Catlin Underwriting Agencies, Ltd. v. ALLETE, Inc., d/b/a Minnesota Power, Schneider Electric USA, Inc., f/k/a Square D Company, as successor in interest to Power Distribution Services, Inc.

CourtCourt of Appeals of Minnesota
DecidedAugust 4, 2014
DocketA13-2078
StatusUnpublished

This text of Catlin Underwriting Agencies, Ltd. v. ALLETE, Inc., d/b/a Minnesota Power, Schneider Electric USA, Inc., f/k/a Square D Company, as successor in interest to Power Distribution Services, Inc. (Catlin Underwriting Agencies, Ltd. v. ALLETE, Inc., d/b/a Minnesota Power, Schneider Electric USA, Inc., f/k/a Square D Company, as successor in interest to Power Distribution Services, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Catlin Underwriting Agencies, Ltd. v. ALLETE, Inc., d/b/a Minnesota Power, Schneider Electric USA, Inc., f/k/a Square D Company, as successor in interest to Power Distribution Services, Inc., (Mich. Ct. App. 2014).

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2012).

STATE OF MINNESOTA IN COURT OF APPEALS A13-2078

Catlin Underwriting Agencies, Ltd., et al., Appellants,

vs.

ALLETE, Inc., d/b/a Minnesota Power, Respondent,

Schneider Electric USA, Inc., f/k/a Square D Company, as successor in interest to Power Distribution Services, Inc., Defendant.

Filed August 4, 2014 Affirmed Rodenberg, Judge

St. Louis County District Court File No. 69HI-CV-11-122

David S. Evinger, Emily P. Hennen, Grotefeld Hoffmann Schleiter Gordon & Ochoa, LLP, Minneapolis, Minnesota (for appellants)

Thomas J. Basting, Jr., Elizabeth M. Brama, Diane B. Bratvold, Maren F. Grier, Briggs & Morgan, Minneapolis, Minnesota (for respondent)

Considered and decided by Rodenberg, Presiding Judge; Johnson, Judge; and

Reilly, Judge. UNPUBLISHED OPINION

RODENBERG, Judge

In this subrogation action, appellants Catlin Underwriting Agencies, Ltd. and

other interested insurers (Insurers) challenge the district court’s grant of summary

judgment to respondent ALLETE, Inc., d/b/a Minnesota Power, arguing that Minnesota

Power owes tort duties to United Taconite, LLC and that genuine issues of material fact

exist as to whether Minnesota Power breached those duties. Because Minnesota Power

owes no tort duties to United Taconite, we affirm.

FACTS

The United Taconite Fairlane plant facility, located in Forbes, is a taconite mining

and processing plant previously owned by Eveleth Mines, LLC. A system of protective

relays and circuit breakers protect the plant’s electrical equipment and its personnel.

Minnesota Power is an electrical utility company that provides electrical power to the

United Taconite plant. In 1997, Eveleth Mines and Minnesota Power entered into an

agreement titled “Amended and Restated Electric Service Agreement” (ESA). When

United Taconite purchased the plant, it acquired the rights and obligations of the ESA.

Under the ESA, United Taconite is required to maintain adequate protective

equipment for the plant and is liable for the design of its equipment on its side of the

point of delivery. The point of delivery is the end of Minnesota Power’s service drop,

which is located at two switches on the transmission lines inside the plant’s substation

fence. United Taconite owns all of the equipment inside the substation plant. After

electricity is “delivered,” the current runs through two United Taconite-owned oil circuit

2 breakers and a 115-kilovolt busbar to five United Taconite-owned transformers. The

transformers reduce the voltage to 4160 volts and then distribute the electricity to the

plant.

In addition to providing electricity to the plant, Minnesota Power provided

protective-relay maintenance services in 1997, 2000, and 2004. The plant has a series of

protective relays that sense fluctuations in the electrical current and signal other devices,

including circuit breakers, to interrupt the current when necessary.

In May 1997, Minnesota Power sent a proposal to Eveleth Mines for “the

cleaning, testing, and calibrating of each [Eveleth Mines] specified relay as well as the

documenting of the ‘as found’ and ‘as left’ relay settings.” Minnesota Power offered to

provide one technician to perform the testing in the plant, with the technician relying on

Eveleth Mines electricians “to keep a supply of relays ready for test[ing].” The proposal

directed Eveleth Mines to issue a purchase order if it wanted Minnesota Power to perform

the services. In October 1997, Eveleth Mines issued a purchase order to Minnesota

Power that stated: “Minnesota Power to test and calibrate [Eveleth Mines’] protective

relays as described in 5-15-97 proposal.”

