CEI Enterprises, Inc. v. Professional Coating Technologies, Inc

District Court, D. New Mexico·Decided November 22, 2023·No. 1:21-cv-01212·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW MEXICO ____________________

CEI ENTERPRISES, INC.,

Plaintiff, Case No. 1:21-cv-01212-MLG-LF v.

PROFESSIONAL COATING TECHNOLOGIES, INC. and MARK WINKELMAN,

Defendants.

MEMORANDUM OPINION AND ORDER GRANTING IN PART PLAINTIFF’S MOTION TO DISMISS FOR FAILURE TO STATE A CLAIM

BACKGROUND

Plaintiff CEI Enterprises, Inc., (“CEI”) is a Tennessee corporation with its principal place of business in New Mexico. Doc. 1 at 1 ¶ 1. It manufactures asphalt-rubber blending plants and related equipment and parts. Id. at 2 ¶ 7. Professional Coating Technologies, Inc., (“PCT”) is a Texas corporation that produces asphalt emulsions used in road building to coat water pipes. Id. at 1-2 ¶¶ 2, 8. In July 2017, CEI and PCT entered into an agreement (the “2017 contract”) providing that CEI would build a “complete automated system” to “automate [PCT’s] facility to significantly increase production and sales.” Doc. 79 at 2; Doc. 19-1 at 15. The project consisted of two phases: (1) the installation of large tanks and related equipment and (2) the design, construction and installation of an automation system that would work with those tanks. Doc. 13 at 3 ¶¶ 7-8. The goods were to be shipped to and the services were to be rendered at PCT’s plant in Texas. Doc. 19-1 at 15; Doc. 1 at 1 ¶ 2. Those terms were simple enough, but in January 2018, CEI requested that PCT execute a replacement contract based on “errors” it identified in the original contract. Doc. 13 at 4 ¶ 11. PCT acquiesced to that request and an amended agreement (the “2018 contract”) was executed in New Mexico. Doc. 19-2 at 14. It contained several material modifications including price, technical specifications, and the controlling law provision.1 Doc. 13 at 4 ¶ 11; Doc. 24 at 3 ¶¶ 5, 8. PCT knew of the changes to the price and specifications but claims it was

unaware of the change to the controlling law provision. Doc. 24 at 3 ¶¶ 5-8. From January 2018 to June 2018, CEI did “very little work” towards completion of the project. Doc. 13 at 4 ¶ 13. The long delay was allegedly due to personnel changes at CEI. Id. ¶ 14. CEI then informed PCT that it “was having trouble finding people to complete the project,” so it put the burden on PCT and asked PCT to find contractors who could complete the work. Id. ¶ 15 CEI told PCT that it would credit that expense against the 2018 contract price. Id. PCT proceeded to find those contractors who could move the project forward. Id. ¶ 16. PCT has paid these contractors approximately $500,000 so far. Id. It is unclear, however, whether CEI ever credited this expense as it represented to PCT. Regardless, at the close of 2018, CEI had “made very little, if any progress on the project.” Id. ¶ 17.

Though the prospects for a successful business venture between PCT and CEI were not off to an auspicious beginning, the parties opted to enter into an additional legal agreement: PCT executed a Secured Promissory Note (the “Note”) and Guaranty.2 Doc. 1-1; Doc. 1-2. The Note had two provisions of import. First, PCT promised to pay more than $1 million to CEI. Doc. 1-1 at 1. Second, PCT released CEI from claims for damages. Id. at 4. The specific release language reads as follows:

1 Whereas the controlling law provision of the 2017 contract specified New Mexico, the 2018 contract listed Tennessee. Compare Doc. 19-1 at 14 with Doc. 19-2 at 13.

2 The Note was executed on January 22, 2019. Doc. 1-1 at 1, 4. Mark Winkelman, PCT’s Chief Executive Officer, signed the document. Id. at 4. In consideration of the foregoing and as a condition to the extension of time period for payment under the [contract], [PCT] hereby releases [CEI] from any and all claims, liabilities, obligations, counterclaims, offsets and damages of any kind, contingent or otherwise, known or unknown, and agrees (i) that [CEI] has committed to fully perform all of its obligations under the [contract], and (ii) not to assert any warranty or other claim against [CEI] thereunder or to exercise any set off against the payments due hereunder.

