Cathedral Group v. Gen. Construction Management Co. CA4/2

CourtCalifornia Court of Appeal
DecidedDecember 9, 2013
DocketE054971
StatusUnpublished

This text of Cathedral Group v. Gen. Construction Management Co. CA4/2 (Cathedral Group v. Gen. Construction Management Co. CA4/2) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cathedral Group v. Gen. Construction Management Co. CA4/2, (Cal. Ct. App. 2013).

Opinion

Filed 12/9/13 Cathedral Group v. Gen. Construction Management Co. CA4/2

NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FOURTH APPELLATE DISTRICT

DIVISION TWO

CATHEDRAL GROUP, LTD.,

Plaintiff, Cross-defendant, and E054971 Appellant, (Super.Ct.No. INC079181) v. OPINION GENERAL CONSTRUCTION MANAGEMENT COMPANY,

Defendant, Cross-complainant, and Respondent.

APPEAL from the Superior Court of Riverside County. Randall Donald White,

Judge. Affirmed.

Hill, Farrer & Burrill, Dean E. Dennis, and Neil D. Martin for Plaintiff, Cross-

defendant, and Appellant.

Roemer & Harnik, Brian S. Harnik, and Helene P. Dreyer Koch for Defendant,

Cross-complainant, and Respondent.

1 I. INTRODUCTION

Respondent General Construction Management Company (General), a general

contractor, completed a 40-unit condominium project for appellant Cathedral Group, Ltd.

(Cathedral), a real estate developer, after another contractor left the job. The parties

signed a “Cost of the Work Plus a Fee” contract on American Institute of Architects

(AIA) Document A114 (the AIA contract). The AIA contract did not expressly authorize

General to be paid for “general conditions” expenses, but section 7.7.1 authorized

payment for “[o]ther costs incurred . . . to the extent, approved in advance in writing” by

Cathedral.

A dispute arose concerning whether the parties agreed, before they signed the AIA

contract, that General would be paid the fixed sum of $42,640 per month for its estimated

general conditions expenses, including its project-related staff time and off-site office

overhead. Cathedral claimed there was no such parol agreement: the AIA contract

governed the issue; the AIA contract did not authorize payment for any estimated general

conditions expenses; and no off-site office overhead or off-site staff time was either

identified in or compensable under the AIA contract.

General claimed the parties’ principals, Gary Covel for General and Moe Nasr for

Cathedral, agreed General would be paid $42,640 per month, its estimated general

conditions expenses, before the AIA contract was signed, and that Nasr confirmed the

agreement both in writing and by his conduct. Thus, General argued, section 7.7.1 of the

2 AIA contract, the “other costs” provision, required Cathedral to pay General the agreed

upon, fixed monthly sum for estimated general conditions expenses.

Following a bench trial, the trial court found in favor of General and awarded it

$401,035.85, plus interest, for Cathedral’s breach of the AIA contract. Among other

things, the court credited Covel’s testimony that he and Nasr agreed General would be

paid $42,640 per month for general conditions expenses, with no requirement for

“backup” documentation, and found Nasr’s testimony denying the agreement not

credible.

Cathedral asserts three claims of error on this appeal: (1) the trial court

misinterpreted the AIA contract and violated the parol evidence rule in construing section

7.7.1 as authorizing payment for General’s estimated general conditions; (2) the AIA

contract is inconsistent with and therefore precludes the court’s additional finding that

Cathedral was barred from denying the prior oral agreement based on waiver and

estoppel principles; and (3) General failed to prove its damages with competent evidence.

We interpret the AIA contract de novo and conclude, with the aid of extrinsic

evidence, including the principal’s testimony, that section 7.1.1 is reasonably susceptible

to the interpretation urged by General: it authorizes payment for General’s estimated

general conditions expenses. We also conclude substantial evidence supports the trial

court’s conclusion that the parties did in fact intend and agree that section 7.7.1 required

Cathedral to pay General $42,640 per month for general conditions expenses. We reject

Cathedral’s other claims of error and affirm the judgment in all respects.

