Cecil Pond Construction Co. v. Ed Bell Investment, Inc.

864 S.W.2d 211, 1993 Tex. App. LEXIS 3004, 1993 WL 433895
CourtCourt of Appeals of Texas
DecidedOctober 28, 1993
Docket12-91-00177-CV
StatusPublished
Cited by11 cases

This text of 864 S.W.2d 211 (Cecil Pond Construction Co. v. Ed Bell Investment, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cecil Pond Construction Co. v. Ed Bell Investment, Inc., 864 S.W.2d 211, 1993 Tex. App. LEXIS 3004, 1993 WL 433895 (Tex. Ct. App. 1993).

Opinion

RAMEY, Chief Justice.

This appeal challenges the sufficiency of the evidence to support the jury findings on two affirmative defenses to a conversion suit 1 . The Appellant, Cecil Pond Construction Company, (“Pond Construction”), sued Appellees, Ed Bell Investments, Inc. (“Bell Investments”) and Federal Insurance Company (“Federal”) for Bell Investment’s taking the proceeds of certain checks owed to Pond Construction. The jury found that the defendants did redirect and appropriate checks belonging to Pond Construction, but that Pond Construction had both waived its right to certain of the cheeks and was estopped from recovering on its claim for the proceeds of all of the checks. The trial court overruled Pond Construction’s Motion for Judgment N.O.V. and entered a take-nothing judgment. With respect to Bell Investments we will reverse and render judgment as to three checks; the judgment will be affirmed with respect to Federal.

The parties to this action have a common history in the construction business. Pond Construction was incorporated and began doing business in 1981. Its president has always been Cecil Pond (“Pond”). Control and ownership of Pond Construction has changed on several occasions. We are primarily concerned with a transaction that occurred on February 24, 1987 (the “Acquisition Date”). Prior to that date, Pond Construction was wholly owned by Bell Investments, which also owned the real estate on which Pond Construction had its offices and much of the equipment used by Pond Construction in its business. On the Acquisition Date, Pond entered into an agreement with Bell Investments pursuant to which he effectively purchased all the stock of Pond Construction, as well as the related real estate and equipment mentioned above (the “Acquisition Agreement”). The Acquisition Agreement made no reference to the checks in dispute in this lawsuit.

Federal is in the business of supplying performance and payment bonds in connec *213 tion with construction contracts. Because the amount of the bond premium for construction jobs such as those involved in this action is set by law, some bonding companies, including Federal, compete by returning to their insureds a percentage of the bond premium at the conclusion of a job. This partial refund of the premium is known as a “bond dividend.” As of the Acquisition Date, three projects had been completed, and a bond dividend was expected, as follows:

Pleasant Grove High School $6,304.20
Central Baptist Church 710.40
Robert E. Lee High School 8,104.66
Total $15,119.26 2

Additionally, bond dividends were anticipated on three additional projects which were completed after the Acquisition Date:

Rains Elementary School $4,082.00
Jefferson High School 7,709.40
Jefferson Middle School 1,796.00
Total $13,587.40

These bond dividend checks constitute the subject matter of this dispute.

The named principal on the bonds issued by Federal was Pond Construction, and Pond Construction paid the premiums. Bell Investments, Pond Construction’s owner and parent corporation, supplied an agreement to indemnify Federal, as required by Federal. Pond Construction paid Bell Investments a fee for this agreement to indemnify Federal, but a fee considerably below the normal market rate for such accommodation.

The acquisition itself was handled informally. Pond negotiated on his own behalf; Bell Investments was represented by Phil Eyre (“Eyre”), at that time both a vice president of Pond Construction and a financial consultant to Bell Investments. Though an attorney drafted the three page Acquisition Agreement, no attorneys participated in the negotiations. Industry accounting practice does not require bond dividends to be treated as receivables, and neither Pond Construction nor Bell Investments reflected anticipated bond dividends as assets on their balance sheets. The Acquisition Agreement was signed by Pond and Bell Investment’s president, Ed Bell (“Bell”).

Shortly after the Acquisition Date, Federal, at Bell Investment’s request, changed the payee name on the pre-Aequisition Date bond dividend checks from “Pond Construction” to “Bell Investments”, and had forwarded the new checks to Bell Investments. The three post-Acquisition Date checks were also eventually made payable and paid solely to Bell Investments.

Pond Construction soon thereafter brought this action for conversion. 3 In addition to generally denying the allegations, Bell Investments and Federal pled waiver and es-toppel as affirmative defenses. The jury’s relevant responses to-the fifteen special issues are summarized as follows:

1) Bell Investments “cashed five (5) bond checks that belonged to Cecil Pond Construction Company after February 24, 1987, in the total sum of $26,312.60,” but without conscious disregard for Pond Construction’s rights. (Jury Question No. 1)
2) Federal reissued two checks originally payable to Pond Construction to Bell Investments and delivered three cheeks to Bell Investments jointly payable to Bell Investments and Pond Construction, in amounts totalling $26,312.60, but without conscious disregard for Pond Construction’s rights. (Jury Question No. 2)
3) Pond Construction waived its right to receive bond dividend payments from Bell Investments for the jobs completed before the Acquisition Date, but not for the post-Acquisition Date jobs. (Jury Questions Nos. 6 and 7)
4) Similarly, Pond Construction waived its right to receive bond dividend payments from Federal for the pre-Acquisition *214 Date jobs, but not for the post-acquisition Date jobs. (Jury Questions Nos. 10 and 11)
5) Pond Construction is estopped from receiving any bond dividends with respect to both Bell Investments and Federal. (Jury Questions Nos. 8, 9, 12, and 13)

Pond Construction raises four points of error in this appeal, each of which challenges the sufficiency of the evidence supporting Bell Investments’ affirmative defenses of waiver and estoppel. Pond Construction claims in its first point that the trial court erred in not granting its motion for judgment, which was made after it rested, but before Bell Investments had presented its evidence. The trial court treated this as a motion for directed verdict and denied it. This motion was premature. Pond Construction’s first point of error is therefore overruled.

Pond Construction’s second point of error asserts that the trial court erred in failing to grant its motion for Judgment N.O.V., because as a matter of law, it was entitled to prevail on the record. The motion asserted that there was no evidence to support the jury findings of waiver and estoppel. The third point of error claims that that the evidence was factually insufficient to support the jury findings of waiver and estoppel.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stearns v. Martens
476 S.W.3d 541 (Court of Appeals of Texas, 2015)
Van Independent School District v. Scott A. McCarty
162 S.W.3d 254 (Court of Appeals of Texas, 2003)
McLure v. Tiller
63 S.W.3d 72 (Court of Appeals of Texas, 2002)
Robinson v. Robinson
961 S.W.2d 292 (Court of Appeals of Texas, 1997)
Enserch Corp. v. Rebich
925 S.W.2d 75 (Court of Appeals of Texas, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
864 S.W.2d 211, 1993 Tex. App. LEXIS 3004, 1993 WL 433895, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cecil-pond-construction-co-v-ed-bell-investment-inc-texapp-1993.