Centech Group, Inc. v. United States

78 Fed. Cl. 658, 2007 U.S. Claims LEXIS 317, 2007 WL 2879459
United States Court of Federal Claims·Decided October 1, 2007·No. No. 07-513C·Published·Cited by 10 cases

Opinion

[659]*659MEMORANDUM OPINION AND ORDER GRANTING PLAINTIFF’S MOTION FOR LEAVE TO FILE AMENDED COMPLAINT

WILLIAMS, Judge.

This matter comes before the Court on Plaintiffs motion for leave to amend its complaint in this bid protest. Because the proposed amended complaint clarifies the original complaint and will not prejudice any party or adversely impact the expedited schedule, leave to amend is granted.

Background and Procedural History

Plaintiff, the Centech Group, Inc., challenges the Air Force’s de facto rescission of its services contract and its decision to reopen discussions and solicit revised proposals — corrective actions the Air Force took to implement a recommendation by the Government Accountability Office (GAO) in a protest filed by Tybrin Corporation (Intervenor). This procurement was a small business set-aside, and Intervenor contended in the GAO protest that Centech failed to comply with the Limitations on Subcontracting (LOS) clause, Federal Acquisition Regulation (FAR) 52.219-14, which requires that a small business perform at least 50 percent of the labor cost using its own personnel. Although the Small Business Administration had determined that Centech complied with this clause and found Centech to be a responsible small-business offeror, GAO deemed compliance with the LOS clause to be a matter of proposal acceptability, not responsibility, and found that Centech’s proposal did not meet the 50 percent personnel requirement. In response to the GAO’s recommendation for corrective action, the Air Force issued Amendment 3 to the solicitation requesting revised proposals. All four offerors, including Centech, submitted revised proposals on July 31, 2007, and these proposals are currently being evaluated. The Air Force intends to make an award in February, 2008. Plaintiff asks this Court to reinstate its original award and declare that the Air Force’s decision to follow GAO’s recommendation and take corrective action was arbitrary and capricious.

Plaintiff filed its original complaint on July 9, 2007. Defendant filed the administrative record on July 20, 2007. Defendant and Intervenor filed motions to dismiss on August 13, 2007. Plaintiff filed an opposition to those motions on September 4, 2007, and Defendant and Intervenor responded to Plaintiff’s opposition on September 11 and 12, respectively. On September 18, 2007, the Court granted the motions to dismiss in part holding that the Court did not have jurisdiction to review GAO’s recommendation as its review is limited to agency procurement decisions under 28 U.S.C. § 1491(b). The Court denied the motions to the extent they sought dismissal on grounds of standing, justiciability, and ripeness.1 On September 25, 2007, Plaintiff moved for leave pursuant to Rule 15(a) of the Rules of the United States Court of Federal Claims (RCFC) to file an amended complaint to resolve ambiguities concerning the “intent and scope” of its claims. Pl.’s Mot. for Leave to File Am. Compl. at 1. Intervenor does not oppose granting leave to amend, but Defendant filed an opposition to this motion on September 26, 2007. Defendant also filed a motion for judgment on the administrative record on September 26, 2007, prior to the deadline of October 1, 2007.

Discussion

Under Rule 15(a), once a responsive pleading is served, “a party may amend the party’s pleading only by leave of court or by written consent of the adverse party.” RCFC 15(a). Further, leave shall be freely given when justice so requires. Id. The decision whether “to grant leave [to amend] rests within the sound discretion of the [court],” and the federal rules “strongly favor granting leave to amend.” Chisolm v. TranSouth Fin. Corp., 95 F.3d 331, 338 (4th Cir.1996) (quoting Medigen of Ky., Inc. v. Public Serv. Comm’n of W. Va., 985 F.2d 164, 167-68 (4th Cir.1993)). As the Federal Circuit has recognized:

Rule 15(a) declares that leave to amend “shall be freely given when justice so requires”; this mandate is to be heeded---If the underlying facts or circumstances relied upon by a plaintiff may be a proper [660]*660subject of relief, he ought to be afforded an opportunity to test his claim on the merits. In the absence of any apparent or declared reason — such as undue delay, bad faith or dilatory motive on the part of the movant, repeated failure to cure deficiencies by amendments previously allowed, undue prejudice to the opposing party by virtue of allowance of the amendment, futility of amendment, etc. — the leave sought should, as the rules require, be “freely given.”

