Cellu Tissue Corp. v. Blake Equipment Co.

676 A.2d 405, 41 Conn. App. 413, 1996 Conn. App. LEXIS 245
CourtConnecticut Appellate Court
DecidedMay 21, 1996
Docket14606
StatusPublished
Cited by12 cases

This text of 676 A.2d 405 (Cellu Tissue Corp. v. Blake Equipment Co.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cellu Tissue Corp. v. Blake Equipment Co., 676 A.2d 405, 41 Conn. App. 413, 1996 Conn. App. LEXIS 245 (Colo. Ct. App. 1996).

Opinion

HEIMAN, J.

The defendant appeals from the judgment rendered in favor of the plaintiff after a trial to the court. The plaintiff cross appeals. The defendant claims that the trial court improperly (1) decided the case on a theory of negligence not raised in the complaint and (2) found that the defendant was negligent based on the facts presented at trial.1 The plaintiff asserts that the trial court improperly determined that [415]*415the plaintiff failed to sustain its burden of proof as to its breach of contract claim. We affirm the judgment of the trial court.

The following procedural facts are relevant to a resolution of this appeal. This case arose out of a two count complaint filed by the plaintiff, a tissue paper manufacturing company, against the defendant, a boiler repair company. The first count sounded in negligence, and the second count sounded in breach of contract. The plaintiff sought to recover damages from the defendant arising out of the failure of the plaintiffs boiler. The defendant filed a special defense alleging that the losses of the plaintiff were caused by the plaintiffs negligence. The trial court found the defendant 50 percent negligent and the plaintiff 50 percent contributorily negligent. The court also found that the plaintiff had not sustained its burden of proof as to its breach of contract claim. The court awarded damages to the plaintiff in the net amount of $29,036.64.

I

The defendant first claims that the trial court improperly decided the case on a theory of negligence not pleaded in the complaint, namely, the failure of the defendant to advise the plaintiff to monitor the water level of the boiler. We do not agree.

In the first count of its complaint, the plaintiff alleged that the defendant was negligent in its responsibilities regarding the repair of the malfunctioning boiler. According to the complaint: “[T]he Defendant . . . was called to the [plaintiffs] plant because it was experiencing problems with [the] boiler water level. The [defendant] was hired to repair the level controls so that the device would work correctly. The Defendant undertook the responsibility to see to it that the water level control equipment operated in a proper way and was charged with a duty to so do by virtue of the [416]*416purposes for which it was retained by the Plaintiff. . . . It was the responsibility of the Defendant to see to it that all functions of the level control of the boiler level devices were performing properly so that the type of occurrence that occurred to this boiler would not occur. That is if a low water level situation developed the devices with which the boiler was equipped would deal with them properly, and shut down the boiler. ... By reason of the Defendant’s breach of its duty that it . . . undertook to see to it that these levels properly operated in a low water level position, so as to protect the boiler and as a result of that failure by the Defendant, the Plaintiff has suffered the damages herein before set forth.” (Emphasis added.)

The trial court made the following relevant findings of fact. On Thursday, August 23, 1990, the defendant found that the water in the plaintiffs boiler was not keeping up to the proper level and concluded that the modulating motor on the boiler needed to be changed. The defendant proceeded to order a new motor. At that time, however, the defendant did not conduct the tests necessary to pinpoint the problem with the boiler because the plaintiff did not want to shut down the boiler. The defendant, however, cautioned the plaintiff to check the water level of the boiler regularly. On Friday, August 24,1990, the defendant advised the plaintiff that the new motor had arrived and could be installed on that day. The plaintiff asked the defendant to wait until Monday, August 27, 1990, to install the new motor because the plaintiff needed the boiler for production. The plaintiff monitored the boiler throughout the weekend, closely at times and not so closely at other times. On Sunday, August 26, 1990, the plaintiff discovered that water was leaking from the boiler, and a subsequent inspection revealed that serious damage had occurred to the inside of the boiler. The trial court concluded that the damage to the boiler occurred [417]*417because there was an insufficient level of water maintained in the boiler to protect it from overheating.

