at 377. Judge Pan, in a portion of
her opinion not joined by the other judges, identified several reasons why the BiOp was deficient.
Chief among them was that the BiOp failed to include “a meaningful site-specific and species-
specific effects analysis,” as required by 50 C.F.R. § 402.14(g). It instead opted to have site-
specific and species-specific information “assessed through the technical assistance process.” Id.
And it left compliance with various other ESA requirements to this “technical assistance program,”
which Judge Pan found was “not ‘as protective’ as the Section 7 consultation process.” Id. Unlike
a Section 7 consultation, the technical assistance process required only that Florida “share permit
applications with the FWS” and give FWS “the option of weighing in to overturn Florida’s effects
determinations.” Id. at 377-78. The FWS then could, but was not required to, provide Florida with
technical information and “recommend[] measures that would avoid or minimize effects.”
Id. at 378. The technical assistance process also did not require that either Florida or the FWS
evaluate each Section 404 permit using “the best scientific and commercial data available,” as the
1 In explaining how the ITS fell short, Judge Pan (writing for the unanimous court) further noted that the ITS failed to “identify specific ‘reasonable and prudent measures’ to minimize the impact of incidental take,” as required by 50 C.F.R. § 402.14(i)(1)(ii). Zeldin, 171 F.4th at 380. Rather, it “(1) generally instruct[ed] the EPA, Florida, and other agencies to minimize impacts on protected species, and (2) ‘assume[d] that through technical assistance with the State,’” the FWS would help develop appropriate measures to ensure each permit minimized adverse effects and avoided placing ESA-listed species in jeopardy. Id. (emphasis in original).
24 FWS “would be required to do in carrying out a proper Section 7 consultation.” Id. (first citing
16 U.S.C. § 1536(a)(2); and then 50 C.F.R. § 402.14(g)(8)).
Considering these differences, Judge Pan concluded that the technical assistance program
was “far less demanding than what is required under Section 7.” Id And the FWS’s reliance on
that “less protective” process to ensure ESA compliance was fundamentally different from the
Service permissibly finding that the effects of later programmatic actions could be addressed by
subsequent Section 7 consultations. Id. at. 378–79. Programmatic consultations, Judge Pan noted,
“may delay but may not avoid the requirements of Section 7.” Id. at 378. After all, “[n]either the
ESA nor its implementing regulations permit the FWS to dilute the requirements of Section 7” and
replace them with a “watered-down” technical assistance procedure that “does not comport with
agency regulations or programmatic approvals.” Id. at 379.
Judge Wilkins did not join Judge Pan’s reasoning regarding the BiOp’s deficiencies but
instead emphasized simply that a BiOp cannot be compliant unless it includes an ITS that specifies
the impact of incidental taking and the amount or extent of such taking. Id. at 385 (Wilkins, J.,
concurring) (first citing 16 U.S.C. § 1536(b)(4)(i); and then 50 C.F.R. § 402.14(i)(1)(i)). In other
words, Judge Wilkins reasoned that because a BiOp requires a compliant ITS and the ITS at issue
was plainly deficient, the BiOp was also deficient and no further analyses of its deficiencies was
necessary. See id. at 384 (“[V]acatur of the Incidental Take Statement as deficient, . . . results in
vacatur of the Biological Opinion because its no jeopardy finding is dependent upon the deficient
ITS.”). Thus, the most significant way in which Judge Wilkins’ view appears to differ from Judge
Pan’s is that he found her additional analysis unnecessary to reach their shared conclusion that the
BiOp was deficient.
25 Third, and finally, Judge Pan and Judge Wilkins agreed that the unlawful agency actions
at issue needed to be set aside. Id. at 382–83. While the Zeldin majority identified four agency
actions that violated the ESA and the APA—“the BiOp, the ITS, the EPA’s failure to consult with
the NMFS, and the EPA’s approval of Florida’s permitting program” 2—they noted that “[e]ach of
those unlawful agency actions require[d] the normal remedy of vacatur.” Id. The Circuit noted that
“the deficiencies of each action [were] serious” and could not be “sufficiently explain[ed] on
remand.” Id. at 383. The FWS’s BiOp and “no-jeopardy determination,” for example, was based
on “a flawed effects analysis and inaccurate assumptions about the efficacy of the technical
assistance process.” Id. The Circuit also found that vacatur was unlikely to cause undue “disruptive
consequences” as it was prospective and would “not call into question previously issued
Section 404 permits.” Id.
