Cearfoss Brothers v. Harvey Harris

Court of Appeals for the Fourth Circuit·Decided July 23, 1997·No. 96-1042·Unpublished

Opinion

UNPUBLISHED

UNITED STATES COURT OF APPEALS

FOR THE FOURTH CIRCUIT

UNITED STATES OF AMERICA, for the use and benefit of PCC Construction Components, Incorporated; PCC CONSTRUCTION COMPONENTS, INCORPORATED, Plaintiffs,

v.

HARVEY HARRIS CONTRACTORS, INCORPORATED; JAMES W. ANCEL, INCORPORATED, HARTFORD ACCIDENT No. 96-1042 AND INDEMNITY COMPANY; HARRIS/ANCEL JOINT VENTURE II, Defendants-Appellees,

v.

CEARFOSS BROTHERS CONSTRUCTION COMPANY, INCORPORATED, a/k/a Cearfoss Brothers Company, Incorporated, Third Party Defendant-Appellant.

Appeal from the United States District Court for the Eastern District of Virginia, at Alexandria. Leonie M. Brinkema, District Judge. (CA-95-123-A)

Argued: June 3, 1997

Decided: July 23, 1997

Before RUSSELL, MURNAGHAN, and MOTZ, Circuit Judges.

Affirmed by unpublished per curiam opinion.

COUNSEL

ARGUED: Robert Anthony Klimek, Jr., KLIMEK, KOLODNEY & CASALE, P.C., Washington, D.C., for Appellant. Roger Cavenaugh Jones, HUDDLE & JONES, P.C., Columbia, Maryland, for Appellees . ON BRIEF: Karen Chalmers Coe, KLIMEK, KOLODNEY & CASALE, P.C., Washington, D.C., for Appellant.

Unpublished opinions are not binding precedent in this circuit. See Local Rule 36(c).

OPINION

PER CURIAM:

Harris/Ancel Joint Venture II (Harris/Ancel) obtained a contract with the National Park Service for the rehabilitation of a maintenance yard near National Airport. After being awarded the contract, Harris/ Ancel subcontracted with Cearfoss Brothers Construction Company, Inc. (Cearfoss) to supply and to erect seven preengineered buildings and one preengineered building owned by the National Park Service. The subcontract provided for progress payments. Payment by the National Service to Harris/Ancel was a condition precedent to Harris/ Ancel's obligation to pay Cearfoss.

After completing some of the work, Cearfoss requested payment from Harris/Ancel. Harris/Ancel refused to pay Cearfoss stating that Cearfoss had failed to comply with the contractual conditions for payment . Thereafter, Cearfoss walked off the job, and Harris/Ancel terminated Cearfoss' subcontract for default. Subsequently, Cearfoss sued Harris/Ancel for damages. The district court concluded that Cearfoss had failed to comply with the terms of the contract and entered judgment in Harris/Ancel's favor.

I.

FACTS AND PROCEDURAL HISTORY

The National Park Service awarded a contract to Harris/Ancel Joint Venture II1 (Harris/Ancel) for the construction of the George Washington Memorial Parkway Maintenance Center (hereinafter "the Project "). The Project required the installation of seven prefabricated metal buildings, which the Prime Contract specified were manufactured by Star Building Systems (Star).

On October 11, 1993, Harris/Ancel entered into a further subcontract with Cearfoss Brothers Construction Company, Inc. (Cearfoss), a local distributor for Star.2 Cearfoss' subcontract was for a fixed amount of $676,000.00. Article 5 of the subcontract provided:

5. PRICE AND PAYMENT

The Subcontract price shall be paid in partial payments, when received by the Contractor from the Owner, to the Subcontractor for payment of work in place and material on jobsite. Payment from the Owner is a specific condition precedent to the Contractor's obligation to pay the Subcontractor ...*** The Contractor is entitled to proof of payment for labor, material and services used before payment is due *** The Subcontractor shall itemize the Subcontract price as a basis for establishing value of work complete, and partial payments. Subcontractor agrees that it will not be paid by the Contractor for work and materials in place until ten (10) days after the Contractor's receipt of payment from the Owner. If the Contractor withholds making payment to the Subcontractor until the Subcontractor has complied with the aforesaid terms and conditions, the Subcontractor shall still diligently proceed with the work as required.

