Case Prestressing Corp v. Chicago College of Osteopathic Medicine

455 N.E.2d 811, 118 Ill. App. 3d 782, 74 Ill. Dec. 382, 1983 Ill. App. LEXIS 2399
CourtAppellate Court of Illinois
DecidedSeptember 29, 1983
Docket82-2887
StatusPublished
Cited by34 cases

This text of 455 N.E.2d 811 (Case Prestressing Corp v. Chicago College of Osteopathic Medicine) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Case Prestressing Corp v. Chicago College of Osteopathic Medicine, 455 N.E.2d 811, 118 Ill. App. 3d 782, 74 Ill. Dec. 382, 1983 Ill. App. LEXIS 2399 (Ill. Ct. App. 1983).

Opinion

PRESIDING JUSTICE ROMITI

delivered the opinion of the court:

Third-party plaintiff-appellant George A. Fuller Company (Fuller) was the contractor on a project for Chicago College of Osteopathic Medicine (the college). Schmidt, Garden & Erikson was the architect (the architect.) After completion of the project, the college sued Fuller in Federal court for breach of contract; Fuller counterclaimed against the college for breach of contract and filed a claim against the college for breach of contract and filed a claim against the architect for causing it to suffer delay damages. Claims relating to damages suffered by subcontractors were withdrawn from the case by stipulation and demand of the college and the architect. The jury returned verdicts for all defendants on all the claims. Thereafter, one of the subcontractors filed a claim in State court against Fuller for damages resulting from being delayed in performing its subcontract work. Fuller then filed this third-party action against the college and the architect. The trial court dismissed on grounds of collateral estoppel and apparently res judicata and also indicated that it believed the third-party complaint did not state a cause of action. It denied a motion for leave to amend the complaint because of its belief that the State action was barred by the prior Federal action. We reverse, holding that the State action is not barred since the parties withdrew the claims in question and in light of the general verdict there is no specific finding upon which a holding of collateral estoppel could be based. Since it appears from the record that the trial court would otherwise have allowed the motion to amend the complaint, we remand the case to the trial court for further proceedings including the desired amendment of the complaint. However we believe that the present complaint does state a valid cause of action against the owner.

The college filed its suit in Federal court in 1975 seeking damages for Fuller’s alleged breach of construction contract. Fuller, as already noted, filed a counterclaim against the college and a third-party claim against the architect. It claimed that due to alleged breaches of the construction contract by the college and the negligent acts, errors, omissions and breaches of contract by the architect, it was delayed and hindered in its contract; and was damaged in the amount of $1,992,944. Initially, one of its claims was that due to defendants’ conduct it might be liable to subcontractors. Fuller also filed to foreclose its mechanics’ lien. Accordingly, as required by law, all other lien claimants were joined as additional counterdefendants and they, in turn, filed their lien claims. It was provided by stipulation that the claims of Fuller, the college and the architect among themselves would be tried before a jury and that thereafter the issue raised by the subcontractor claims would be tried by the court. Thereupon counsel for the college and the architect demanded that:

“I also think that some of the claims that are contained in there are some of the subcontractors’ claims which we are going to hear in the next portion of the trial, Mr. Hoffman, Mr. Reliable, and therefore those should not be included in any damage claim by Fuller. Those are going to be adjudicated in the subsequent hearing.”

Therefore it would appear that the issue of Fuller’s potential liability as it related to subcontractors was not submitted to the jury. The jury returned general verdicts for all the defendants on all the claims.

Reliable Welding, the subcontractor involved in the action, withdrew its claim and refiled it in the State court. One subcontractor, Hoffman, did proceed to a bench trial in the Federal court. The trial court found all three parties, Fuller, the college and the architect to be responsible for the delays as to Hoffman. Fuller’s conduct which caused the delay apparently consisted of instructing the subcontractor to remove the backfill which ordinarily would have been there. While the Federal court denied Fuller’s claim over against the college and the architect it did so only on the ground that following Board of Education v. Joseph J. Duffy Co. (1968), 97 Ill. App. 2d 158, 240 N.E.2d 5, and Talandis Construction Corp. v. Illinois Building Authority (1974), 23 Ill. App. 3d 929, 321 N.E.2d 154, indemnity could not be had for contract damages. It did hold that the prior jury verdicts did not bar the contractor’s claim for indemnification.