B. The Current Challenge
Turning to this case, the Court finds that Zeldin controls and resolves this case in the
Plaintiffs’ favor. First, the ITS that accompanies the 2020 BiOp violates the ESA because it does
not set a clear and enforceable incidental take limit. Second, the 2020 BiOp is itself invalid because
it does not include a robust effects analysis and relies on a technical assistance coordination process
that is not as protective as Section 7 consultation under the ESA. Third, those deficiencies warrant
the normal remedy of vacatur, although in a more limited fashion than was appropriate in Zeldin.3
2 The latter two actions are not relevant here, so the Court need not address them. 3 The Parties more broadly disagree about whether non-federal entities may ever receive incidental take coverage based on a Section 7 consultation obtained by a federal agency that is not the permitting authority or if they must instead proceed under Section 10 themselves. See Pls.’ Mot. 15–21; Defs.’ Cross-Mot. 21–22. The Court declines to reach that question given its finding that the 2020 BiOp and ITS at issue are invalid.
26 In arguing otherwise, the Defendants effectively ask the Court to disregard Zeldin. And,
curiously, even post-Zeldin, they “maintain” that the Second Circuit’s decision in Cooling Water
Intake Structure Coalition v. EPA, 905 F.3d 49 (2d Cir. 2018), “was correctly decided and is
persuasive under the facts of this case.” Defs.’ Reply 3 n.1. But the Defendants do not bother to
explain how that position can be reconciled with Zeldin, which concluded that Cooling Water is
neither binding in this Circuit nor persuasive. 171 F.4th at 378 (“Cooling Water does not bind us
and its reasoning is at odds with applicable regulations and our own precedents.” (citation
omitted)); see also id. at 386–87 (Wilkins, J., concurring). The Circuit’s dim view of Cooling
Water was consistent with that of the district court in Zeldin, which found that the Second Circuit’s
decision “stands alone” and “is at odds with the statute, regulations, and caselaw.” Ctr. for
Biological Diversity, 734 F. Supp. 3d at 48. This Court agrees.
1. The 2020 ITS
The ITS attached to the 2020 BiOp suffers from the same critical deficiencies as the ITS
in Zeldin. The ITS does not quantify or even estimate the amount or extent of incidental take of
ESA-listed species that is permitted, as the ESA requires. See 50 C.F.R. § 402.14(i)(1)(i); Zeldin,
171 F.4th at 380. It instead claims an inability to provide such an estimate because of insufficient
information about where specific permitted activities might occur in the future and “the number of
specific individuals that might be affected by such activities.” FWS_36684; see also Zeldin,
171 F.4th at 380. And it therefore leaves the amount of incidental take to be quantified later
through a technical assistance process conducted by the FWS and a State regulatory authority.
FWS_36684–85; Zeldin, 171 F.4th at 380.
The Zeldin court rejected such an approach as inconsistent with the ESA. Like the ITS in
Zeldin, the 2020 ITS lacks a clear take limit that, if exceeded, can effectively trigger “immediate
27 reinitiation of consultation” as required by 50 C.F.R. § 402.14(i)(5). Zeldin, 171 F.4th at 380–81
(citing Am. Rivers, 895 F.3d at 48–49); see also id. at 385 (Wilkins, J., concurring) (noting that an
ITS “without a clear and enforceable incidental take limit . . . violates the ESA”). In addition to
this critical shortcoming, the ITS also fails to “identify specific ‘reasonable and prudent measures’
to minimize the impact of incidental take.” Id. at 380 (emphasis added) (quoting 50 C.F.R.
§ 402.14(i)(1)(ii)). It instead generally instructs the OSMRE to use its oversight “authorities to
minimize impacts to listed species.” FWS_36685. Just as in Zeldin, “[b]ecause the ITS openly
violates applicable regulations regarding take amounts and the reinitiation of consultation, it is
arbitrary and capricious” in violation of the APA. Zeldin, 171 F. 4th at 381.
