Cazales v. Lecon, Inc.

994 F. Supp. 765, 1997 U.S. Dist. LEXIS 22806, 1997 WL 840072
CourtDistrict Court, S.D. Texas
DecidedOctober 2, 1997
DocketCivil Action H-96-3659
StatusPublished
Cited by5 cases

This text of 994 F. Supp. 765 (Cazales v. Lecon, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cazales v. Lecon, Inc., 994 F. Supp. 765, 1997 U.S. Dist. LEXIS 22806, 1997 WL 840072 (S.D. Tex. 1997).

Opinion

MEMORANDUM AND ORDER

CRONE, United States Magistrate Judge.

Pending before the court is Defendant and Third-Party Defendant United States Department of Veterans Affairs’ (“the VA”) motions to dismiss for lack of subject matter jurisdiction and for failing to state a claim upon which relief can be granted, or in the alternative for summary judgment (#’s 7, 85). The VA seeks to dismiss Plaintiffs Irene Cazales, Individually and as Next Friend of Rogelio Cazales and Mayra S. Cazales, Felipe Cazales Gonzales, and Rosa Maria Fraire de Cazales’s (“the Cazaleses”) wrongful death and survival action and Le-con, Inc.’s (“Lecon”) third-party claim seeking contribution or indemnification.

Having reviewed the pending motions, the submissions of the parties, the pleadings, and the applicable law, this court is of the opinion that the United States’ motions for summary judgment should be GRANTED.

I. Background

The present ease arises from the death of Rogelio Cazales (“Rogelio”), who was electrocuted while excavating at the Houston National Veteran’s Administration Cemetery (“the cemetery”). In 1995, the VA awarded a contract to Lecon to serve as the general contractor in the expansion of the cemetery. Lecon, in turn, subcontracted work to: (1) Associated Electrical (“Associated”), the electrical subcontractor; (2) Huitt-Zollars (“Huitt”), the engineering subcontractor; and (3) Landscape Construction (“Landscape”), the landscaping subcontractor. This project included the development of 130 acres of land to hold 20,000 grave sites and other improvements, including refurbishing two well houses and related electrical equipment. One of the wells, Number Two, was located in an area in which a fence topped by barbed wire surrounded the perimeter. Before the project commenced, padlocks secured the gate to this area as well as the metal' cabinet containing the live electrical switch. Signs were posted on both the front and rear doors to the enclosure containing the electrical switch with the warning “Danger/High Voltage” printed in large letters. When the project began, Lecon asked the VA to remove its padlocks to permit Lecon to substitute its own padlocks. Clyde Rowney, the Cemetery Director, complied with Le-con’s request.

*767 Ón January 3, 1996, Charles Winward (“Winward”), the foreman of the electrical subcontractor, Associated, went to Bob Clifton (“Clifton”), the VA Resident Engineer, in an attempt to determine whether the area around Well Number Two was electrified, or “hot.” Although he was not performing his weekly safety check at the time, Clifton accompanied Winward to the switch of Well Number Two, but Winward did not have the appropriate equipment with him to test the switch. After securing a voltage tester later in the day, Winward tested the switch and determined that it was “hot.” Winward informed Clifton that the switch was electrified, but they were unable to ascertain the manner in which the power could be turned off, Winward told his boss, the electrical subcontractor’s superintendent, that the switch was “hot.” Clifton contends that on the same day he also told Dan Montana (“Montana”), the project manager for Lecon, that the switch was “hot,” and requested that Montana provide him with the “as built” plans so that it could be determined how to shut off the switch. Montana denies this. Nevertheless, a few days later, Montana provided the “as built” plans to Clifton, who passed them on to Winward. In his declaration, Winward stated that he informed Montana on January 4, 1996, as well as on other occasions, that the switch was energized.

On January. 23, 1996, Rogelio, an employee of Landscape, was operating a backhoe in an attempt to excavate for a water line at the site of the cemetery expansion. In his excavation, Rogelio uncovered a gray electrical conduit. Rogelio then went to his supervisor at Landscape to determine if the wires within the conduit were “hot.” After checking with Associated, Lecon, and Huitt, Rogelio’s supervisor advised him that the wiring had been de-energized years ago. As a result, Rogelio continued his excavation duties. When the excavation took him near the transformer at Well Number Two, he got off the backhoe to see whether the transformer was connected. Despite two warning signs cautioning “Danger/High Voltage,” Rogelio touched the transformer and was immediately electrocuted.

The underlying contract between Lecon and the VA contains several provisions addressing the respective duties and responsibilities of Lecon and the VA. At least one of these provisions transfers the primary duty of ensuring the safety of employees and other persons during the project to Lecon. Under clauses 1.42(d) and 1.43 of the contract, the VA retains an “oversight” or “policing” role with regard to safety, on the job site. These and other provisions mandate that the VA’s Contracting Officer conduct regular inspections of the work site to ensure the safety of government personnel and the public. 1 The Contracting Officer is also required to inform the contractor in writing of any imminent dangers to the public or government, personnel that he discovers.

Notably, Clifton was the only VA employee assigned to the 130-aere site, while the contractors often had in excess of thirty employees on’ the job at various locations performing different functions, making it impossible for Clifton to monitor all safety hazards constantly. In determining which areas war-' ranted the greatest attention, Clifton gave priority to areas where VA employees or visitors were likely to be found, as his spot checks were to be performed for the government’s benefit, not for that of its contractors or subcontractors. In his declaration, Clifton stated that he did not expect to find VA visitors or employees around the transformer. Clifton further indicated that he had no reason to believe that any imminent danger existed at or around the transformer.

The Cazaleses initially filed suit in probate court in Harris County, Texas, against Lecon and others, asserting negligence, wrongful death, and survival claims. Lecon, in turn, filed a third-party claim against Clifton seeking contribution and/or indemnification for his alleged negligence in causing the electrocution of Rogelio. The case was removed to federal court on October 25, 1996. On December 3, 1996, the VA was substituted for Clifton as a third-party defendant, and on *768 May 1, 1997, the Cazaleses amended their complaint to name the VA as an additional defendant.

II. Analysis

A. Summary Judgment Standard

Rule 56(c) provides that summary judgment “shall be rendered forthwith if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue of material fact and that the moving party is entitled to judgment as a matter of law.” Fed. R. Crv. P. 56(c). The party seeking summary judgment bears the initial burden of informing the court of the basis for its motion and identifying those portions of the pleadings, depositions, answers to interrogatories, admissions on file, and affidavits, if any, which it believes demonstrate the absence of a genuine issue of material fact. See Celotex Corp. v. Catrett, 477 U.S. 817, 323, 106 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re the Complaint of Ingram Barge Co.
194 F. Supp. 3d 766 (N.D. Illinois, 2016)
In Re Katrina Canal Breaches Consolidated Litigation
627 F. Supp. 2d 656 (E.D. Louisiana, 2009)
Winters v. United States
127 F. Supp. 2d 814 (S.D. Texas, 2001)
Bragg v. United States
55 F. Supp. 2d 575 (S.D. Mississippi, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
994 F. Supp. 765, 1997 U.S. Dist. LEXIS 22806, 1997 WL 840072, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cazales-v-lecon-inc-txsd-1997.