Campbell v. the Daimler Group, Inc.

686 N.E.2d 337, 115 Ohio App. 3d 783
CourtOhio Court of Appeals
DecidedNovember 26, 1996
DocketNos. 96APE03-291 and 96APE03-295.
StatusPublished
Cited by11 cases

This text of 686 N.E.2d 337 (Campbell v. the Daimler Group, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Campbell v. the Daimler Group, Inc., 686 N.E.2d 337, 115 Ohio App. 3d 783 (Ohio Ct. App. 1996).

Opinion

Petree, Presiding Judge.

Plaintiffs, Brian Campbell and Katy Corriveau-Clark, Administrator of the Estate of Donald Clark, deceased, appeal from judgments of the Franklin County Court of Common Pleas in favor of defendants Korda/Nemeth Engineering, Inc., Northeast Concrete Construction, Inc., and The Daimler Group, Inc.

Plaintiffs set forth the following assignments of error:

*786 “[1.] The trial court committed prejudicial error in granting the motion for summary judgment filed by Korda Nemeth Engineering. There was an issue of material fact that precluded the granting of such motion.
“[2.] The trial court erred in refusing to allow appellant[s] to conduct a voir dire examination of appellees’ expert, Peter Korda, regarding an in-court experiment performed by him.
“[3.] The trial court erred in allowing appellees’ expert, Peter Korda, to conduct his in-court experiment without the required foundation to show that the conditions of [the] experiment were substantially similar to those of the construction site at the time of the building’s collapse. The experiment purported to compare the merits of cross-bracing with that of proper anchors in a structure, which was the ultimate issue to be decided by the jury.
“[4.] [The] trial court committed prejudicial error in refusing to allow Dale Campbell, the President of Seneca Steel Erectors, to render an opinion as to the cause of the building’s collapse.”

In 1991, defendant The Daimler Group, Inc. (“Daimler Group”) was hired by Huntington National Bank (“HNB”) to manage the construction of the HNB Mortgage Operations Center in Columbus, Ohio. Defendant Korda/Nemeth Engineering, Inc. (“Korda/Nemeth”) was subsequently hired by the project’s architect to perform engineering design work. Thereafter, defendant Northeast Concrete and Construction, Inc. (“Northeast”) was hired as the concrete contractor and Seneca Steel Erectors (“Seneca Steel”) was hired to erect the steel frame.

During the spring of 1991, Northeast poured concrete pads for the first of the four phases of construction. Northeast was also responsible for sinking anchor bolts into the concrete pads. The original design plans drawn up by Korda/Nemeth called for fourteen-inch-by-three-quarter-inch steel anchor bolts, which were to be imbedded nine inches deep into the concrete slab.

In pouring the concrete slabs for the first phase of the project, Northeast set several of the anchor bolts in the wrong place. When informed of this problem, Steven Rice, construction supervisor for Daimler Group, contacted Dave Holtzapple, the design engineer with Korda/Nemeth. Holtzapple authorized the use of three-quarter-inch expansion anchor bolts, commonly known as the “Hilte Quick-bolt.” Accordingly, Northeast burned off the original bolts and imbedded Hilte Quick-bolts into the concrete slabs. The substitution of the Hilte Quick-bolts was noted in the “general notes” or “field notes,” which became part of the project design plans.

When Seneca Steel began erecting steel columns in phase one of the project, it encountered problems trying to straighten or “plumb” some of the columns. Several of the Hilte Quick-bolts would not tighten properly and, in one instance, a *787 bolt pulled completely out of the concrete slab. Eventually, Seneca Steel was able to straighten the columns with the aid of heavy machinery.

When phase one neared completion, Steve Rice notified Dale Campbell, the owner of Seneca Steel, that preliminary construction in phase two was not yet complete. Rice told Campbell that Seneca Steel should begin construction of phase four, out of sequence.

