Carey Electric Co. v. Abf Freight System, Unpublished Decision (8-13-1999)

CourtOhio Court of Appeals
DecidedAugust 13, 1999
DocketC.A. Case No. 17335. T.C. Case No. 97-7764.
StatusUnpublished

This text of Carey Electric Co. v. Abf Freight System, Unpublished Decision (8-13-1999) (Carey Electric Co. v. Abf Freight System, Unpublished Decision (8-13-1999)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carey Electric Co. v. Abf Freight System, Unpublished Decision (8-13-1999), (Ohio Ct. App. 1999).

Opinion

OPINION
The present case is before us on the appeal of Carey Electric, Inc. from a trial court decision overruling Carey's motion for summary judgment. As a preliminary point, we note that we issued a show cause order in this case on August 26, 1998, asking Carey to explain why the appeal should not be dismissed for lack of a final, appealable order. After receiving memoranda on the issue, we filed a decision and entry on December 1, 1998, finding that a final, appealable order existed. In our decision, we observed that a denial of summary judgment is ordinarily not an appealable order. However, we also said that, in this case, the trial court had done more than simply deny a motion for summary judgment. Specifically, by invalidating Carey's mechanics' lien, the court had effectively determined Carey's foreclosure action and had prevented a judgment in Carey's favor. Our conclusion in this regard was also supported by the trial court's nunc pro tunc order of July 28, 1998, which expressly stated that the court's prior decision had terminated the foreclosure action. Accordingly, the merits of this appeal are properly before us.

Concerning the appeal, Carey's single assignment of error is as follows:

I. The trial court erred in applying a strict compliance standard to the service requirements for notices of furnishings under R.C. 1311.19 when it denied Appellant's motion for partial summary judgment and, in effect, allowed an owner to ignore actual receipt and knowledge of the notice of furnishing.

After considering the assignment of error and the undisputed facts, we agree with the trial court that Carey's lien is invalid. A short explanation of our decision follows.

I
According to the undisputed facts, ABF Freight System, Inc. (ABF) filed and recorded a notice of commencement (NOC) with the Montgomery County Recorder on July 18, 1995. The NOC related to a general construction contract between ABF and Pauley Construction, Inc., the general contractor for ABF's proposed truck terminal facility. Carey was a subcontractor for the truck terminal project, and entered into a contract with Pauley on July 17, 1995. Under the contract, Carey was to furnish materials, equipment, and labor for electrical work on the project. Subsequently, on September 20, 1995, Carey mailed a notice of furnishing (NOF) to ABF at the address listed in the NOC. The NOF was sent by first class mail, postage pre-paid, and stated that Carey had first furnished labor, work, or materials for the project on July 14, 1995.

ABF did receive the NOF at some point, but the record does not indicate the date of receipt. In a request for admissions, ABF admitted that a copy of the NOF was contained in ABF files. However, ABF had no record indicating whether the NOF had been received from Carey or from Pauley Construction, nor did ABF know the date of receipt. In support of its summary judgment motion, Carey submitted an affidavit from a postal employee, who said the standard delivery time for first class mail in September, 1995, would have been three business days.

The contract between Pauley and Carey was in the amount of approximately $871,000, and the last date of work performed by Carey was November 18, 1996. Carey filed an affidavit with the Montgomery County Recorder on November 25, 1996, claiming that $117,975.56 was still due for materials and labor. A copy of the affidavit was then served on ABF by certified mail on December 10, 1996.

The central issue in this case is whether the first class mail service of the NOF complied with the requirements of R.C. 1311.05 and R.C. 1311.19. In this regard, Carey contends that service substantially complied with the statutes and should be deemed adequate to preserve its lien. The trial court felt otherwise, and we agree.

Concerning notices of furnishing, R.C. 1311.05(A) states that:

a subcontractor or materialman who performs labor or work upon or furnishes material in furtherance of an improvement to real property and who wishes to preserve his lien rights shall serve a notice of furnishing, if any person has recorded a notice of commencement in accordance with section 1311.04 of the Revised Code, upon the owner's, part owner's, or lessee's designee named in the notice of commencement or amended notice and the original contractor under the original contract pursuant to which he is performing labor or work or furnishing materials, as named in the notice of commencement or amended notice and at the address listed in the notice or amended notice at any time after the recording of the notice of commencement or amended notice but within twenty-one days after performing the first labor or work or furnishing the first materials or within the extended time period provided for in division (I) or (J) of section 1311.04 of the Revised Code.

(Emphasis added). Regarding service, R.C. 1311.19(A), provides, in pertinent part, that:

any notice, affidavit, or other document required to be served under this chapter shall be served by one of the following means:

* * *

(2) Certified or registered mail, overnight delivery service, hand delivery, or any other method which includes a written evidence of receipt.

Admittedly, Carey did not comply with these service requirements, since sending a document by first class mail is not a method which includes written evidence of receipt. Carey claims, however, that the correct standard to be used is substantial, rather than strict compliance. To support this proposition, Carey makes several arguments. First, Carey contends that the new mechanics' lien law passed in 1992 distinguishes between "preservation" and "perfection" of lien rights. Next, Carey points to Michigan case law which interprets a similar statutory scheme and uses a "substantial compliance" standard. And finally, Carey relies on Ohio cases which have allegedly applied a substantial compliance standard.

Concerning the first point, Carey claims that under the law prior to 1992, contractors had no right of action against an owner until they notified the owner in writing of the identities of subcontractors and the amounts due. See, former R.C. 1311.04, effective for projects contracted for before January 1, 1992. Carey also contends, by way of contrast, that contractors, laborers, and material suppliers have lien rights under the new law the moment they provide labor and materials, and need only serve notice to "preserve" those rights. See, R.C. 1311.05 (A), effective for projects contracted for after January 1, 1992. We consider this a distinction without a difference, since the right to recover on the lien does not exist in either situation if the statutory procedures and requirements have not been followed.

Furthermore, lien rights arise under R.C. 1311.02, not R.C. 1311.04 or R.C. 1311.05. In this regard, R.C. 1311.02 contained essentially the same wording before and after amendment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vugterveen Systems, Inc. v. Olde Millpond Corp.
560 N.W.2d 43 (Michigan Supreme Court, 1997)
Hoppes Builders & Development Co. v. Hurren Builders, Inc.
692 N.E.2d 622 (Ohio Court of Appeals, 1996)
State v. Hooper
386 N.E.2d 1348 (Ohio Supreme Court, 1979)
Ohio State Board of Pharmacy v. Frantz
555 N.E.2d 630 (Ohio Supreme Court, 1990)
Roxane Laboratories, Inc. v. Tracy
661 N.E.2d 1011 (Ohio Supreme Court, 1996)
Hoppes Builders & Development Co. v. Hurren Builders, Inc.
690 N.E.2d 11 (Ohio Supreme Court, 1998)
RN Building Materials, Inc. v. C.R. Huffer Roofing & Sheetmetal, Inc.
683 N.E.2d 884 (Court of Common Pleas of Ohio, Franklin County, Civil Division, 1997)
Jim Morgan Electric Co. v. Smith
684 N.E.2d 117 (Court of Common Pleas of Ohio, Franklin County, Civil Division, 1996)
Jim Morgan Electric Co. v. Smith
684 N.E.2d 121 (Court of Common Pleas of Ohio, Franklin County, Civil Division, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Carey Electric Co. v. Abf Freight System, Unpublished Decision (8-13-1999), Counsel Stack Legal Research, https://law.counselstack.com/opinion/carey-electric-co-v-abf-freight-system-unpublished-decision-8-13-1999-ohioctapp-1999.