2. The 2020 BiOp
The 2020 BiOp is also unlawful. As discussed earlier, Judge Pan found the BiOp in Zeldin
legally deficient because, among other reasons, it did not include a robust effects analysis as
required by 50 C.F.R. § 402.14(g), and it left that analysis and compliance with other ESA
requirements to a “technical assistance program” that was “not ‘as protective’ as the Section 7
consultation process.” Zeldin, 171 F.4th at 377. Both of those things are true here as well. 4
First, as to the effects analysis, the FWS concluded in the 2020 BiOp that “it [was] not
feasible, nor [was] it required, to conduct a meaningful site-specific and species-specific effects
analysis” in the BiOp. FWS_36662. Instead, the FWS noted “that site-specific and species-specific
4 Though Judge Pan wrote alone on this point in Zeldin, the Court finds her analysis highly persuasive. The Defendants note that the Court may not be bound by either concurring opinion in Zeldin, citing J.G.G. v. Trump, No. 25-5124, 2025 WL 3198891, at *3 (D.C. Cir. Nov. 14, 2025). Defs.’ Reply 2. But J.G.G. noted only that two concurrences in a fragmented circuit panel decision may have no “precedential effect” if they “have no meaningful points of agreement.” 2025 WL 3198891, at *3 (Pillard, Wilkins & Garcia, JJ., respecting the denial of rehearing en banc). And the Court does not read Judge Wilkins and Judge Pan as “hav[ing] no meaningful points of agreement.” Id. Either way, the Court finds both concurrences persuasive and sees no compelling reason to disregard them.
28 information [would] be available and assessed through the technical assistance process.” Id. This
is functionally identical to the approach that Judge Pan rejected in Zeldin. See 171 F.4th at 377
(“[T]he FWS did not evaluate how the approval of Florida’s permitting program would affect listed
species or critical habitat” and instead “stated in the BiOp that it was ‘not feasible, nor [was] it
required, to conduct a meaningful site-specific and species-specific effects analysis in [the]
BiOp.’” (second alteration in original)). That approach is equally problematic here.
Second, the technical assistance process outlined in the Coordination and Dispute
Resolution Processes is less protective than Section 7 consultation under the ESA. As discussed at
length above, the Section 7 formal consultation process is rigorous. See id. at 365. It requires that
the federal agency initiating consultation provide the consulting agency with a substantial amount
of information regarding all aspects of the proposed action. See 50 C.F.R. § 402.14(c)–(d). The
consulting agency is then required to conduct a detailed review of that information; to conduct, if
necessary, an on-site inspection; to evaluate the current status and environmental baseline for any
listed species or critical habitat that may be affected by the proposed action; and to assess what
effects the action might have on those species and habitats. Id. § 402.14(g). These tasks require
the consulting agency to play a direct and proactive role in reviewing each proposed action and to
thereby formulate a well-supported opinion “as to whether the action is likely to jeopardize” the
species or habitat in question. See id. § 402.14(g)– (h).
Here, the technical assistance process takes key responsibilities assigned to the consulting
agency under Section 7 (like conducting effects analyses and making a jeopardy determination)
and delegates them to state regulatory authorities to conduct in the first instance. FWS_36708–09.
It also leaves the scope of information to be provided to the FWS for each permit to “the discretion
of the State regulatory authority.” FWS_36708. Thus, the technical assistance process is less
29 protective than Section 7 and the Court agrees with Judge Pan that “[a] technical assistance process
that sets standards less protective than those prescribed by the ESA cannot displace the ESA itself.”
Zeldin, 171 F. 4th at 379.
Indeed, although the technical assistance process at issue does not suffer from all the same
deficiencies as the process in Zeldin, compare, e.g., id. at 371 (noting the FWS’s participation in
permit approval process was optional) with FWS_36709 (spelling out actions the FWS “will” take
as part of approval process), it is even less protective than the process in Zeldin in at least one key
respect. In Zeldin, the technical assistance process gave the FWS the option to overturn effects
determinations that Florida made with respect to specific permit applications. 171 F.4th at 377–78.
It also empowered the FWS to insist that a project “include additional protective measures” and,
if it did not, “Florida [would] reject the permit.” Id. at 371. Here, the Coordination and Dispute
Resolution Processes do not give the FWS such dispositive authority. Rather, even after the
Secretary of Interior has proposed that a State regulatory authority require protective measures for
a certain mining project, the State may still “reject the proposed resolution and approve the
permit.” FWS_36713.
In attempting to rebut arguments about the deficiency of the technical assistance process,
the Defendants make much of the fact that the SMCRA regulatory program at issue is not a new
program like Florida’s proposal in Zeldin. They emphasize that “states with primacy have been
appropriately following a technical assistance process mandated by the federal regulations
implementing [the] SMCRA” for “nearly five decades.” Defs.’ Reply 3–4. The 2020 BiOp
expressly acknowledges, however, that the requirements of the SMCRA, “on their own, will not
necessarily eliminate adverse effects on ESA-proposed and listed species and designated proposed
critical habitat.” FWS_36670 (emphasis added); see also FWS_36673 (“Implementation of the
30 monitoring practices associated with SMCRA, on their own, will not necessarily adequately
monitor effects on ESA-proposed and -listed species or designated and proposed critical habitat in
all cases.”). That is why the BiOp emphasizes the importance of the Coordination and Dispute
Resolution Processes—both of which were developed as part of the 2020 consultation,
FWS_36607—to ensure that the FWS can help reduce “the impacts of surface mining operations
on ESA-proposed and -listed species” and “critical habitat,” FWS_36670. And as described above,
that technical assistance process is lacking.
