Carr v. Bridgewater Planning Zoning Comm., No. 058078 (Nov. 24, 1992)

1992 Conn. Super. Ct. 10547
CourtConnecticut Superior Court
DecidedNovember 24, 1992
DocketNo. 058078
StatusUnpublished

This text of 1992 Conn. Super. Ct. 10547 (Carr v. Bridgewater Planning Zoning Comm., No. 058078 (Nov. 24, 1992)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carr v. Bridgewater Planning Zoning Comm., No. 058078 (Nov. 24, 1992), 1992 Conn. Super. Ct. 10547 (Colo. Ct. App. 1992).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION The plaintiff, John F. Carr, Jr., seeks a writ of mandamus to compel the defendant Planning and Zoning Commission ("Commission") to sign the plaintiff's mylar subdivision plan and compel the Board of Selectmen ("Board") to approve the subdivision CT Page 10548 road.

The plaintiff is the owner of property located on Route 133 in the Town of Bridgewater, Connecticut. (Plaintiff's Exhibit 1.) By application dated October 3, 1989, the plaintiff applied to the defendant Commission for approval of a residential subdivision of the property. (Plaintiff's Exhibit 4). The plaintiff's application was received by the Commission at its regular meeting of October 11, 1989. (Plaintiff's Exhibit 9).

At the November 6, 1989 regular meeting of the Commission the plaintiff received a Memorandum prepared by Robert D. King, consultant to the Town of Bridgewater, which listed eight (8) items which needed to be completed or revised in accordance with the subdivision regulations. (See Plaintiff's Exhibit 10). A map submitted by plaintiff's counsel showing that information was submitted under cover of a November 27th letter. (plaintiff's Exhibit 11). Thereafter, plaintiff received another Memorandum, dated December 11, 1989, in which it was suggested that "[t]he applicant advise the Commission as to whether the above listed maps or plans are complete and accurate." (Plaintiff's Exhibit 12). The Chairman of the Commission was advised by letter dated January 5, 1990, that the maps were both complete and accurate. (Plaintiff's Exhibit 14).

At its March 14, 1990 regular meeting, the Commission approved plaintiff's subdivision application, but made that approval subject to the satisfaction of four conditions. Those conditions were:

a. modification numbers 2 through 23 and number 25 of Mr. King's memorandum dated March 13, 1990 be adopted;

b. subject to the approval of the road by the Board of Selectmen; (that the construction plans have been signed and dated by the Board of Selectmen);

c. notation be placed on the subdivision maps which states that the wells be drilled and tested on each lot before a building permit is issued;

d. delete additional Open Space/Conservation Easement other than that shown on the Subdivision Plan revised to January 18, 1990, and the remainder of which, up to 15%, be in the area of Lot # 10. CT Page 10549

Plaintiff's Exhibit 23.

This decision by the Commission stated that it was "subject to approval of the road by the Board of Selectmen." (Plaintiff's Exhibit 23 at 3, 41 at 9). The Town of Bridgewater, however, then had and still has a Road Ordinance requiring all streets in subdivisions to be reviewed and approved by the Selectmen. (Plaintiffs Exhibit 50, 51; Defendants Exhibit 1). In addition, the plaintiff admitted that he would have had to comply with the Road ordinance regardless of whether the Commission had noted that fact in its subdivision approval. (Transcript at 34).

Section 3.8 of the Bridgewater Subdivision Regulations, entitled "Completion of Required Modifications and Conditions," provides, in pertinent part:

When the Commission modifies and approves an application it shall promptly advise the applicant of the required modifications to the maps, plans or other application documents. No application shall be endorsed for filing until the required modifications have been completed and submitted in the final required form.

All approvals shall be conditioned upon the applicant's presentation and recording of any deeds or easements required by the Commission . . .

All of the above information, documents or performance guaranties shall be submitted within forty-five (45) days of the Commissions's (sic) approval. If not so filed the subdivision approval shall be deemed automatically void.

Plaintiff's Exhibit 2, at 9-10. This section requires an applicant who has received approval of a subdivision plan subject to modifications to file a revised final plan within 45 days after approval. (Plaintiff's Exhibit 2). This Regulation also expressly states, "[i]f not so filed, the subdivision approval shall be deemed automatically void." Id. The plaintiff admitted that he did not file modified plans within the required time. (Transcript at 30). In fact, modified plans have never been submitted to the Commission, although plaintiff did send amended plans to King over one year later. (Transcript at 61).