The erection of steel columns and beams in phase four was underway on June 1, 1992, when one of the columns in row C began to lean. Seneca Steel attached a guy wire to column C-2 to provide support. On June 2, 1992, Dale Campbell was using a crane to place bundles of steel joists atop the structure; decedent was working at the top of a steel frame. According to Dale Campbell, one of his employees told him that two of the columns in row C were leaning. Moments later, Campbell heard a snapping sound and saw the structure crash to the ground. Decedent fell from the structure and was killed. Campbell did not learn that Hilte Quick-bolts had also been used in phase four of the project until after the accident occurred.

Plaintiff Katy Corriveau-Clark was appointed administrator of decedent’s estate. On April 22,1993, plaintiffs filed the instant action seeking damages from several defendants for the wrongful death of decedent, Donald Clark. Seneca Steel, Korda/Nemeth, Northeast, Daimler Group, and HNB were among the named defendants. 1 Defendant Korda/Nemeth filed a motion for summary judgment, which was granted by the trial court in a decision dated June 30, 1995. A judgment entry was journalized on July 18,1995.

Thereafter, the case proceeded to a jury trial against the remaining defendants, Northeast and Daimler Group. The jury returned a verdict in favor of both defendants and, on February 7, 1996, the trial court entered judgment upon the jury verdicts. Plaintiffs appeal to this court from the July 18, 1995 judgment in favor of Korda/Nemeth and the February 7, 1996 judgments in favor of Northeast and Daimler Group.

In plaintiffs’ first assignment of error, plaintiffs contend that the trial court erred when it granted summary judgment in favor of Korda/Nemeth. Under Civ.R. 56, summary judgment is proper when (1) no genuine issue as to any material fact remains to be litigated; (2) the moving party is entitled to judgment as a matter of law; and (3) it appears from the evidence that reasonable minds can come to but one conclusion, and in viewing the evidence most strongly in *788 favor of the party against whom the motion is made, that conclusion is adverse to that party. Welco Industries, Inc. v. Applied Cos. (1993), 67 Ohio St.3d 344, 617 N.E.2d 1129; Leibreich v. A.J. Refrigeration, Inc. (1993), 67 Ohio St.3d 266, 617 N.E.2d 1068.

The trial court held the Korda/Nemeth’s contract with the architectural contractor determined the extent of the company’s duty to plaintiffs’ decedent. 2 The trial court found that the limitation of liability provision contained in the contract shielded Korda/Nemeth from any liability to plaintiffs as a matter of law. The contract provides, in relevant part:

“The Architect shall not have control over or charge of and shall not be responsible for construction means, methods, techniques, sequences or procedures, or for safety precautions and programs in connection with the Work, since these are solely the Contractor’s responsibility under the Contract for Construction. The Architect shall not be responsible for the Contractor’s schedules or failure to carry out the Work in accordance with the Contract Documents.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Cartwright
2013 Ohio 2156 (Ohio Court of Appeals, 2013)
Young-Hatten v. Taylor, 08ap-511 (3-17-2009)
2009 Ohio 1185 (Ohio Court of Appeals, 2009)
Lautenschlager v. Midohio Cardiology, 07ap-308 (7-24-2008)
2008 Ohio 3692 (Ohio Court of Appeals, 2008)
State v. Walters, 06ap-693 (10-18-2007)
2007 Ohio 5554 (Ohio Court of Appeals, 2007)
Kimble Mixer Co. v. St. Vincent, Unpublished Decision (5-2-2006)
2006 Ohio 2258 (Ohio Court of Appeals, 2006)
Nationwide Mutual Ins. v. Icon, Unpublished Decision (5-26-2005)
2005 Ohio 2638 (Ohio Court of Appeals, 2005)
Tackett v. Gas Energy, Inc., Unpublished Decision (12-21-2004)
2004 Ohio 6979 (Ohio Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
686 N.E.2d 337, 115 Ohio App. 3d 783, Counsel Stack Legal Research, https://law.counselstack.com/opinion/campbell-v-the-daimler-group-inc-ohioctapp-1996.