Cassidy v. Eternit, Inc.

32 S.W.2d 75, 326 Mo. 342, 1930 Mo. LEXIS 679
CourtSupreme Court of Missouri
DecidedOctober 13, 1930
StatusPublished
Cited by18 cases

This text of 32 S.W.2d 75 (Cassidy v. Eternit, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cassidy v. Eternit, Inc., 32 S.W.2d 75, 326 Mo. 342, 1930 Mo. LEXIS 679 (Mo. 1930).

Opinions

Maurice J. Cassidy and Theresa C. Cassidy, father and mother, and Jean Catherine Cassidy, sister, of Maurice J. Cassidy, Jr., deceased, filed with the Workmen's Compensation Commission their claim for death benefits against Eternit, Inc., the *Page 344 employer of deceased, and Royal Indemnity Company, the insurer. A hearing on their claim before the Commission resulted in a final award of $150 for burial expenses, and a total death benefit of $13,200, or the sum of $10 per week for 660 weeks to Maurice J. Cassidy, and the sum of $10 per week for 660 weeks to Theresa C. Cassidy. The employer and insurer took an appeal to the Circuit Court of the City of St. Louis, where a judgment was entered affirming the final award of the Commission in all particulars, and from that judgment the employer and insurer have, in due course, perfected an appeal to this court.

The evidence adduced at the hearing before the Commission is substantially as follows: At the time of the accident in question, the Eternit Company was engaged in the construction of a plant in the city of St. Louis, in which it was to manufacture asbestos shingles and building products. It was acting as the general contractor and had general supervision over the construction work, but some of the work was being done by independent contractors. The Morgan Hauling Company, as an independent contractor, had the job of erecting some cranes and other machinery. The work of the Morgan Hauling Company required the services of a hoisting engineer to operate the air hoist on one of its automobile trucks. A controversy arose as to whether this hoisting engineer should be placed on the pay roll of the Eternity Company or the Morgan Hauling Company, and it was finally determined that this hoisting engineer would be paid by the Eternit Company in the same manner as the hoisting engineer who was operating the overhead crane. Under this arrangement, Maurice J. Cassidy, Jr., went to work on the morning of Friday, July 8, 1927, for wages of $1.50 per hour, or $12 per day. All workmen on this job quit work at twelve o'clock noon on the following day, Saturday, July 9th. Shortly before twelve o'clock on that day, while climbing down a ladder to the cage of the overhead crane, Cassidy came in contact with a highly charged electric wire of the overhead crane, and was thereby caused to fall, about forty feet, to his death.

P.J. Brice, representative of the Hoisting Engineers' Local, testified that Cassidy went to work as a member of the Eternit Company's crew, subject to the orders of the foreman of the Morgan Hauling Company, and was placed on the pay roll of the Eternit Company, in furtherance of an agreement to that effect.

Paul McCorkle, plant manager of the Eternit Company, testified that the independent contractors, including the Morgan Hauling Company, were doing the work on a "time and material plus basis;" that Cassidy was on the pay roll of the Eternit Company; and that the Morgan Hauling Company "got no percentage" on Cassidy's wages. *Page 345

Moody Crews, foreman of the Morgan Hauling Company, testified that Cassidy was employed by the Eternit Company, but that Cassidy was subject to his orders and directions in operating the air hoist on one of the Morgan Hauling Company's trucks. He further testified as follows:

"Direct Examination.
"Q. Mr. Crews, how long before you learned of Mister — of young Cassidy's death was it that you had seen him or talked to him? A. It was exactly nine minutes to twelve.

"Q. That was the time when you last talked to him? A. Yes, sir.

"Q. And at that time what did he say to you or what did you tell him to do, if anything? A. He came up to me and asked me what time it was and I told him, I pulled out my watch and I said, it is nine minutes to twelve, and he asked me whether he had to make any more hoists before noon or not and I told him I didn't have any, I just got through raising the posts and we had to bolt it up in its place and it would take quite a while to do that and we would not need any more before dinner. He said, `Where am I supposed to get my check at?' I told him that I didn't know whether they brought the checks around or whether he was supposed to line up at the office, so I told him to go up and see the other engineer on the other crane that is in operation and he will inform you where to get your check at.

"Cross Examination.
"Q. Had this other engineer ever told you to send to him anybody that inquired about checks? A. No, sir.

"Q. Had anybody in the employ as far as you know of the Eternit Company told you where to send men who might inquire of you where they would get their checks? A. Well, some time previous, that is, before this accident happened, there was a little argument up there about who was supposed to pay this engineer that was operating there before, but I don't know, I don't know much about this, and Mr. Morgan, I believe, had his check made out to this engineer and the Eternit people told Mr. Morgan they would pay the engineer themselves. That is all I know about it.