On March 20th 1990, plaintiff appeared at a special meeting of CT Page 10550 the defendant Board of Selectmen, to request approval of the subdivision road. (See Plaintiff's Exhibit 26). The defendant Board approved the subdivision road, but conditioned its approval upon plaintiff's providing a minimum sight line distance of 450 feet at the southerly intersection of the subdivision road with Route 133. This sight line distance was based on the concerns of King, and the Selectmen's own knowledge of traffic conditions, mainly excessive speed, on Route 133. (Transcript at 52, 59). This "condition" actually represented a concession to the developer, as Section 3.1.7 of the Road Ordinance would ordinarily require a 525-foot sight line. (See Plaintiff's Exhibit 20 at 2).

In order to accommodate the Board's requirement of a 450 foot sight line, the plaintiff had to obtain approval of the Connecticut Department of Transportation ("DOT"), (Transcript at 18), because achieving the 450 foot sight line was impossible with out relocating the travel way of Route 133 to the east. (Transcript at 18).

The plaintiff admitted that he had knowledge of the Road Ordinance prior to submitting his subdivision application. (Transcript at 34). Moreover, the plaintiff's trial exhibits show that the sight line requirements were raised by King in memoranda to the Commission several times prior to its decision. This sight line requirement was also raised on one occasion prior to the submission of plaintiff's application. (Plaintiff's Exhibits 8 at 2, 10 at 3, 18 at 1, 20 at 2). Each of these memoranda specifically refer to section 3.1.7 of the Road Ordinance. In addition, the written responses of the plaintiff's engineer is additional proof that plaintiff was aware of King's memoranda. (Plaintiff's Exhibits 11, 13, 21). The plaintiff, however, never resolved the sight line issue, or even addressed it, with the Board until after the Commission had approved the subdivision application. (Transcript at 35-36). The plaintiff also testified that he has been a developer for the last eight to ten years and that he was aware of the need to obtain such a permit when he submitted his subdivision application. (Transcript at 3, 34).

In August of 1991, approximately one year and five months after receiving approval of the defendant Board, plaintiff obtained the DOT's approval by agreeing to pay for the relocation of Route 133. (Transcript at 19). However, during this one year and five month period the plaintiff never sought an extension of the 45 day period from the defendant Commission nor did the plaintiff inform the Commission of the status of the permit application with the CT Page 10551 DOT. (Transcript at 41). The plaintiff could now meet the defendant Board's condition and provide a 450 foot sight line. The plaintiff returned to the defendant Board on August 13, 1991 to request the subdivision road construction permit, only to be told that the defendant Board believed that his subdivision was no longer valid under Section 3.8 of the Subdivision Regulations. (Transcript at 22; see also Plaintiff's Exhibit 38). The defendant Board for that reason refused to issue the road construction permit. (Transcript at 22).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carpenter v. Planning & Zoning Commission
409 A.2d 1029 (Supreme Court of Connecticut, 1979)
Roy v. Centennial Insurance
370 A.2d 1011 (Supreme Court of Connecticut, 1976)
Nicoli v. Planning & Zoning Commission
368 A.2d 24 (Supreme Court of Connecticut, 1976)
Sterner v. Saugatuck Harbor Yacht Club, Inc.
450 A.2d 369 (Supreme Court of Connecticut, 1982)
Waterbury Teachers Assn. v. Furlong
294 A.2d 546 (Supreme Court of Connecticut, 1972)
Sullivan v. Morgan
236 A.2d 906 (Supreme Court of Connecticut, 1967)
Hackett v. City of New Britain
477 A.2d 148 (Connecticut Appellate Court, 1984)
Vartuli v. Sotire
472 A.2d 336 (Supreme Court of Connecticut, 1984)
Caldrello v. Planning Board
476 A.2d 1063 (Supreme Court of Connecticut, 1984)
Simons v. Canty
488 A.2d 1267 (Supreme Court of Connecticut, 1985)
Halpern v. Board of Education
495 A.2d 264 (Supreme Court of Connecticut, 1985)
Capalbo v. Planning & Zoning Board of Appeals
547 A.2d 528 (Supreme Court of Connecticut, 1988)
Spero v. Zoning Board of Appeals
586 A.2d 590 (Supreme Court of Connecticut, 1991)
Double I Ltd. Partnership v. Plan & Zoning Commission
588 A.2d 624 (Supreme Court of Connecticut, 1991)
Timber Trails Corp. v. Planning & Zoning Commission
610 A.2d 620 (Supreme Court of Connecticut, 1992)
Moscowitz v. Planning & Zoning Commission
547 A.2d 569 (Connecticut Appellate Court, 1988)
Shailer v. Planning & Zoning Commission
596 A.2d 1336 (Connecticut Appellate Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
1992 Conn. Super. Ct. 10547, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carr-v-bridgewater-planning-zoning-comm-no-058078-nov-24-1992-connsuperct-1992.