Carolina Freight Carriers Corporation v. Carlo Galuppi and Irma Galuppi, A/K/A Erma Sue Galuppi

902 F.2d 32, 1990 U.S. App. LEXIS 7246, 1990 WL 58402
CourtCourt of Appeals for the Sixth Circuit
DecidedMay 3, 1990
Docket89-1539
StatusUnpublished

This text of 902 F.2d 32 (Carolina Freight Carriers Corporation v. Carlo Galuppi and Irma Galuppi, A/K/A Erma Sue Galuppi) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carolina Freight Carriers Corporation v. Carlo Galuppi and Irma Galuppi, A/K/A Erma Sue Galuppi, 902 F.2d 32, 1990 U.S. App. LEXIS 7246, 1990 WL 58402 (6th Cir. 1990).

Opinion

902 F.2d 32

Unpublished Disposition
NOTICE: Sixth Circuit Rule 24(c) states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Sixth Circuit.
CAROLINA FREIGHT CARRIERS CORPORATION, Plaintiff-Appellant,
v.
Carlo GALUPPI and Irma Galuppi, a/k/a Erma Sue Galuppi,
Defendants-Appellees.

No. 89-1539.

United States Court of Appeals, Sixth Circuit.

May 3, 1990.

Before KEITH and DAVID A. NELSON, Circuit Judges, and CONTIE, Senior Circuit Judge.

PER CURIAM.

This is a contract action that was brought in federal court on diversity of citizenship grounds. After declining to consider parol evidence offered, as the court believed, to change the meaning of written contract language that was not ambiguous, the court granted summary judgment for the plaintiff. Given the deference that must be accorded a district court's understanding of how the parol evidence rule would be applied under the law of the state in which the court sits, and given the existence of alternate grounds on which the summary judgment can be supported in this case, we are not prepared to hold that any reversible error occurred here. The judgment of the district court will be affirmed.

Plaintiff Carolina Freight Carriers Corporation entered into a written contract for the purchase from defendants Carlo and Irma Galuppi of a tract of land in Westland, Michigan. The parties entered into a separate agreement in which the Galuppis promised to construct a paved access road and install certain utilities. The work was to be done before September 1, 1987, and the Galuppis undertook to maintain the road until it was accepted by the City of Westland.

To secure their obligation to complete the access road, the Galuppis granted Carolina Freight a mortgage on an adjacent parcel for $175,000, the road's estimated construction cost. The mortgage gave Carolina Freight the right to demand payment of the $175,000, plus interest, if the Galuppis failed to perform their obligations under the agreement. None of the instruments contained an integration clause.

The Galuppis failed to construct the road and install the utilities, and Carolina Freight declared a default and demanded payment of $175,000, plus interest. The demand for payment was not met, and Carolina Freight brought suit.

The Galuppis admitted that they had failed to fulfill their contractual duties, that "all of the representations and agreements made between the parties are contained in the contractual agreements," and that the agreements "speak for themselves." In opposing Carolina Freight's motion for summary judgment, however, the Galuppis claimed that Carolina Freight told Mr. Galuppi at the time of the closing that the company would have the option of constructing the road itself and foreclosing on the mortgage to recover its costs. Mr. Galuppi claimed that he thought Carolina Freight would be required to do this.

The district court held that the terms of the written agreement were unambiguous, and that the Galuppi's assertions were not admissible to alter those terms. The court granted summary judgment to Carolina Freight in the amount of $175,000, plus interest.

"Even when no ambiguity appears on the face of a written agreement Michigan courts may receive extrinsic evidence to disclose ambiguity or to show that there is none." American Anodco, Inc. v. Reynolds Metals Co., 743 F.2d 417, 422 (6th Cir.1984). In the case at bar, however, the Galuppis presented no evidence which, if accepted by the court, would have established an ambiguity. The existence of an ambiguity is a question of law. S.C. Gray, Inc. v. Ford Motor Company, 286 N.W.2d 34, 45 (Mich.App.1979). The mortgage agreement clearly provided that a failure by the Galuppis to perform their obligations under the companion agreement would constitute a default, and that upon default Carolina Freight could demand payment of $175,000 plus interest. Mr. Galuppi offered to show he was told that "Carolina Freight would have the option of doing the construction themselves" and that "Carolina Freight could then proceed to foreclose on the mortgage to pay off any construction costs." (Emphasis supplied.) Mr. Galuppi may have entertained a subjective belief that Carolina Freight was required to exercise this option, but such a belief can avail him nothing if it was not warranted by the words Carolina Freight actually used. See Michigan Chandelier Company v. Morse, 297 N.W. 64, 67 (Mich.1941). The record does not show Mr. Galuppi's understanding was warranted, in our opinion.

The Galuppis argue that Carolina Freight had a duty to mitigate damages. The district court concluded, however, that the terms of the mortgage were equivalent to a liquidated damages clause. It is not apparent that this conclusion was erroneous under Michigan law. A contractual provision for liquidated damages is nothing more than an agreement by the parties fixing the amount of damages in case of a breach. Papo v. Aglo Restaurants of San Jose, Inc., 386 N.W.2d 177, 181 (Mich.App.1986). A provision for liquidated damages is valid if it is reasonable, Curran v. Williams, 89 N.W.2d 602, 604 (Mich.1958), and there was no showing of unreasonableness here. The provision may even work to the Galluppis' advantage, because $175,000 plus interest is all that Carolina Freight can recover, regardless of what damages may actually have arisen from the Galuppis' breach of their contractual obligations.

The Galuppis assert, in conclusory fashion, that Carolina Freight could have constructed the road for less than $175,000, but they point to no evidence in support of this assertion. Even if Carolina Freight had a duty to mitigate, the burden of proving a breach of the duty would rest with the Galuppis. Gorman v. Soble, 328 N.W.2d 119, 127 (Mich.App.1982). Summary judgment would be appropriate in any event, absent a showing of a factual issue as to whether Carolina Freight could build the road for less than the stipulated amount. See Celotex Corp. v. Catrett, 477 U.S. 317, 325 (1986).

The judgment of the district court is AFFIRMED. Carolina Freight's motion for damages for delay is DENIED.

CONTIE, Senior Circuit Judge, dissenting.

I respectfully dissent. Though the Roadway and Utilities Agreement and the Second Mortgage Agreement are arguably clear and unambiguous on their face, Michigan authority has clearly, and repeatedly, held that parol evidence is nevertheless admissible absent an integration clause.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
902 F.2d 32, 1990 U.S. App. LEXIS 7246, 1990 WL 58402, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carolina-freight-carriers-corporation-v-carlo-galuppi-and-irma-galuppi-ca6-1990.