"Q. This was some other engineer before Maurice Cassidy? A. Yes, sir; that is why I thought I would tell him to go up and see this other engineer and he could tell him where to get his check from.

"Recross Examination.
"Q. The place where you and he were when he came to ask you about the check, where was that? A. Inside of the building, *Page 346

"Q. How close to the place where the accident occurred? A. About 250 foot, 200 foot.

"Q. Did any part of the duties that fell on Mr. Maurice Cassidy in his employment up there, take him to this crane from which he fell? A. I don't know nothing about that, only simply going up there to inquire about getting his check at twelve o'clock."

J. Paul, another hoisting engineer, was interrogated, in part, as follows:

"Direct Examination.
"Q. On July 9, 1927, were you working on this job where Mr. Cassidy was killed? A. I was.

"Q. Did you hear any conversation between him and Mr. Crews? A. Mr. Cassidy was just hoisting up a piece of iron, I believe, and I was on the air compressor for the Arthurs Ice Company. I was operating the air compressor and after Mr. Cassidy had been hoisting up this piece of iron he came over to the compressor and asked me who was going to pay him, so I told him I thought the Eternit people would pay him, and just about that time he asked Mr. Crews, and Mr. Crews told him to go up and ask the engineer up on the crane. That was just a short time before twelve o'clock and just a few minutes after that a young man came down to where I was at and said there was somebody up there all cut to pieces, so I hurried up and here he was stretched out on the platform.

"Q. You are a hoisting engineer, too? A. Yes, sir.

"Q. Do you know who hoisting engineers work for on the job? A. Well, there is several subcontractors, some of the work is being done by contract and then some of it what we call time basis.

"Q. Why did you say the Eternit people would pay Cassidy? A. I am the steward on the job and it is up to any engineer that has any grievance to come and see me and I direct him to the best of my ability to get him straightened out.

"Q. Who did you say you were working for? A. Arthurs Ice Company.

"Q. What made you think the Eternit Company would pay Cassidy? A. Well, I was talking to a heavy hauler for the Morgan Company about two weeks ago about putting an engineer on this, I think it is Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hacker v. City of Potosi
340 S.W.2d 166 (Missouri Court of Appeals, 1960)
Heaton v. Ferrell
325 S.W.2d 800 (Missouri Court of Appeals, 1959)
Snowbarger v. M. F. A. Central Cooperative
317 S.W.2d 390 (Supreme Court of Missouri, 1958)
Scharlott v. New Empire Bottling Co.
192 S.W.2d 853 (Supreme Court of Missouri, 1946)
Daugherty v. City of Monett
192 S.W.2d 51 (Missouri Court of Appeals, 1946)
Wamhoff v. Wagner Electric Corp.
190 S.W.2d 915 (Supreme Court of Missouri, 1945)
Smith v. Seaman & Schuske Metal Works Co.
127 S.W.2d 435 (Supreme Court of Missouri, 1939)
Buckner v. Quick Seal, Inc., and Lib. Mut. Ins. Co.
118 S.W.2d 100 (Missouri Court of Appeals, 1938)
State Ex Rel. F. T. O'Dell Construction Co. v. Hostetter
104 S.W.2d 671 (Supreme Court of Missouri, 1937)
Reed v. Sensenbaugh
86 S.W.2d 388 (Missouri Court of Appeals, 1935)
State Ex Rel. Probst v. Haid
62 S.W.2d 869 (Supreme Court of Missouri, 1933)
Shroyer v. Missouri Livestock Commission Co.
61 S.W.2d 713 (Supreme Court of Missouri, 1933)
Griffin v. Anderson Motor Service Co.
59 S.W.2d 805 (Missouri Court of Appeals, 1933)
Sweeny v. Sweeny Tire Stores Co.
49 S.W.2d 205 (Missouri Court of Appeals, 1932)
Sawtell v. Stern Bros. Co.
44 S.W.2d 264 (Missouri Court of Appeals, 1931)
Hohlstein Ex Rel. Hohlstein v. St. Louis Roofing Co.
42 S.W.2d 573 (Supreme Court of Missouri, 1931)
Ft. Smith Aircraft Co. v. State Industrial Commission
1931 OK 409 (Supreme Court of Oklahoma, 1931)
Leilich v. Chevrolet Motor Co.
40 S.W.2d 601 (Supreme Court of Missouri, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
32 S.W.2d 75, 326 Mo. 342, 1930 Mo. LEXIS 679, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cassidy-v-eternit-inc-mo-1930.