In December 1997, Minnesota Power sent a letter to Eveleth Mines describing the

work it had performed. “The work included compiling relay information, visually

checking the relays for loose parts or connections and indications of problems, cleaning

relay contacts and taconite dust from the relays, testing the relays, recording the test

results and correcting any problems that could be fixed at the time.” The letter stated that

“[a] significant number of relays were found to be providing little to no protection

3 because of bent, missing or extremely dirty contacts and other mechanical parts” and that

“[s]etting sheets were not available on many of the relays, so it could not be determined if

they were at a desirable setting.” Minnesota Power then provided a list of

recommendations to Eveleth Mines, including to “function test[] the control circuits and

associated breakers to verify that the trip circuits are functional and [to perform] load

checks, to make sure that the relays are in fact monitoring the actual load current.”

In December 2000, Minnesota Power again provided maintenance on Eveleth

Mines’ protective relays. Also in 2000, Eveleth Mines hired Minnesota Power to conduct

a “Power System Study” to analyze the plant’s “existing electrical power system

equipment and facilities for possible electrical problems.” One of the two main parts of

the study was “a relay coordination study for finding possible problems with protective

devices during fault conditions” that included “all equipment on the 4160 volt system

down through the main 480 volt static trip breakers.” Individual motor overload

protection was not addressed. The relay coordination study “indicated that all electrical

equipment (that could be verified) has some fault protection, although some fault clearing

times may be longer than desired.”

In April 2004, Minnesota Power sent another proposal to United Taconite to test

the protective relays. The “scope of services would include the cleaning, testing, and

calibrating of approximately 177 United Taconite specified relays, as well as

documentation of the ‘as found’ and ‘as left’ test results.” Minnesota Power required that

“an electrician from United Taconite be available to work with [its] technician to keep a

supply of relays available for testing in a centralized location.” In June 2004, United

4 Taconite sent a purchase order to Minnesota Power that stated: “During major shutdown

Minn[esota] Power to calibrate 177 protective relays at plant per quote from . . .

4/27/2004.”

Minnesota Power’s employee, Clark Lamppa, performed the relay testing in

August 2004. Lamppa has a two-year degree in industrial instrumentation from a

vocational college in Eveleth and began working for Minnesota Power in 1989. As a

relay technician, he tests, calibrates, and performs maintenance on Minnesota Power’s

and outside companies’ protective relay systems. As had been the case on earlier such

occasions, United Taconite and its electricians removed the relays from where they were

in the plant and delivered them to Lamppa for testing at a table in the expansion

substation of the plant. After Lamppa tested them, United Taconite electricians

reinstalled the relays.

Just over two years later, in September 2006, senior relay technicians from

Minnesota Power installed new panel protection relays on the two transmission lines.

Minnesota Power replaced the old mechanical relays with microprocessor-based relays.

In October 2006, United Taconite employees were servicing a ball mill motor that

had been sporadically shutting off.1 Specifically, the employees were working on a

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gage v. HSM ELECTRONIC PROTECTION SERVICES, INC.
655 F.3d 821 (Eighth Circuit, 2011)
Moss v. Guttormson
1996 SD 76 (South Dakota Supreme Court, 1996)
DLH, Inc. v. Russ
566 N.W.2d 60 (Supreme Court of Minnesota, 1997)
Becker v. Mayo Foundation
737 N.W.2d 200 (Supreme Court of Minnesota, 2007)
Bjerke v. Johnson
742 N.W.2d 660 (Supreme Court of Minnesota, 2007)
Gradjelick v. Hance
646 N.W.2d 225 (Supreme Court of Minnesota, 2002)
80 South Eighth Street Ltd. Partnership v. Carey-Canada, Inc.
486 N.W.2d 393 (Supreme Court of Minnesota, 1992)
Harper v. Herman
499 N.W.2d 472 (Supreme Court of Minnesota, 1993)
D & a DEVELOPMENT CO. v. Butler
357 N.W.2d 156 (Court of Appeals of Minnesota, 1984)
Funchess v. Cecil Newman Corp.
632 N.W.2d 666 (Supreme Court of Minnesota, 2001)
Bryant v. Northern Pacific Railway Co.
23 N.W.2d 174 (Supreme Court of Minnesota, 1946)
Riverview Muir Doran, LLC v. JADT Development Group, LLC
790 N.W.2d 167 (Supreme Court of Minnesota, 2010)
Domagala v. Rolland
805 N.W.2d 14 (Supreme Court of Minnesota, 2011)
Glorvigen v. Cirrus Design Corp.
816 N.W.2d 572 (Supreme Court of Minnesota, 2012)
Doe 169 v. Brandon
845 N.W.2d 174 (Supreme Court of Minnesota, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Catlin Underwriting Agencies, Ltd. v. ALLETE, Inc., d/b/a Minnesota Power, Schneider Electric USA, Inc., f/k/a Square D Company, as successor in interest to Power Distribution Services, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/catlin-underwriting-agencies-ltd-v-allete-inc-dba-minnesota-power-minnctapp-2014.