Capitol Materials, Inc. v. Kellogg & Kimsey, Inc.

530 S.E.2d 488, 242 Ga. App. 584, 2000 Fulton County D. Rep. 1214, 2000 Ga. App. LEXIS 270
CourtCourt of Appeals of Georgia
DecidedMarch 2, 2000
DocketA99A2240
StatusPublished
Cited by11 cases

This text of 530 S.E.2d 488 (Capitol Materials, Inc. v. Kellogg & Kimsey, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Capitol Materials, Inc. v. Kellogg & Kimsey, Inc., 530 S.E.2d 488, 242 Ga. App. 584, 2000 Fulton County D. Rep. 1214, 2000 Ga. App. LEXIS 270 (Ga. Ct. App. 2000).

Opinion

Miller, Judge.

The following undisputed chronology is relevant to the disposition of this appeal from the grant of summary judgment refusing to enforce an alleged settlement agreement resolving a claim of lien.

On January 16, 1997, Capitol Materials, Inc. filed a lien against Lot 948 of the 17th District, Second Section of Cobb County, Georgia, for materials provided as of October 18, 1996, to a subcontractor in the construction of a Barnes & Noble bookstore. This lien was ostensibly against the real property of Nazemian Properties Associates. On January 23, Capitol filed a purported amendment to its lien against Lot 948, changing the name of the owner of the real property against which the lien was asserted to BN Development Company LLC (“Owner”), and also giving a different description of the boundaries to Lot 948. A month later, Capitol filed a cancellation of the original January 16 lien. On February 25, Ira L. Rachelson, counsel for Capitol, submitted a written proposal to the Owner, offering to settle the combined claims of Capitol and the subcontractor “for the amount owed Capitol.” In return, Capitol would “deliver the appropriate lien waivers, releases and satisfactions.”

In subsequent negotiations with the general contractor, Kellogg & Kimsey, Inc., its counsel, Anthony S. Cabrera, offered to pay $36,000 to release the lien, and Rachelson countered with an offer to accept $38,000. After further discussion, Rachelson believed he reached an oral agreement to settle Capitol’s claim for $37,250 in exchange for a release of all claims of lien. Cabrera relayed that amount to Kellogg & Kimsey, and on March 17, Harry Rodriguez, Kellogg & Kimsey’s controller, authorized a check in that amount payable to Capitol. On March 19, Rachelson sent Cabrera a letter purporting to confirm the agreement and its terms. But the time for performance of this settlement agreement came and went without payment. Responding to Rachelson’s inquiries, Cabrera wrote back on March 24, denying the existence of a complete settlement agreement, and giving the following reasons:

While an amount for which our clients would be willing to compromise the claim of lien was discussed, various items including the forms of the release documents, the release of *585 [Capitol’s] claim of lien, etc., related to a resolution of this matter remained open. Of particular significance is that throughout our various discussions, it was our understanding that [Capitol] had otherwise recorded a valid claim of lien on the project. . . . Further investigation has concluded that the [January 16] claim of lien may have been recorded on the wrong real property.

Cabrera first became aware that Capitol might not have a valid lien against the Owner’s property sometime after his last conversation with Rachelson, and this March 24 letter was the only time he communicated to Rachelson any doubts about the validity of the lien. Kellogg & Kimsey’s continued failure to pay resulted in the instant action for breach of contract and for enforcement of the settlement agreement in the principal sum of $37,250. After discovery, Capitol moved for partial summary judgment to enforce the settlement agreement. Kellogg & Kimsey also moved for summary judgment, contending that no enforceable contract was reached because of: (1) a lack of consideration; (2) no meeting of the minds; (3) misrepresentations of fact; and (4) the statute of frauds. The trial court denied Capitol’s motion while granting that of Kellogg & Kimsey, and Capitol appeals that ruling.

1. Lack of consideration. Capitol’s attempted amendment of its lien after the three-month period allowed by OCGA § 44-14-361.1 (a) (2) is ineffectual under the authority of Shirah Contracting Co. v. Waite. 1 But the ultimate invalidity of Capitol’s materialman’s lien would not be a valid basis for reneging on an existing settlement agreement compromising Capitol’s $42,320 claim for payment of the lesser sum of $37,250. Forbearance to prosecute a legal claim and the compromise of a doubtful right are both sufficient consideration to support a contract. 2 “If the requirement of consideration is met, there is no additional requirement of a gain, advantage, or benefit to the promisor or of a loss, disadvantage, or detriment to the promisee.” 3 Thus, where parties have conflicting claims, depending upon a law point, and they compromise them, each is bound by the settlement, whether the law point turns out to have been for it or against it. 4 The grant of summary judgment on behalf of Kellogg & Kimsey cannot be sustained on the ground there was no valid consideration.

2. Misrepresentation. As the factual basis for the alleged misrep *586 reservation, Cabrera testified he “never questioned whether the lien was valid or not; [he] assumed it was,” based upon the assertions of Rachelson. But upon inspection of the original documents (after his negotiations with Rachelson), Cabrera concluded that the underlying claim of lien might be invalid because the untimely amendment was, in his professional judgment, a nullity, while the original timely claim was filed against the wrong property and, in any event, had been canceled by Rachelson.

Under OCGA § 13-4-60, a contract may be rescinded at the instance of the party defrauded. 5 But a claim of fraud cannot be predicated upon misrepresentations of law or misrepresentations as to matters of law. 6 Consequently, any alleged misrepresentation about the legal validity of Capitol’s untimely amended lien or its timely-but-canceled original lien cannot provide a basis for rescinding the alleged settlement agreement. Similarly, a unilateral mistake based upon defendant’s negligence in failing to determine the facts would not justify defendant’s failure to perform under OCGA § 13-5-4. 7

3. Meeting of the minds. Whether a settlement is an enforceable agreement is a question of contract law for the trial court, but an appellate court owes no deference to its conclusions. 8 “No contract exists until all essential terms have been agreed to. OCGA § 13-3-2.” 9 Cabrera indicated that there was no meeting of the minds because the forms of the lien releases had not been negotiated. In our view, this does not render the alleged agreement incomplete.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Piccard v. Deedy
N.D. Georgia, 2023
Louis Syms v. State
Court of Appeals of Georgia, 2015
Syms v. State
770 S.E.2d 305 (Court of Appeals of Georgia, 2015)
Johnson v. DeKalb County
726 S.E.2d 102 (Court of Appeals of Georgia, 2012)
Kemp v. Adams
677 S.E.2d 743 (Court of Appeals of Georgia, 2009)
Mealer v. Kennedy
659 S.E.2d 809 (Court of Appeals of Georgia, 2008)
Matrix Financial Services, Inc. v. Dean
655 S.E.2d 290 (Court of Appeals of Georgia, 2007)
DeRossett Enterprises, Inc. v. General Electric Capital Corp.
621 S.E.2d 755 (Court of Appeals of Georgia, 2005)
Speed v. Muhanna
619 S.E.2d 324 (Court of Appeals of Georgia, 2005)
Pourreza v. Teel Appraisals & Advisory, Inc.
616 S.E.2d 108 (Court of Appeals of Georgia, 2005)
Paul Dean Corp. v. Kilgore
556 S.E.2d 228 (Court of Appeals of Georgia, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
530 S.E.2d 488, 242 Ga. App. 584, 2000 Fulton County D. Rep. 1214, 2000 Ga. App. LEXIS 270, Counsel Stack Legal Research, https://law.counselstack.com/opinion/capitol-materials-inc-v-kellogg-kimsey-inc-gactapp-2000.