Case Handyman Service of Tennessee, LLC v. Helen Marie Harben Lee

CourtCourt of Appeals of Tennessee
DecidedJune 13, 2012
DocketM2011-00751-COA-R3-CV
StatusPublished

This text of Case Handyman Service of Tennessee, LLC v. Helen Marie Harben Lee (Case Handyman Service of Tennessee, LLC v. Helen Marie Harben Lee) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Case Handyman Service of Tennessee, LLC v. Helen Marie Harben Lee, (Tenn. Ct. App. 2012).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE November 15, 2011 Session

CASE HANDYMAN SERVICE OF TENNESSEE, LLC v. HELEN MARIE HARBEN LEE

Appeal from the Chancery Court for Davidson County No. 071868I Claudia Bonnyman, Chancellor

No. M2011-00751-COA-R3-CV - Filed June 13, 2012

Homeowner retained Contractor to remodel her residence and paid Contractor two out of three installments as provided in the contract. Homeowner was not satisfied with Contractor’s work and refused to pay the final installment. Contractor sued for breach of contract and Homeowner filed a counterclaim asserting Contractor breached the contract by failing to perform the job in a workmanlike and reasonable manner. Homeowner also claimed Contractor violated the Tennessee Consumer Protection Act by engaging in unfair and deceptive practices. The trial court dismissed Contractor’s complaint and held Contractor breached the contract by failing to perform the work in a reasonable and workmanlike manner. The court found Contractor was not liable for double or treble damages under the Tennessee Consumer Protection Act because Homeowner did not prove its deficiencies were intentional or willful. Homeowner appealed, claiming the trial court erred in denying her motion to amend her counterclaim to assert a claim for rescission and erred in holding Contractor did not violate the Tennessee Consumer Protection Act. We affirm the trial court’s judgment.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed

P ATRICIA J. C OTTRELL, P.J., M.S., delivered the opinion of the Court, in which F RANK G. C LEMENT, J R. and A NDY D. B ENNETT, JJ., joined.

Helen Marie Harben Lee, Nashville, Tennessee, Pro Se.

Case Handyman Services of Tennessee, LLC did not participate in this appeal. OPINION

This is a breach of contract case in which Helen Marie Harben Lee hired Case Handyman Service of TN, LLC (“Case Handyman”) to remodel a recently acquired condominium. Case Handyman alleged Ms. Lee breached the contract by refusing to pay the final $18,433.70 due on the contract, and Ms. Lee alleged Case Handyman breached the contract by failing to perform the contract in a workmanlike manner, causing her to hire other contractors to complete the project and redo Case Handyman’s defective work. The trial court concluded Case Handyman breached the contract and awarded Ms. Lee damages. Ms. Lee appeals the trial court’s opinion, claiming she is entitled to rescind her contract with Case Handyman, and if she is not entitled to rescission, she should be awarded more damages than the trial court awarded her.

I. B ACKGROUND

Ms. Lee and Case Handyman entered into a construction contract on October 10 or 11, 2006, for the remodeling of Ms. Lee’s condominium in Nashville, Tennessee (the “Contract”). The Contract was very specific about the work Case Handyman was to do in each room of Ms. Lee’s residence and provided that Ms. Lee would pay Case Handyman a total of $56,282.55. Ms. Lee was to pay Case Handyman one-third upon signing the Contract, one-third when Case Handyman began the work, and one-third upon completion of the project.

Ms. Lee paid Case Handyman the first two installments as the Contract specified. As the work progressed, Case Handyman prepared three change orders that Ms. Lee agreed to and signed on October 24, 2006, November 2, 2006, and January 3, 2007. Pursuant to the terms of these change orders, Ms. Lee paid Case Handyman an additional $11,515.33.

Case Handyman alleges it completed its work on Ms. Lee’s residence on March 12, 2007 and demanded its final payment due under the Contract, but that Ms. Lee refused to make the final payment. Ms. Lee denies Case Handyman completed the job described in the Contract on March 12 or at any other time and contends Case Handyman is not entitled to any more compensation.

Case Handyman filed suit against Ms. Lee alleging breach of contract and sought to recover the final payment due under the Contract, which it claimed was $18,433.70. Case Handyman also sought to enforce a mechanics’ and materialmen’s lien pursuant to Tenn. Code Ann. §66-11-101 et seq. As an alternative theory of recovery to breach of contract, Case Handyman alleged unjust enrichment.

