Celanese Corp. v. Martin K. Eby Const. Co., Inc.

620 F.3d 529, 71 ERC (BNA) 1943, 2010 U.S. App. LEXIS 19518, 2010 WL 3620231
CourtCourt of Appeals for the Fifth Circuit
DecidedSeptember 20, 2010
Docket09-20487
StatusPublished
Cited by89 cases

This text of 620 F.3d 529 (Celanese Corp. v. Martin K. Eby Const. Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Celanese Corp. v. Martin K. Eby Const. Co., Inc., 620 F.3d 529, 71 ERC (BNA) 1943, 2010 U.S. App. LEXIS 19518, 2010 WL 3620231 (5th Cir. 2010).

Opinion

JENNIFER WALKER ELROD, Circuit Judge:

At issue is whether Eby is liable as an “arranger” under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), 42 U.S.C. § 9607(a)(3), and the Texas Solid Waste Disposal Act (SWDA), Tex. Health & Safety Code § 361.344. We hold that Eby is not an arranger, and we AFFIRM the district court’s final judgment, denying recovery to Celanese, and we AFFIRM the district court’s denial of Celanese’s motion to alter that judgment pursuant to Federal Rule of Civil Procedure 59(e).

I.

The parties tried the CERCLA claim to the bench and the SWDA claim to the jury. Under SWDA, litigants are entitled to have a jury act as the fact-finder. See R.R. Street & Co. Inc. v. Pilgrim Enter., Inc., 166 S.W.3d 232, 237 (Tex.2005). In a CERCLA case, the findings of a jury are only advisory. See id. Unless otherwise indicated, the relevant facts regarding the underlying events are taken from the jury’s findings and the district court’s findings. They are uncontested on appeal.

In 1979, the Coastal Water Authority of Texas (CWA) contracted with Eby to install an underground water pipeline from Clear Lake, Texas to Bayport Marine Terminal in Harris County, Texas. The pipeline was to cross several underground pipelines, including Celanese’s methanol pipeline. To accomplish this, Eby first excavated an area to install a pipeline segment, thereby uncovering the pipelines in that area. Eby then ran its own pipeline underneath those pipelines. After installing a segment, Eby backfilled that area and repeated the process with the next segment.

While excavating the area containing Celanese’s pipeline, an Eby employee struck and damaged that pipeline with a backhoe. That employee did not know what he had struck, and there was no contemporaneous report of the incident. Neither Eby nor any of its employees knew that the work on the CWA pipeline had damaged the Celanese pipeline.

According to Celanese, “Over the years, the dented areas of the pipe deteriorated in a process known as stress corrosion cracking. Eventually, one of the cracks in the dented area penetrated the wall of the pipe, allowing methanol to leak from the pipe during each methanol transfer.” Celanese discovered the leak on October 1, 2002, when someone observed and reported a patch of dead grass at the site. Soon after discovering the leak, Celanese fixed the pipeline. Celanese also worked with state and federal agencies to clean up the site and to prevent the contamination of nearby groundwater. As of mid-Novem *531 ber 2008, Celanese had removed and disposed of over 232,028 gallons of methanol from the subsurface at the site. The exact amount of released methanol is unknown.

Celanese sued Eby under CERCLA and SWDA to recover its clean-up costs. Liability hinges on whether Eby was an arranger under those statutes. Both the jury and the district court found that “[t]he release at the Site would not have occurred but for the 1979 damage to the Celanese methanol line.” The court nonetheless held that Eby was not liable as an arranger under CERCLA or SWDA because Eby did not know that it had damaged the Celanese pipeline and because “Eby is not a person responsible for solid waste under the SWDA.” Accordingly, the court entered a take-nothing final judgment on Celanese’s claims.

Celanese filed a motion under Rule 59(e) to alter or amend that judgment, which the district court denied. Celanese timely appealed the final judgment and the denial of its Rule 59(e) motion. On appeal, Celanese contends that the common law of negligence, industry custom and practice, and Eby’s contract with the CWA “imposed on Eby the obligation to investigate what it hit in a pipeline corridor and rectify any damage.” According to Celanese, Eby “consciously disregarded” that obligation by failing to investigate the incident and is therefore liable under CERCLA and SWDA as a matter of law. Celanese does not challenge any factual findings of the district court or the jury.

II.

Because the sole issue here is whether the district court erred as a matter of law regarding arranger liability, our review is de novo. See Cox v. City of Dallas, 256 F.3d 281, 288 (5th Cir.2001) (citation omitted). Although this court generally reviews a decision on a motion to amend or alter the judgment for abuse of discretion, insofar as the decision reconsidered a question of law, our review is de novo. Elementis Chromium L.P. v. Coastal States Petroleum Co., 450 F.3d 607, 610 (5th Cir.2006) (citations omitted). Such motions “cannot be used to raise arguments which could, and should, have been made before the judgment issued and cannot be used to argue a case under a new legal theory.” Id. (citation and internal quotation marks omitted).

As a threshold matter, we find that Celanese has waived its conscious-disregard argument. Furthermore, even if the argument were not waived, Eby still would not be liable as an arranger under CERCLA or SWDA because it did not plan or take any intentional steps to release methanol from the Celanese pipeline.

A.

Celanese did not try its case before the district court on a conscious-disregard theory; thus the argumentas waived. The general rule of this court is that arguments not raised before the district, court are waived and will not be considered on appeal. See AG Acceptance Corp. v. Veigel, 564 F.3d 695, 700 (5th Cir.2009). The Joint Pretrial Order and the Verdict Form show that Celanese did not seek a finding on conscious disregard. Rather, as the Joint Pretrial Order demonstrates, Celanese tried this case on an entirely different theory — that Eby had actually known that it had struck and damaged the Celanese pipeline and then attempted to cover it up. Along the same lines, Celanese did not propose any questions to the jury regarding conscious disregard. Instead, the jury questions focus on (1) whether “the Celanese methanol line was damaged as a result of the actions of Eby in 1979,” (2) whether “Eby knew that it damaged the Celanese methanol line in 1979,” and (3) whether Eby “decided to backfill the exea *532 vation ... knowing that the 1979 damage to the Celanese methanol line could result in a leak.” 1 For this reason alone, Celanese cannot prevail.

B.

Alternatively, we hold that Celanese’s conscious-disregard allegations do not establish arranger liability under CERCLA. Congress enacted CERCLA to address the “serious environmental and health risks posed by industrial pollution,” and CERCLA “was designed to promote the ‘timely cleanup of hazardous waste sites’ and to ensure that the costs of such cleanup efforts were borne by those responsible for the contamination.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wyly v. Eichor
Fifth Circuit, 2025
Dent v. McDonough
Fifth Circuit, 2025
United States v. Nelson
990 F.3d 947 (Fifth Circuit, 2021)
Alvarado v. BP Expl & Prod
988 F.3d 192 (Fifth Circuit, 2021)
Jill Hill v. IAMAW
Fifth Circuit, 2020
David Hager v. Todd G. Rowan
903 F.3d 460 (Fifth Circuit, 2018)
PBBM-Rose Hill, Ltd. v. Comm'r of Internal Revenue
900 F.3d 193 (Fifth Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
620 F.3d 529, 71 ERC (BNA) 1943, 2010 U.S. App. LEXIS 19518, 2010 WL 3620231, Counsel Stack Legal Research, https://law.counselstack.com/opinion/celanese-corp-v-martin-k-eby-const-co-inc-ca5-2010.