Carr Office Park, LLC v. Charles Schwab & Co., Inc.

291 F. App'x 178
CourtCourt of Appeals for the Tenth Circuit
DecidedAugust 29, 2008
Docket07-1277
StatusUnpublished
Cited by2 cases

This text of 291 F. App'x 178 (Carr Office Park, LLC v. Charles Schwab & Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carr Office Park, LLC v. Charles Schwab & Co., Inc., 291 F. App'x 178 (10th Cir. 2008).

Opinion

ORDER AND JUDGMENT *

MICHAEL R. MURPHY, Circuit Judge.

Plaintiff Carr Office Park, LLC (Carr) and defendant Charles Schwab & Co., Inc. (Schwab) are, respectively, landlord and tenant in a corporate center located in Colorado. Numerous leases and agreements regulate the relationship between the parties. This dispute arose out of an agreement that obligated Carr to build an office complex and associated parking garage, which Schwab was then obligated to lease. Changed circumstances led the parties to alter the agreement so that it covered a multiple-tenant parking garage, rather than an single-tenant office complex. After completion of the parking garage, Carr and Schwab were unable to agree on the terms governing the lease of the garage. Carr filed this suit in Colorado state court, claiming Schwab was in breach of contract for its failure to pay rent for the garage. Schwab removed the action to the Federal District Court for the District of Colorado. The district court, with diversity jurisdiction pursuant to 28 U.S.C. §§ 1332 and 1441, determined that essential elements of the parking garage lease were ambiguous and the agreements between the parties constituted only an unenforceable agreement to agree. The district court accordingly granted Schwab’s motion for summary judgment. This court has jurisdiction under 28 U.S.C. § 1291 and AFFIRMS the judgment of the district court.

I. Background

Carr owns and operates an office park in Arapahoe County, Colorado known as Pan *180 orama Corporate Center. In 1997, Carr and Schwab entered into a lease (Building III Lease) for a building known as Panorama III in the Corporate Center. At the same time, Carr and Schwab entered into an Option Agreement. Under the Option Agreement, Schwab was entitled to exercise five Expansion Notices, which would trigger Carr’s obligation to construct a new building and Schwab’s obligation to lease the newly constructed premises. The Option Agreement specified that after the exercise of an expansion option, Carr would deliver a lease for the new building (New Building Lease). The Option Agreement also specified that the failure of the parties to agree to a New Building Lease would not affect the validity of the Expansion Notice. Rather, absent an agreement to alternate terms, the New Building Lease would contain, as a default, the same terms and conditions expressed in the Building III Lease. In December of 2000, the parties entered into the Second Amendment to the Option Agreement. That Amendment replaced the default lease terms from the Building III Lease with the terms negotiated for a different, prior lease between the parties for the Panorama VIII development. This new default lease was termed the Lease Form for New Buildings (Lease Form).

In June of 2000 Schwab exercised its expansion option, requiring Carr to build a new office site and parking garage known as Panorama IV. After the exercise of this option, Carr was approached by the Regional Transportation District (RTD) regarding the proposed construction of a light rail stop and parking facilities near the Panorama IV building site. Carr and RTD, with Schwab’s knowledge, entered into an agreement under which the Panorama IV parking garage (Shared Parking Facility) would be shared by RTD and Schwab. Carr and Schwab entered into the Third Amendment to the Option Agreement, by which Schwab formally approved the agreement between Carr and RTD and agreed that Carr would not be in breach of the Option Agreement by performing its contractual obligations to RTD.

Subsequently, Schwab determined that, due to current economic conditions, it no longer wished to go forward with the Panorama IV expansion. The parties agreed in the Fourth Amendment to the Option Agreement (Fourth Amendment) that Schwab could revoke its exercise of the expansion option with respect to the office building in exchange for payments in excess of seven million dollars. 1 The Fourth Amendment specified that the revocation did not apply to Schwab’s lease of the Shared Parking Facility. It stated, “[u]pon completion of the Shared Parking Facility, [Schwab] shall be required to lease from [Carr] the parking spaces which are contained in two lowest levels of the Shared Parking Facility (the ‘Parking Spaces’).” The Fourth Amendment further provided that,

within [sixty] days after [Schwab’s] receipt of [Carr’s] notice of commencement of construction of the Shared Parking Facility, [Carr] and [Schwab] shall, in good faith, negotiate and finalize a lease document (the “Garage Structure Lease”) based on the Lease Form for New Buildings ... concerning [Schwab’s] lease of the Parking Spaces which requires [Schwab] to pay to [Carr] an annual triple net rent for use of the Parking Spaces calculated as a product of the Total Project Costs (as such term is defined in the Lease Form) for [Carr’s] cost of the construction of [Schwab’s] portion of the Shared Parking Facility and the Return Rate for *181 Panorama IV.... [Can-] estimates that such rent will equal $502,200.00 per annum (triple net) assuming a Total Project Cost of $5,400,000.00 for [Schwab’s] portion of the Shared Parking Facility.”

In addition, the Fourth Amendment dictated that “[i]n the event of any conflict between the terms and provisions of the Option Agreement, as it has previously been amended, and the terms and provisions of this Fourth Amendment, the terms and provisions of this Fourth Amendment shall control.”

In January of 2004 Carr notified Schwab that it would commence construction of the Shared Parking Facility in February. As agreed to in the Fourth Amendment, this notification triggered negotiations between the parties for a Shared Parking Facility lease. On March 5, 2004, Carr representative Lisa Foyston sent Schwab a proposed lease (March 5 Draft). The March 5 Draft was redlined against a previously proposed draft lease for the entire Panorama IV complex, with changes intended to convert the lease into one for only the parking garage. Included in those changes were deletions of terms that would allow Schwab to purchase the premises (Article 33) and giving Schwab a right of first offer on the parking garage (Article 34). Schwab rejected the March 5 Draft and the parties continued their negotiations. The negotiations between the parties included discussions on issues such as the premises covered by the lease, which party bore the maintenance obligations for the structure, rental of excess space by Schwab, and whether an extension option would exist.

The parties failed to resolve these issues. The Shared Parking Facility was completed and delivered on December 3, 2004, but Schwab has never occupied the Facility nor paid rent. Carr brought suit on November 29, 2005, alleging Schwab was in breach of contract. In the district court, the parties filed cross motions for summary judgment. Carr argued the existing agreements obligated Schwab to pay rent on the Shared Parking Facility and its failure to do so constituted breach.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gruber v. Regis Corp.
D. Colorado, 2019
Bloom Master Inc. v. Bloom Master LLC
2019 UT App 63 (Court of Appeals of Utah, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
291 F. App'x 178, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carr-office-park-llc-v-charles-schwab-co-inc-ca10-2008.