3 II. FACTS AND PROCEDURAL HISTORY

A. Background

In 2005 and 2006, Cathedral owned a 40-unit condominium project under

construction in Cathedral City (the project). Cathedral’s principal, Moe Nasr, was the

architect on the project and had over 25 years of experience in real estate development.

The first contractor to work on the project, Gencon Construction (Gencon), agreed to

complete the project for the fixed fee of $4,435,040. Gencon’s fixed fee included an 8

percent contractor’s fee and a 5 percent fee for “general conditions.”

By late 2006, there were problems with Gencon’s work and Cathedral hired a new

general contractor, General, to complete the project. General’s principal, Gary Covel,

had over 30 years of experience as a general contractor and was familiar with AIA

contract documents. Due to the “enormous unknowns” involved in assuming the project

and correcting problems in Gencon’s work, Covel would not agree to complete the

project for a fixed sum. Instead, Covel and Nasr agreed that General would complete the

project for the costs of construction plus an 8 percent contractor’s fee.

In a “cost plus” contract arrangement, the owner has no guaranteed maximum

price protection; the owner simply agrees to pay the costs of construction plus a

contractor’s fee. The central dispute in this case is whether Cathedral agreed to pay

General a fixed monthly fee of $42,640 for estimated but undocumented general

conditions expenses in addition to the other costs of constructing the project plus an 8

percent contractor’s fee.

4 B. The Pre-AIA Contract Discussions

In September 2006, Nasr and Covel met to discuss the project before they signed

the AIA contract in December 2006. According to Nasr, he and Covel discussed and

agreed that General’s compensation would be the cost of construction, including the costs

of “general conditions” incurred on the project site (e.g., temporary utilities, water trucks,

cleaning, protection, security), plus an 8 percent contractor’s fee.

Nasr claimed the compensable “general conditions” costs included “any labor that

the contractor uses on the job,” but not the costs of General’s supervisory and other

personnel who worked on the project, or General’s off-site office overhead expenses. In

Nasr’s view, the 8 percent contractor’s fee was to cover General’s off-site overhead and

personnel expenses. Nasr denied he ever agreed to pay General a flat monthly fee or a

stipulated sum for general conditions expenses.

Covel’s testimony was at odds with Nasr’s regarding General’s compensation for

general conditions expenses and what those expenses included. According to Covel, in

September 2006, he and Nasr discussed and agreed that General would receive a fixed

fee of $42,640 “and some odd dollars” per month for general conditions. Covel testified:

“We agreed on a fixed fee. The general conditions are an estimate of the cost to the

contractor to do the work, and it’s typically a fixed fee that’s arrived at through

negotiations . . . and that’s exactly how we did this one.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Gas & Electric Co. v. G. W. Thomas Drayage & Rigging Co.
442 P.2d 641 (California Supreme Court, 1968)
Panno v. Russo
186 P.2d 452 (California Court of Appeal, 1947)
Bettelheim v. Hagstrom Food Stores, Inc.
249 P.2d 301 (California Court of Appeal, 1952)
Superior Dispatch, Inc. v. Insurance Corp. of New York
181 Cal. App. 4th 175 (California Court of Appeal, 2010)
Cedars-Sinai Medical Center v. Shewry
41 Cal. Rptr. 3d 48 (California Court of Appeal, 2006)
Utility Audit Co. v. City of Los Angeles
5 Cal. Rptr. 3d 520 (California Court of Appeal, 2003)
Founding Members of Newport Beach Country Club v. Newport Beach Country Club, Inc.
135 Cal. Rptr. 2d 505 (California Court of Appeal, 2003)
Winet v. Price
4 Cal. App. 4th 1159 (California Court of Appeal, 1992)
Casa Herrera, Inc. v. Beydoun
83 P.3d 497 (California Supreme Court, 2004)
Crestview Cemetery Ass'n v. Dieden
356 P.2d 171 (California Supreme Court, 1960)
Gould v. Corinthian Colleges, Inc.
192 Cal. App. 4th 1176 (California Court of Appeal, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Cathedral Group v. Gen. Construction Management Co. CA4/2, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cathedral-group-v-gen-construction-management-co-ca42-calctapp-2013.