Casa Del Mar Association, Inc. v. Gossen Livingston Associates, Inc.

434 S.W.3d 211, 2014 WL 1394884, 2014 Tex. App. LEXIS 3989
CourtCourt of Appeals of Texas
DecidedApril 10, 2014
Docket01-13-00556-CV
StatusPublished
Cited by5 cases

This text of 434 S.W.3d 211 (Casa Del Mar Association, Inc. v. Gossen Livingston Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Casa Del Mar Association, Inc. v. Gossen Livingston Associates, Inc., 434 S.W.3d 211, 2014 WL 1394884, 2014 Tex. App. LEXIS 3989 (Tex. Ct. App. 2014).

Opinion

OPINION

EVELYN V. KEYES, Justice.

Appellant, Casa del Mar Association, Inc. (“Casa del Mar”), sued appellee, architecture firm Gossen Livingston Associates, Inc. (“GLA”), for services GLA provided during renovation of Casa del Mar’s condominiums. 1 GLA moved for summary judgment, arguing that the doctrine of collateral estoppel applied based on a previous arbitration proceeding addressing the same renovation project. The trial court granted GLA’s motion for summary judgment and dismissed Casa del Mar’s case. In its sole issue on appeal, Casa del Mar challenges the trial court’s grant of summary judgment on collateral estoppel grounds.

We affirm.

Background

Casa del Mar is the governing association for a group of condominiums called the Casa del Mar Beachfront Suites located in Galveston, Texas (“the Property”). GLA is an architecture firm that provided architectural design and other services to Casa del Mar from November 2000 until December 2007. On November 16, 2001, Casa del Mar contracted with GLA for certain design services for the Property, which was undergoing substantial renovations and reconstruction (“the 2001 Contract”). This contract was subsequently revised and amended on multiple occasions *214 to reflect changing conditions in the renovation project.

In August 2002, in a change order to the 2001 Contract, GLA agreed to provide architectural consulting services for balcony repair for some condominium units that were damaged in a fire (the “fire test balconies”). GLA submitted several designs to Casa del Mar, which rejected at least one of the designs — “a Schulter design system” with an incorporated drainage system — as too complex and costly. GLA also submitted a sloped balcony design, which the parties eventually referred to as the “bath tub” design, that Casa del Mar chose to use. The bath tub design functioned under the theory that water would infíltrate the mortar joint into the grout of the tiled balcony floor and then would evaporate out of the mortar joint over time. A company called Belfor Construction constructed the fire test balconies.

On February 14, 2003, Casa del Mar and GLA entered into a second agreement (“the 2003 Contract”), which was based on a form contract provided by a professional architecture association. The 2003 Contract was substantially similar in form to the 2001 Contract. It contained an arbitration provision and a standard merger clause. The 2003 Contract provided that GLA would first submit “Conceptual Design Documents” to Casa del Mar, and, upon Casa del Mar’s approval, GLA would provide “Construction Documents consisting of Drawings and Specifications setting forth in detail the requirements for the construction of the Project.” Under a section entitled “Scope of Architect’s Basic Services,” GLA also agreed to provide “construction-phase administration of the construction contract.” Article 12 of the form contract instructed the parties to insert a description of other services or modifications to the payment and compensation terms and further provided, “It is understood and agreed that the Architect’s Basic Services under this Agreement do not include Project observation or review of the Contractor’s performance or any other construction phase services, and that such services will be provided for by the Client.” The 2003 Contract also provided that the agreement could be amended in writing and stated the procedure for preparation and approval of change orders.

Among the specific projects addressed in the 2003 Contract was GLA’s design for a second set of balconies. The 2003 Contract provided that the “Balconies facing Seawall Blvd. will be repaired in a similar manner to repairs made to [the fire-test balconies],” and it contained details about the contemplated reconstruction of the balconies. GLA prepared the drawings for the second set of balconies, which were essentially the same as the fire test balconies and also used the bath tub design. Williams & Thomas, L.P. d/b/a Jamail Construction (“Jamail Construction”) constructed the second set of balconies.

This same pattern was repeated for a third set of balconies, referred to by the parties as the “saw-tooth balconies,” for which GLA again provided the same bath tub design that had been used on the previous two sets of balconies. On September 7, 2005, GLA provided a proposal for services indicating that the third phase of balcony repairs would utilize the previous balcony repair projects as “go-bys.” The proposal listed the specific work to be performed for the saw-tooth balconies. The proposal also stated, “If this Proposal is acceptable, we will prepare a Change Order to our existing Agreement.” The proposal was accepted by Casa del Mar’s property manager, Andy Van Baak. On December 5, 2005, GLA submitted a set of drawings to Casa del Mar for the sawtooth balconies that was essentially the *215 same as the drawings for the two previous sets of balconies.

On August 10, 2006, GLA submitted construction drawings based on the previous bath tub design that addressed the construction concerns specific to the saw-tooth balconies. Casa del Mar requested that Jamail Construction build a “mock up” that modified GLA’s bath tub design by replacing the single piece of stainless steel flashing called for in the design with a lesser-grade steel that was in two pieces. Casa del Mar approved Jamail Construction’s proposed mock up, and Jamail Construction began the construction of the saw-tooth balconies.

On January 23 and 24, 2007, Casa del Mar’s employees inspected the balcony renovations on the Property and noticed staining on the saw-tooth balconies, which they documented on their “punch list.” Casa del Mar’s general manager also documented the staining on certain saw-tooth balconies. Jamail Construction’s on-site supervisor investigated the staining and submitted a proposal to address the staining, which Casa del Mar rejected. On August 6, 2007, Jamail Construction certified that the work on the balconies was substantially complete, and GLA signed the Certification for Payment on August 10, 2007.

On November 3, 2011, Casa del Mar filed a demand for arbitration against GLA and Jamail Construction. In its second amended demand for arbitration, Casa del Mar alleged that it had “contracted with [GLA] and Jamail Construction for the design and construction of improvements” to the Property, specifically naming the saw-tooth balcony reconstruction project. Casa del Mar alleged causes of action against GLA for breach of contract for “failing to properly design the balcony and exterior siding systems,” breach of express warranty for services, breach of implied warranty of good and workmanlike conduct, negligence, negligent misrepresentation based on GLA’s alleged representation “that it would design quality balcony and exterior siding systems for the Property,” and violations of the Texas Deceptive Trade Practices Act (“DTPA”). Regarding specific design defects, Casa del Mar alleged that the design of the balcony waterproofing system was poor and incomplete, and failed to provide for proper drainage from the balconies. It attached an expert affidavit identifying GLA’s failure “to design a drainage layer ... resulting in water retention in the tile system.” Casa del Mar alleged similar causes of action against Jamail Construction based on its role in constructing the balconies.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clem v. Tomlinson
124 F.4th 341 (Fifth Circuit, 2024)
Genender v. Kirkwood
506 S.W.3d 508 (Court of Appeals of Texas, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
434 S.W.3d 211, 2014 WL 1394884, 2014 Tex. App. LEXIS 3989, Counsel Stack Legal Research, https://law.counselstack.com/opinion/casa-del-mar-association-inc-v-gossen-livingston-associates-inc-texapp-2014.