Canton Lutheran Church v. Sovik, Mathre, Sathrum & Quanbeck

507 F. Supp. 873, 1981 U.S. Dist. LEXIS 10630
CourtDistrict Court, D. South Dakota
DecidedFebruary 13, 1981
DocketCiv. 79-4068
StatusPublished
Cited by12 cases

This text of 507 F. Supp. 873 (Canton Lutheran Church v. Sovik, Mathre, Sathrum & Quanbeck) is published on Counsel Stack Legal Research, covering District Court, D. South Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Canton Lutheran Church v. Sovik, Mathre, Sathrum & Quanbeck, 507 F. Supp. 873, 1981 U.S. Dist. LEXIS 10630 (D.S.D. 1981).

Opinion

MEMORANDUM DECISION AND ORDER

NICHOL, Senior Judge.

PROCEDURAL HISTORY

This action was originally filed by the plaintiff, Canton Lutheran Church, in First Judicial Circuit Court, Lincoln County, South Dakota. It was removed to federal court by the defendant W. A. Kepp & Sons. Subsequent to the removal, defendants W. A. Kepp & Sons and Sovik, Mathre, Sathrum & Quanbeck each filed a motion for summary judgment on the basis that “the statute of limitations provided by South Dakota law in SDCL 15-2-9 for action for deficiencies in construction of a building has expired.”

Plaintiff countered with the argument that the statute is unconstitutional and maintains that even if it is constitutional the statute was tolled by the fraudulent concealment of the defendants or because the defendants were without the jurisdiction of the state pursuant to SDCL 15-2-20.

Plaintiff then moved for partial summary judgment “dismissing and striking out that part of the answer of each of the defendants which is based upon a defense of the bar of statute of limitations for building deficiencies or a purported ‘General Statute of Limitations.’ ”

FACTS

Prior to June 3, 1960, plaintiff, Canton Lutheran Church, made plans to construct an educational building addition to its principal structure.

*875 On June 3, 1960, plaintiff and defendant Sovik, Mathre, Sathrum & Quanbeck (hereinafter referred to as defendant architect) entered into a contract for professional architectural services for the educational building addition.

On August 18,1961, plaintiff and defendant W.A. Kepp & Sons (hereinafter referred to as defendant contractor) entered into a contract for the construction of the educational building addition. Defendant contractor agreed to furnish all materials and construct the educational building in accordance with certain specifications drawn by defendant architect.

Pursuant to the above contracts, plans were drawn and construction commenced. Defendant architect gave its certificate of substantial completion on or about October 8, 1963.

In the spring of 1977, plaintiff observed cracks in the exterior structural concrete of the education building addition. After the defects were first noticed in the spring of 1977, tests of the structural concrete in the educational building were made at plaintiff’s request. The results of the tests, conducted by Twin City Testing and Engineering Laboratory, Inc., indicated the presence of calcium chloride in the educational building addition concrete. Calcium chloride, when added to concrete, will cause the concrete to set up faster in cold weather.

The architectural specifications for the concrete in the educational building addition set forth in detail the mixing, pouring, and curing criteria for the concrete and did not call for, or authorize, the use of calcium chloride.

In a report on the cracks in the concrete to Maynard Lintvedt, President of the Canton Lutheran Church Congregation, by defendant architect it was their conclusion that the cracking condition was unusual and severe and:

due to corrosion of the corner reinforcing bars, causing residue or by-product which creates internal pressure in the surrounding concrete resulting in splitting of the concrete. Moisture by itself in the concrete would not have caused this extensive corrosion. However, the additional presence of calcium chloride would create the chemical environment which would allow corrosion of the steel to take place.

As a result, plaintiff commenced this action in the spring of 1979, alleging breach of warranty, negligent supervision by defendant architect, breach of contract and fraud.

Both defendants have raised SDCL 15-2-9, “Limitation of action for deficiencies in construction of building” as a defense.

STATUTORY BACKGROUND

SDCL 15-2-9 through 15-2-12 are patterned after the Model Code proposed by various associations of design professionals and contractors. These statutes were a response by the associations to major extensions in the sixties of their members’ potential liability. Watts v. Putnam County, 525 S.W.2d 488 (Tenn.1975). Similar statutes have been adopted in at least 42 states. Phillips v. ABC Builders, Inc., 611 P.2d 821 (Wyo.1980).

The statute bars any action for personal injury or death or for any injury to real or personal property “arising out of any deficiency in the design, planning, supervision, inspection and observation of construction, or construction of an improvement to real property” not brought within six years after the date the owner can occupy or use the improvement. 1 SDCL 15-2-9. There is, however, a one year grace period in which an action may be brought for those injuries occurring in the sixth year after completion. SDCL 15-2-11. The statute is not a conventional limitation provision. Unlike other statutes of limitations, it is entirely unrelated to the accrual of any cause of action; the period beginning to *876 run on the date of substantial completion, rather than the date of injury, damage, or discovery. SDCL 15-2-9. Cf. Generally SDCL Ch. 15-2. In fact, it has been said that the statute “does not bar a cause of action; its effect, rather, is to prevent what might otherwise be a cause of action from ever arising.” Rosenberg v. Town of North Bergen, 61 N.J. 190, 293 A.2d 662 (1972). If this, in fact, is the effect of the statute, it would be inconsistent with existing case law of the United States Supreme Court 2 , the Eighth Circuit Court of Appeals 3 , and the South Dakota Supreme Court 4 .

The statute is obviously strong medicine, and as one would expect, has been the subject of considerable discussion 5 and litigation. At least 28 courts have ruled on the constitutionality of statutes similar to SDCL 15-2-9.

In 12 cases the statutes have been upheld. Arkansas, Carter v. Hartenstein, 248 Ark. 1172, 455 S.W.2d 918 (1970); Louisiana, Burnmaster v. Gravity Drainage District No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eagleman v. Diocese of Rapid City
2015 SD 22 (South Dakota Supreme Court, 2015)
Rosenberg v. Falling Water, Inc.
709 S.E.2d 227 (Supreme Court of Georgia, 2011)
Blue Cross and Blue Shield v. WR Grace & Co.
781 F. Supp. 420 (D. South Carolina, 1991)
L.R. Foy Construction Co. v. South Dakota State Cement Plant Commission
399 N.W.2d 340 (South Dakota Supreme Court, 1987)
Sander v. Wright
394 N.W.2d 896 (South Dakota Supreme Court, 1986)
Elbe v. Yankton Independent School District No. 63-3
640 F. Supp. 1234 (D. South Dakota, 1986)
Beecher v. White
447 N.E.2d 622 (Indiana Court of Appeals, 1983)
McMacken v. State
325 N.W.2d 60 (South Dakota Supreme Court, 1982)
Holy Cross Parish v. Huether
308 N.W.2d 575 (South Dakota Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
507 F. Supp. 873, 1981 U.S. Dist. LEXIS 10630, Counsel Stack Legal Research, https://law.counselstack.com/opinion/canton-lutheran-church-v-sovik-mathre-sathrum-quanbeck-sdd-1981.