After Reliable filed its claim for delay damages, Fuller filed its present action against the college and the architect. While the complaint against the college is quite lengthy and detailed it is accurately summarized by defense counsel: “If we [Fuller] are liable to Reliable, it’s because the college breached its contract with us,” that is, any delays were the direct and proximate result of the college’s acts in breach of its contract with Fuller and not due to any active conduct by Fuller. Fuller’s claim against the architect seems to be based both on the college’s contract with Fuller, to which it does not appear the architect was a party, and in tort based solely on a general duty to exercise due care to avoid harming the interests of Fuller and its subcontractors.

I

The doctrine of collateral estoppel bars the litigating of the same issue twice. But it is only applicable when the issue was actually and necessarily litigated and determined in the first actions. (Kemling v. Country Mutual Insurance Co. (1982), 107 Ill. App. 3d 516, 437 N.E.2d 1253; Baird & Warner, Inc. v. Addison Industrial Park, Inc. (1979), 70 Ill. App. 3d 59, 387 N.E.2d 831; Pipitone v. Mandola (1962), 33 Ill. App. 2d 461, 180 N.E.2d 33.) In order for a former judgment to operate as an estoppel, there must have been a finding of a specific, material and controlling fact in the former case and it must conclusively appear that the issue of fact was so in issue that it was necessarily determined by the court rendering the judgment; if there is any uncertainty because more than one distinct issue of fact was presented, estoppel will not be applied. (Lange v. Coca-Cola Bottling Co. of Chicago, Inc. (1969), 44 Ill. 2d 73, 254 N.E.2d 467; Haack v. Lindsay Light & Chemical Co. (1946), 393 Ill. 367, 66 N.E.2d 391; Hoffman v. Hoffman (1928), 330 Ill. 413, 161 N.E. 723; Baird & Warner, Inc. v. Addison Industrial Park, Inc. (1979), 70 Ill. App. 3d 59, 387 N.E.2d 831; Siebach v. Pienta (1978), 60 Ill. App. 3d 645, 377 N.E.2d 393

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Salgado v. Lenoci (In re Lenoci)
599 B.R. 599 (N.D. Illinois, 2019)
Lakeview Collection Inc. v. Bank of America, N.A.
942 F. Supp. 2d 830 (N.D. Illinois, 2013)
Peregrine Financial Group, Inc. v. Martinez
Appellate Court of Illinois, 1999
Dowling v. Finley Associates, Inc.
727 A.2d 1245 (Supreme Court of Connecticut, 1999)
Cain v. Cross
Appellate Court of Illinois, 1997
Tralon Corp. v. Cedarapids, Inc.
966 F. Supp. 812 (N.D. Iowa, 1997)
Anderson v. Financial Matters, Inc.
672 N.E.2d 1261 (Appellate Court of Illinois, 1996)
Zielinski v. Miller
660 N.E.2d 1289 (Appellate Court of Illinois, 1996)
Taylor v. Peoples Gas Light & Coke Co.
656 N.E.2d 134 (Appellate Court of Illinois, 1995)
Progressive Land Developers, Inc. v. Exchange National Bank of Chicago
641 N.E.2d 608 (Appellate Court of Illinois, 1994)
Jones v. Melrose Park National Bank
592 N.E.2d 562 (Appellate Court of Illinois, 1992)
Betts v. Manville Personal Injury Settlement Trust
588 N.E.2d 1193 (Appellate Court of Illinois, 1992)
Congregation of the Passion, Holy Cross Province v. Touche Ross & Co.
586 N.E.2d 600 (Appellate Court of Illinois, 1991)
Smith v. Chemical Personnel Search, Inc.
576 N.E.2d 340 (Appellate Court of Illinois, 1991)
Maloney v. Pihera
573 N.E.2d 1379 (Appellate Court of Illinois, 1991)
In Re Marriage of Wilson
549 N.E.2d 1348 (Appellate Court of Illinois, 1990)
People Ex Rel. Hartigan v. Community Hospital
545 N.E.2d 226 (Appellate Court of Illinois, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
455 N.E.2d 811, 118 Ill. App. 3d 782, 74 Ill. Dec. 382, 1983 Ill. App. LEXIS 2399, Counsel Stack Legal Research, https://law.counselstack.com/opinion/case-prestressing-corp-v-chicago-college-of-osteopathic-medicine-illappct-1983.