For all the above reasons, the Court concludes that the 2020 BiOp is arbitrary and
capricious because it lacks an effects analysis and relies on a technical assistance process that is
less protective than Section 7 consultation. 5
C. Remedies
Turning to the appropriate remedy, “[w]hen an agency’s action is unlawful, ‘vacatur is the
normal remedy.’” Zeldin, 171 F.4th at 378 (quoting Allina Health Servs. v. Sebelius, 746 F.3d
1102, 1110 (D.C. Cir. 2014)). That is because Congress has directed courts to “hold unlawful and
set aside agency action” that is “not in accordance with law.” 5 U.S.C. § 706(2)(A). Under certain
limited circumstances, a court may remand an agency’s action or decision to the agency. Am. Great
5 As noted above, Judge Wilkins agreed with Judge Pan that the BiOp in Zeldin needed to be set aside, but he reached that conclusion for a different reason. Judge Wilkins reasoned that the validity of the BiOp was so inextricably linked to the validity of its accompanying ITS that the deficient ITS rendered the BiOp deficient. See Zeldin, 171 F.4th at 384–86 (Wilkins, J. concurring) (“[V]acatur of the Incidental Take Statement as deficient, . . . results in vacatur of the Biological Opinion because its no jeopardy finding is dependent upon the deficient ITS.”). As he explained, “a clear and enforceable take limit” is necessary to enable effective monitoring of the impact of an approved federal action, and thus a consulting Service cannot conclude its consultation (and issue a BiOp) without first setting a clear take limit. Id. at 385–86 (“Neither the statute nor the regulations allow the action agency to state that take limits will be determined at a later time, and then deem Section 7 consultations finished.”). The Court agrees with Judge Wilkins’ reasoning, which provides an independent basis for finding that the 2020 BiOp is deficient.
31 Lakes Ports Ass’n v. Schultz, 962 F.3d 510, 518 (D.C. Cir. 2020). But “remand without vacatur
remains an exceptional remedy.” Id. at 519. To determine whether remand without vacatur is
appropriate, the Court must consider: (1) “the seriousness of the order’s deficiencies (and thus the
extent of doubt whether the agency chose correctly),” and (2) “the disruptive consequences of an
interim change that may itself be changed.” Allied-Signal, Inc. v. U.S. Nuclear Regul. Comm’n,
988 F.2d 146, 150–51 (D.C. Cir. 1993). The Court must also ensure that any “injunction” it issues
is “narrowly tailored to remedy the specific harm shown.” Neb. Dep’t of Health & Hum. Servs. v.
HHS, 435 F.3d 326, 330 (D.C. Cir. 2006).
In Zeldin, the Circuit held that the BiOp and the ITS were “each . . . unlawful agency
actions” that “require[d] the normal remedy of vacatur.” 171 F.4th at 382–83. In applying the
Allied-Signal factors, the Circuit held: first, that “the deficiencies of each action [were] serious and
the EPA [could] not sufficiently explain its actions on remand,” and second, that “vacatur would
not likely cause undue ‘disruptive consequences’ from ‘an interim change that may itself be
changed.’” Id. Given that the Court has identified much the same deficiencies with the BiOp and
ITS here, it sees no reason to deviate from Zeldin’s general finding that vacatur rather than remand
is appropriate for the unlawful agency actions at issue.