Id. A dispute subsequently arose regarding the purpose of the Note. PCT alleges that it executed the Note as confirmation of the remaining balance on the contract and its intention to pay that balance in exchange for CEI’s actual completion of the work. Doc. 13 at 5 ¶ 20. CEI sees it differently, alleging that the Note was executed because PCT experienced “difficulties paying for the [system] and requested CEI’s assistance in working out a formal payment schedule.” Doc. 1 at 2 ¶ 11. At any rate, the Note reflected PCT’s payment obligation to CEI in connection with the sale of the complete system. Id. at 3 ¶ 12; Doc. 1-1 at 1. At the close of 2020, CEI dispatched representatives to PCT’s plant to try and convince PCT that the project was complete. Doc. 13 at 5 ¶ 25. PCT was unpersuaded. It asserts that “[t]he automation system has never been completed and has never been functional.” Id. To date, PCT has paid $600,000 to CEI for its goods and services. Id. ¶ 26. PROCEDURAL HISTORY

On December 22, 2021, CEI filed a complaint against PCT and Winkelman after PCT failed to pay the outstanding balance on the Note by the maturity date. Doc. 20 at 2-3; see generally Doc. 1. The complaint attached the Note, the Guaranty, and a letter from CEI to PCT. Doc. 1-1; Doc. 1-2; Doc. 1-3. PCT answered on February 17, 2022, asserting various affirmative defenses and counterclaims including breach of contract, violation of the New Mexico Unfair Practices Act (“UPA”), breach of the covenant of good faith and fair dealing, and negligent misrepresentation. Doc. 13 at 2-8. PCT seeks damages in the form of lost revenue, lost business opportunities, monies paid to CEI to date, reimbursement for the monies spent by PCT on outside contractors, and attorney’s fees. Id. at 6 ¶¶ 27, 33-34. CEI now moves to dismiss PCT’s counterclaims, asserting that the terms of the Note release CEI from liability under the counterclaims; the terms of the contract bar relief due to the limited warranty clause, the thirty-day inspection period, the

integration clause, and the election of Tennessee law as controlling; and the non-contractual counterclaims are barred by the economic loss rule. Doc. 20 at 6-19. PCT responded in opposition, attaching an affidavit from Winkelman, Doc. 24-1 at 1-6, the 2017 and 2018 contracts, id. at 7-36, an email from CEI to PCT relating to the purpose of the 2018 contract, id. at 37, an email from Astec to PCT showing a “punch list,” id. at 38, the punch list, id. at 39-47, and the Note. Id. at 48- 51. DISCUSSION

I. The controlling law provision in the 2018 contract supersedes the controlling law provision in the 2017 contract.

Free access — add to your briefcase to read the full text and ask questions with AI

CEI Enterprises, Inc. v. Professional Coating Technologies, Inc, (D.N.M. 2023).

CEI Enterprises, Inc. v. Professional Coating Technologies, Inc (CEI Enterprises, Inc. v. Professional Coating Technologies, Inc) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Neitzke v. Williams
490 U.S. 319 (Supreme Court, 1989)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Sutton v. Utah State School for the Deaf & Blind
173 F.3d 1226 (Tenth Circuit, 1999)
Issa v. Comp USA
354 F.3d 1174 (Tenth Circuit, 2003)
Smith v. United States
561 F.3d 1090 (Tenth Circuit, 2009)
Gallagher v. Shelton
587 F.3d 1063 (Tenth Circuit, 2009)
Kristen Cox MORRISON v. Paul ALLEN Et Al.
338 S.W.3d 417 (Tennessee Supreme Court, 2011)
Lyons v. Farmers Insurance Exchange
26 S.W.3d 888 (Court of Appeals of Tennessee, 2000)
Torres v. State
894 P.2d 386 (New Mexico Supreme Court, 1995)
Utah International, Inc. v. Caterpillar Tractor Co.
775 P.2d 741 (New Mexico Court of Appeals, 1989)
Maxey v. Quintana
499 P.2d 356 (New Mexico Court of Appeals, 1972)
Beenken v. Chicago and Northwestern Railroad Co.
367 F. Supp. 1337 (N.D. Iowa, 1973)
Guidance Endodontics, LLC v. Dentsply International, Inc.
749 F. Supp. 2d 1235 (D. New Mexico, 2010)
Farmers Alliance Mutual Insurance v. Naylor
480 F. Supp. 2d 1287 (D. New Mexico, 2007)
Fiser v. Dell Computer Corporation
2008 NMSC 046 (New Mexico Supreme Court, 2008)