Te-Moak Bands of Western Shoshone Indians v. United States, 948 F.2d 1258, 1260 (Fed.Cir.1991) (quoting Foman v. Davis, 371 U.S. 178, 182, 83 S.Ct. 227, 9 L.Ed.2d 222 (1962)). In a bid protest, the Court’s decision on whether to grant leave to amend a complaint must be informed by an additional consideration-the statutory admonition that in exercising its bid protest jurisdiction, the Court “shall give due regard to the need for expeditious resolution of the action.” 28 U.S.C. § 1491.

Defendant argues that the proposed amended complaint “adds new requests for declaratory relief and reimbursement for bid and proposal preparation costs in connection with Amendment No. 3.” Def.’s Opp. to Pl.’s Mot. for Leave to File Am. Compl. at 1. However, Defendant did not articulate what language in the proposed amended complaint is “new,” but merely cited the amended complaint at pages 1, 2,18, and 19. Presumably, Defendant’s challenges relate to the following requésts for relief in the amended complaint:

[Djeclare that the Air Force lawfully and properly awarded CENTECH the contract on April 28, 2006 under the [ARDTEAS] program pursuant to the lawfully performed source selection that the Air Force conducted ...
[Prohibit the Air Force from arbitrarily, capriciously, and illegally canceling, rescinding, recompeting, or re-awarding such contract, as the Air Force is currently doing in connection with Amendment No. 3 to the ARDTEAS Request for Proposals
[Award Plaintiff] reimbursement for bid and proposal preparation costs it had to expend in connection with being forced to compete in the illegal reaward process under RFP Amendment No. 3.
Declare that the Air Force violated federal procurement laws and acted unreasonably, arbitrarily, and capriciously by its actions complained about herein, with an Order prohibiting the Air Force from arbitrarily, capriciously, and illegally canceling, rescinding, recompeting, or re-awarding its [ARDTEAS] contract it awarded to CEN-TECH on April 28, 2006, as the Air Force is currently doing in connection with Amendment No. 3 to the ARDTEAS [RFP] ...
Preliminarily and permanently enjoin the Ah- Force from illegally allowing anyone other than CENTECH to perform the Air Force’s ARDTEAS service requirements for the stated term of the ARDTEAS contract awarded to CENTECH ...

Pl.’s Am. Compl. at 1, 2,18, and 19.

Free access — add to your briefcase to read the full text and ask questions with AI

Centech Group, Inc. v. United States, 78 Fed. Cl. 658, 2007 U.S. Claims LEXIS 317, 2007 WL 2879459 (uscfc 2007).

78 Fed. Cl. 658 (Centech Group, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Dixon v. United States
Federal Claims, 2022
Hanover Insurance Company (The) v. United States
134 Fed. Cl. 51 (Federal Claims, 2017)
Uusi, LLC v. United States
133 Fed. Cl. 263 (Federal Claims, 2017)
Smith v. United States
120 Fed. Cl. 455 (Federal Claims, 2015)
Aey, Inc. v. United States
114 Fed. Cl. 619 (Federal Claims, 2014)
Joint Venture of Comint Systems Corp. v. United States
100 Fed. Cl. 170 (Federal Claims, 2011)
Martin v. United States
96 Fed. Cl. 627 (Federal Claims, 2011)
Delpin Aponte v. United States
83 Fed. Cl. 80 (Federal Claims, 2008)
Tommaseo v. United States
80 Fed. Cl. 366 (Federal Claims, 2008)