Even so, the Court deviates from Zeldin’s approach on vacatur in one notable way. As
discussed, the 2020 BiOp and ITS cover not just the OSMRE’s oversight of state regulatory
programs with primacy, but also the OSMRE’s “direct implementation and enforcement” of the
SMCRA “in Federal program States and on Indian lands.” FWS_36605. And the BiOp provides
different guidance for the OSMRE’s implementation of the SMCRA in states where it “retains
permitting authority” as compared to its role in overseeing the regulatory programs of primacy
States. FWS_36609. Of particular note, the BiOp’s assessment of the OSMRE’s direct permitting
32 of projects in states where it is the primary regulatory authority does not hinge on the technical
assistance process that undergirds its oversight of primacy states. Rather, the BiOp concluded that
the OSMRE’s direct permitting of mining projects was “not likely to jeopardize” ESA-protected
species or habitats because each of those projects would be covered by site-specific “step-down”
Section 7 consultations that would assess the effects of the proposed projects. FWS_36682; see
also FWS_36667 (“For OSMRE-issued permits that may affect ESA-listed species or designated
critical habitat, section 7(a)(2) consultation is required and will be performed separately.”);
FWS_36621; FWS_36629; FWS_36664; FWS_36670; FWS_36678; FWS_36680. Those
“project-specific, step-down” Section 7 consultations would also analyze and quantify “any
incidental take anticipated to occur” from “mining activities in which [the] OSMRE is the authority
issuing permits.” FWS_36684–85.
The Plaintiffs do not challenge the 2020 BiOp as it applies to the OSMRE’s direct
permitting authority. Indeed, the Plaintiffs’ facial challenge to the BiOp focuses on how the BiOp
“does not ‘insure’ that SMCRA-permitted mining activities in states with primacy are not likely
to jeopardize” ESA-protected species and habitats. Am. Compl. ¶ 157 (emphasis added). And the
specific harms that the Plaintiffs identify are in primacy states: Kentucky, Virginia, and West
Virginia. Id. ¶ 67; see also FWS_36609–10. Further, the Plaintiffs’ summary judgment motion
asks that the Court “vacate the 2020 BiOp as it applies to State-delegated SMCRA programs.”
Pls.’ Mot. 29 (emphasis added). Accordingly, the Court sees no basis for disturbing the 2020 BiOp
or its accompanying ITS as they apply to the OSMRE’s regulation of mining activities in non-
primacy states. It thus vacates and sets aside only those portions of the 2020 BiOp and the ITS that
concern the OSMRE’s oversight of primacy states. Finally, to further minimize any “disruptive
33 consequences” from this decision, the Court’s vacatur of the BiOp and ITS “is prospective and
[does] not call into question previously issued . . . permits.” Zeldin, 171 F.4th at 383.
* * *
The Court recognizes that the burdens imposed by the ESA can often be substantial. But
that is by design. As the Supreme Court has noted, “[t]he plain intent of Congress in enacting [the
ESA] was to halt and reverse the trend toward species extinction, whatever the cost.” Tenn. Valley
Auth., 437 U.S. at 184. That “is reflected not only in the stated policies of the Act, but in literally
every section of the statute.” Id. The D.C. Circuit’s recent decision in Zeldin affirms the importance
of enforcing all aspects of the ESA—even though that makes it more difficult for federal and state
actors to authorize activities, like coal mining, that may adversely affect the endangered and
threatened species that the ESA protects. Congress knowingly imposed these burdens based on its
recognition of what was at stake for our nation’s wildlife. And it is not this Court’s place to
question or ignore that policy choice.
In issuing this decision, the Court is also cognizant of the federalism concerns that underlie
the SMCRA’s regulatory scheme for coal mining. But in enacting the SMCRA, Congress did not
displace the ESA. Indeed, the Circuit faced similar concerns regarding the Clean Water Act in
Zeldin and still vacated the agency action at issue. To be clear, the Court’s decision today says
nothing about the validity of the relevant SMCRA regulations. It says only that the Defendants
may not ignore critical aspects of the ESA when administering the SMCRA.
CONCLUSION
For all these reasons, the Court grants the Plaintiffs’ Motion for Summary Judgment as to
Claim 3, ECF No. 42, and denies the Defendants’ Cross-Motion for Summary Judgment,
ECF No. 45, on that same claim. In light of this ruling, and the Court’s conclusion that it warrants
vacating and setting aside the 2020 BiOp and ITS as they apply to the OSMRE’s oversight of
34 primacy states, the Court declines to reach the merits of Claims 1 or 2 as they essentially present
alternative theories for obtaining the same relief. Moreover, because the Court’s conclusion
regarding Claim 3 is not dependent on any extra-record materials, the Court denies as moot the
Defendants’ Motion to Strike the Plaintiffs’ Extra Record Declaration and Exhibits. ECF No. 44.
A separate order will issue.
SPARKLE L. SOOKNANAN United States District Judge
Date: May 29, 2026
Related
Cite This Page — Counsel Stack
Center for Biological Diversity v. U.S. Office of Surface Mining Reclamation and Enforcement, Counsel Stack Legal Research, https://law.counselstack.com/opinion/center-for-biological-diversity-v-us-office-of-surface-mining-dcd-2026.