1 James W. Ancel, Inc. entered into a partnership with Harvey Harris Contractors, Inc. to form the joint venture. 2 In turn, Cearfoss subcontracted the majority of its work to material suppliers, Star, and labor subcontractors, such as PCC Construction Components, Inc. (PCC), a plaintiff in the action below.

On March 28, 1994, by letter addressed to Star, Harris/Ancel, Cearfoss , and Star entered into a "Joint Check Agreement" whereby the parties agreed that Harris/Ancel would issue a joint check payable to Cearfoss and Star. The letter directed Star to provide invoices for work and materials on or about the 25th of each month. The invoices were to be provided concurrently by Star to both Harris/Ancel and Cearfoss.

On August 29, 1994, Cearfoss submitted an Application and Certificate for Payment. Harris/Ancel returned the Application unpaid to Cearfoss stating that Cearfoss' Application was submitted too late to receive payment, and additionally, Cearfoss had failed to provide "any back-up for the monies invoiced." On September 23, 1994, Cearfoss resubmitted its Application and Certificate for Payment in the amount of $422,244.00. On October 14, 1994, Harris/Ancel informed Cearfoss that it would not pay the invoice and listed the following reasons: (1) Cearfoss had failed to provide a certified payroll of its workers; (2) Cearfoss had failed to provide a certificate of insurance as required by Article 363 of the subcontract; (3) the exterior wall panels had not been installed; (4) Cearfoss' refusal to clean oil spills created by it; (5) Harris/Ancel's purchase of materials and provision of "front monies" to enable the project to proceed; (6) the presence of deteriorated materials; (7) Cearfoss' failure to provide additional manpower on site; and (8) Cearfoss' failure to provide an on-site superintendent. As a result in its October 17, 1994, requisition to National Park Service (the Owner), Harris/Ancel did not include any sums for the account of Cearfoss. On October 19, 1994, Harris/Ancel acknowledged receipt of Cearfoss' certified payroll report, but its position on payment to Cearfoss remained unchanged.

On October 20, 1994, Cearfoss advised Harris/Ancel that unless Cearfoss received payment of the $422,244.00 immediately, Cearfoss

3 Article 36 provides:

This subcontract must be executed by the Subcontractor and returned to the Contractor within fifteen (15) days of its receipt by the Subcontractor. Until the subcontract is executed and returned to the Contractor, along with any required bonds and Certificates of Insurance, the Contractor has a right to withhold any payment due the Subcontractor.

would cease all work on the Project effective the next day.4 By letter, dated October 21, 1994, Harris/Ancel took strong exception to Cearfoss ' threat to cease work on the Project, and advised Cearfoss that any such stoppage would be considered a breach of the contract, and Harris/Ancel would proceed to terminate the subcontract for default. True to its word, on October 21, 1994, Cearfoss ceased work on the Project.

Thereafter, on October 27, 1994, in accordance with Article 135 of the subcontract, Harris/Ancel advised Cearfoss that its subcontract would be terminated for default after the close of business on November 1, 1994. Cearfoss did not return to the Project to cure its alleged

4 Cearfoss also reported that PCC, its subcontractor, refused to deliver any more materials or to provide any further work.

5 Article 13 provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Cearfoss Brothers v. Harvey Harris, (4th Cir. 1997).

Cearfoss Brothers v. Harvey Harris (Cearfoss Brothers v. Harvey Harris) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Gadson v. Chater
60 F.3d 821 (Fourth Circuit, 1995)
Sara Lee Corporation v. Kayser-Roth Corporation
81 F.3d 455 (Fourth Circuit, 1996)