CEI Engineering Associates, Inc. v. Elder Construction Co.

306 S.W.3d 447, 2009 Ark. App. 259, 2009 Ark. App. LEXIS 312
CourtCourt of Appeals of Arkansas
DecidedApril 8, 2009
DocketCA 08-601
StatusPublished
Cited by9 cases

This text of 306 S.W.3d 447 (CEI Engineering Associates, Inc. v. Elder Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CEI Engineering Associates, Inc. v. Elder Construction Co., 306 S.W.3d 447, 2009 Ark. App. 259, 2009 Ark. App. LEXIS 312 (Ark. Ct. App. 2009).

Opinion

COURTNEY HUDSON HENRY, Judge.

| , Appellant CEI Engineering Associates, Inc., (CEI) appeals an order of the Washington County Circuit Court denying its motion to compel arbitration of claims asserted against it by appellee Elder Construction Company (Elder). After first finding that some of Elder’s claims were subject to arbitration and allowing Elder time to amend its complaint, the trial court ultimately found that all of Elder’s claims sounded in tort and were thus not subject to arbitration under the Arkansas Uniform Arbitration Act (AUAA). 1 On appeal, CEI concedes that two counts of Elder’s amended complaint present legitimate tort ^claims, which are not suitable for arbitration. We agree that those claims sound in tort, and we affirm the trial court’s ruling as to those two claims. CEI argues, however, that Elder’s remaining five claims sound in contract and are, therefore, subject to arbitration. We find merit in this argument and reverse and remand for the entry of an order compelling arbitration of these claims.

In 2005, Elder engaged CEI to perform engineering services in connection with six construction projects that are referred to as Fox Creek, Sagefield, Chester, Hidden Lake, Avignon Court, and Glenstone. The parties’ agreement is contained in separate proposals submitted by CEI for each project. The proposals incorporated by reference a document entitled “Standard Terms and Conditions,” which contained the following provision:

DISPUTE RESOLUTION
Client and CEI agree to attempt to settle all claims, disputes or controversies arising out of, or in relation to the interpretation, application or enforcement of the Agreement by direct discussions; however, absent resolution by direct discussions, they agree to attempt to settle disputes by formal mediation according to the Construction Industry Mediation Rules of the American Arbitration Association. Absent resolution by mediation, they agree to binding arbitration under the Rules of the American Arbitration Association.

On October 4, 2007, Elder filed a complaint against CEI alleging negligence, fraud, and breach-of-contract claims concerning the Fox Creek and Sagefield projects. With regard to the Fox Creek project, Elder asserted that its purchase of the property was subject to a contingency that the land had access to adequate sewage; that CEI negligently | oconcluded and advised that the property had such access; and that Elder purchased the property for $600,000 in reliance on this advice, which proved to be wrong. Elder asserted that CEI’s representative, Johnie Long, the manager of the Fox Creek Project, fraudulently concealed the fact that the property did not have access to adequate sewage and that CEI continued to perform and bill for services on the project that Elder would not have authorized had it known the facts. Concerning the Sagefield project, Elder asserted claims for breach of contract and negligence. Elder alleged that CEI breached the contract by routinely over-billing for its services; that it refused to provide copies of plans; and that it threatened to halt performance of additional services unless it was paid. Elder also alleged that CEI negligently designed plans for the use of single-barrel elliptical pipe when the project required a two-barrel pipe.

In response to the complaint, CEI filed a motion to compel arbitration in keeping with the dispute resolution provision in the agreement. The trial court held a hearing on this issue on January 22, 2008, and it denied CEI’s motion to compel arbitration of Elder’s negligence and fraud claims but granted the motion to compel arbitration with respect to the breach-of-contract claims. The trial court allowed Elder thirty days to amend its complaint to assert claims with regard to the other projects.

On February 27, 2008, Elder filed an amended complaint that deleted all express reference to claims for breach of contract. In Count I of the amended complaint, Elder asserted that CEI violated the Arkansas Deceptive Trade Practices Act (ADTPA), found |4at Arkansas Code Annotated sections 4-88-101 to -503 (Repl. 2001 & Supp.2007). In stating this claim, Elder alleged that CEI represented that it would provide services in a timely manner despite knowing that it was understaffed; that CEI failed to advise that Long would be responsible for the projects despite knowing that he was not a licensed engineer; that CEI grossly over-billed for its services on all projects except Fox Creek; that it threatened to cease work until disputed billings were paid; and that it refused to provide digital copies of plans unless Elder executed a release. Elder claimed that it was entitled to recover damages for the cost of delays occasioned by CEI’s conduct and to recoup the cost of hiring other engineers to complete the projects. In Counts II and III, Elder reasserted its negligence and fraud claims against CEI with regard to the Fox Creek project. In Count IV, Elder restated its negligence claim with respect to the Sage-field project. In Count V, Elder claimed that CEI negligently created a drainage error and performed an incorrect survey of the Hidden Lake project. In Count VI, Elder alleged that CEI negligently drew plans of the Chester project depicting a water line in an incorrect location. And finally in Count VII, Elder asserted that CEI negligently advised that an eight-acre plot in the Avignon Court project was usable and that it negligently estimated the amount of fill dirt required for that project. All of the negligence counts alleged that CEI’s actions caused a delay in finishing the projects and required Elder to hire other engineers to complete CEI’s work.

The trial court conducted a second hearing to determine whether the claims asserted by Elder in the amended complaint were subject to arbitration. Applying the decision in Terminix Int’l v. Stabbs, 326 Ark. 239, 930 S.W.2d 345 (1996), the trial court found that all of Elder’s claims involved either negligence, fraud, or a violation of the ADTPA and were not subject to arbitration under Arkansas law. The court entered a written order to that effect on May 19, 2008. This timely appeal followed.

At the outset of this appeal, CEI concedes that Elder stated tort claims of negligence and fraud with regard to the Fox Creek project. CEI’s argument on appeal, however, is that the other claims asserted by Elder, though disguised as tort claims, are in reality claims for breach of contract and that the trial court erred by not compelling arbitration as to these remaining claims.

We begin by noting that an order denying a motion to compel arbitration is an immediately appealable order. Ark. R. App. P.—Civil 2(a)(12) (2008); Showmethemoney Check Cashers, Inc. v. Williams, 342 Ark. 112, 27 S.W.3d 361 (2000). We review the trial court’s order denying a motion to compel de novo on the record. Advance Am. Servicing of Ark., Inc. v. McGinnis, 375 Ark. 24, 289 S.W.3d 37 (2008). In a de novo review, we analyze the evidence and the law without giving deference to the trial court’s rulings. Terminix Int’l Co. v. Trivitt, 104 Ark.App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Filat v. Rand
2015 Ark. App. 316 (Court of Appeals of Arkansas, 2015)
Bank of the Ozarks Inc. v. Walker
2013 Ark. App. 517 (Court of Appeals of Arkansas, 2013)
B & B Hardware, Inc. v. Fastenal Co.
688 F.3d 917 (Eighth Circuit, 2012)
Phillippy v. ANB Financial Services, LLC
386 S.W.3d 553 (Court of Appeals of Arkansas, 2011)
Advocat, Inc. v. Heide
378 S.W.3d 779 (Court of Appeals of Arkansas, 2010)
PC Scale, Inc. v. Roll Off Services, Inc.
379 S.W.3d 649 (Court of Appeals of Arkansas, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
306 S.W.3d 447, 2009 Ark. App. 259, 2009 Ark. App. LEXIS 312, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cei-engineering-associates-inc-v-elder-construction-co-arkctapp-2009.