-2- Ms. Lee filed an Answer in which she denied any money was owing to Case Handyman and filed a Counterclaim in which she asserted five causes of action. First, Ms. Lee alleged Case Handyman failed to construct the project in a workman-like manner and was liable to her for negligence and negligent supervision. Second, Ms. Lee alleged Case Handyman breached the Contract by performing only a portion of the project and failing to perform the work it did in a manner consistent with the standards in the construction industry. Third, Ms. Lee alleged Case Handyman intentionally made representations to her that its work would be completed in accordance with or above the standards in the construction industry and that Case Handyman knew or should have known when it made these representations that they were false. Ms. Lee alleged Case Handyman intentionally double charged her by including in the change orders work that was already provided for in the Contract and that these acts constituted a violation of the Tennessee Consumer Protection Act. Fourth, Ms. Lee alleged Case Handyman was liable for fraudulent misrepresentation. Ms. Lee’s fifth and final cause of action was for punitive damages, which Ms. Lee contended she was entitled to based on Case Handyman’s intentional, malicious, and outrageous conduct. Ms. Lee asserted as damages the amount she had to pay other contractors to remedy Case Handyman’s defective work, the value of the lost use of her home, punitive damages, and other damages to be proven at trial.

Ms. Lee attempted to amend her Counterclaim prior to trail to add a prayer for rescission. The trial court considered Ms. Lee’s proposed amendment on the first day of trial, before the parties gave their opening arguments. After explaining that rescission is not available as a remedy based on the facts of Ms. Lee’s case, the court denied Ms. Lee’s motion to amend.

A bench trial was held on three separate days in September and December 2010 and in January 2011. Case Handyman presented testimony and evidence supporting its argument that it performed construction work on Ms. Lee’s residence in a reasonable and workmanlike manner and that Ms. Lee breached the Contract when she refused to pay the balance of what she owed under the Contract. Ms. Lee represented herself and presented testimony and numerous items of documentary evidence in support of her claim that Case Handyman failed to perform its work in a manner that would be acceptable to the reasonable homeowner. Ms. Lee presented photographs of Case Handyman’s work as well as documentation of the money she paid to other contractors she hired to complete the work Case Handyman began, the work Case Handyman was supposed to do but never initiated, or, in some cases, to rip out and redo the work Case Handyman did that was not up to par.

-3- II. T RIAL C OURT’S F INDINGS

Following the parties’ presentation of proof and closing arguments, the trial court made the following findings of fact from the bench:

[T]he plaintiff and the homeowner entered into a written contract on October 10 or 11, 2006. The homeowner made the first one-third installment payment on October 11, 2006. . . .

.....

[T]he parties agreed that certain work would be done at the homeowner’s . . . residence. The contract did not have a completion date. There were three change orders and the homeowner paid fully for each change order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Poole v. Union Planters Bank, N.A.
337 S.W.3d 771 (Court of Appeals of Tennessee, 2010)
Tucker v. Sierra Builders
180 S.W.3d 109 (Court of Appeals of Tennessee, 2005)
Cracker Barrel Old Country Store, Inc. v. Epperson
284 S.W.3d 303 (Tennessee Supreme Court, 2009)
Whaley v. Perkins
197 S.W.3d 665 (Tennessee Supreme Court, 2006)
Bogan v. Bogan
60 S.W.3d 721 (Tennessee Supreme Court, 2001)
New Life Corp. of America v. Thomas Nelson, Inc.
932 S.W.2d 921 (Court of Appeals of Tennessee, 1996)
Blair v. Brownson
197 S.W.3d 681 (Tennessee Supreme Court, 2006)
Hass v. Knighton
676 S.W.2d 554 (Tennessee Supreme Court, 1984)
Capitol Cadillac Olds, Inc. v. Roberts
813 S.W.2d 287 (Kentucky Supreme Court, 1991)
Early v. Street
241 S.W.2d 531 (Tennessee Supreme Court, 1951)
Union Carbide Corp. v. Huddleston
854 S.W.2d 87 (Tennessee Supreme Court, 1993)
Richards v. Taylor
926 S.W.2d 569 (Court of Appeals of Tennessee, 1996)
Wilson v. State Farm Fire & Casualty, Co.
799 F. Supp. 2d 829 (E.D. Tennessee, 2011)
Chastain v. Billings
570 S.W.2d 866 (Court of Appeals of Tennessee, 1978)
Brungard v. Caprice Records, Inc.
608 S.W.2d 585 (Court of Appeals of Tennessee, 1980)
Robinson v. Brooks
577 S.W.2d 207 (Court of Appeals of Tennessee, 1978)
Lamons v. Chamberlain
909 S.W.2d 795 (Court of Appeals of Tennessee, 1993)
Cannon v. Chadwell
150 S.W.2d 710 (Court of Appeals of Tennessee, 1940)
Simmons Et Ux. v. Evans Et Ux
206 S.W.2d 295 (Tennessee Supreme Court, 1947)
Farrell v. Third Nat. Bank in Nashville
101 S.W.2d 158 (Court of Appeals of Tennessee, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
Case Handyman Service of Tennessee, LLC v. Helen Marie Harben Lee, Counsel Stack Legal Research, https://law.counselstack.com/opinion/case-handyman-service-of-tennessee-llc-v-helen-mar-tennctapp-2012.