The trial court determined that the defendant was negligent in failing (1) to run a complete test of the boiler prior to the weekend in order to pinpoint the problem with the boiler, and (2) to advise the plaintiff in sufficiently specific language and in writing, particularly in view of the fact that a new modulating motor had been ordered and that there might be a problem with the primary water cutoff, that operation of the boiler could not be safely continued without twenty-four hour surveillance of the water level. According to the defendant, the trial court improperly determined that the defendant was negligent on the second ground because that ground was not pleaded by the plaintiff in the complaint.

“It is fundamental in our law that the right of a plaintiff to recover is limited to the allegations of [its] complaint. . . . Lundberg v. Kovacs, 172 Conn. 229, 232, 374 A.2d 201 (1977). However, [t]he modern trend, which is followed in Connecticut, is to construe pleadings broadly and realistically, rather than narrowly and technically. . . . Beaudoin v. Town Oil Co., 207 Conn. 575, 587-88, 542 A.2d 1124 (1988); Fuessenich v. DiNardo, 195 Conn. 144, 150-51, 487 A.2d 514 (1985). As long as the pleadings provide sufficient notice of the facts claimed and the issues to be tried and do not surprise or prejudice the opposing party, we will not conclude that the complaint is insufficient to allow recovery. Tedesco v. Stamford, 215 Conn. 450, 459, 576 A.2d 1273 (1990) , on remand, 24 Conn. App. 377, 588 A.2d 656 (1991) , rev’d, 222 Conn. 233, 610 A.2d 574 (1992); Giul-letti v. Connecticut Ins. Placement Facility, 205 Conn. 424, 434, 534 A.2d 213 (1987); see also Web Press Services Corp. v. New London Motors, Inc., 203 Conn. 342, 359-60, 525 A.2d 57 (1987); see also Practice Book §§ 108 and 109.

[418]*418“Furthermore, a judgment ordinarily cures pleading defects .... Tedesco v. Stamford, supra, 215 Conn. 458. The absence of a requisite allegation in a complaint that would have justified the granting of a motion to strike, however, is not a sufficient basis for vacating a judgment unless the pleading defect has resulted in prejudice.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gleason v. Durden
211 Conn. App. 416 (Connecticut Appellate Court, 2022)
Hamilton v. Gasia, No. Cv 000504690 S (Apr. 26, 2002)
2002 Conn. Super. Ct. 4954 (Connecticut Superior Court, 2002)
Maloney v. PCRE, LLC
793 A.2d 1118 (Connecticut Appellate Court, 2002)
Thames River Recycling, Inc. v. Gallo
720 A.2d 242 (Connecticut Appellate Court, 1998)
Remington Investments, Inc. v. National Properties, Inc.
716 A.2d 141 (Connecticut Appellate Court, 1998)
Fidanza v. Tdb International, No. Cv95-0128541 (Jun. 18, 1997)
1997 Conn. Super. Ct. 6327 (Connecticut Superior Court, 1997)
City of Stamford v. Szollosy, No. Cv96 0155842 S (May 28, 1997)
1997 Conn. Super. Ct. 5135 (Connecticut Superior Court, 1997)
Durkin v. Durkin
685 A.2d 344 (Connecticut Appellate Court, 1996)
Muller v. Muller
682 A.2d 1089 (Connecticut Appellate Court, 1996)
Corcoran v. Corcoran, No. Fa93-00116631 (Sep. 27, 1996)
1996 Conn. Super. Ct. 5433 (Connecticut Superior Court, 1996)
MacLean v. Town of Darien
682 A.2d 1064 (Connecticut Appellate Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
676 A.2d 405, 41 Conn. App. 413, 1996 Conn. App. LEXIS 245, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cellu-tissue-corp-v-blake-equipment-co-connappct-1996.