This text of 1995 Conn. Super. Ct. 11786 (Camp v. Planning Zoning Commission, No. Cv95 0319318s (Oct. 13, 1995)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Camp v. Planning Zoning Commission, No. Cv95 0319318s (Oct. 13, 1995), 1995 Conn. Super. Ct. 11786 (Colo. Ct. App. 1995).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION The plaintiff, Herbert V. Camp, Jr., appeals, pursuant to General Statutes § 8-8, from a decision of the defendant, the Planning and Zoning Commission of the Town of Bethel (Commission), that modified and approved the subdivision application of Camp.

Camp commenced this appeal by service of process on December 23, 1994, against the Commission. Camp alleges that the Commission's action in modifying his subdivision application was illegal, arbitrary and in abuse of its discretion.

Camp owns property located at Topstone Drive and Greenwood Drive in Bethel. Exhibit A: July 14, 1978 deed to property. The property contains three residences, and is located in an R-10 zone which has a minimum lot size of 10,000 square feet and a minimum frontage requirement of 80 feet. Complaint ¶ 2. On August 17, 1994, Camp filed a five lot subdivision application with the Commission, and subsequently supplemented his application with the required documentation, including a subdivision map. [Return of Record [ROR], Item 1: August 16, 1994 application; ROR, Item 3: Subdivision Application Form § 95-4 (indicating items submitted)].

The subdivision map identifies the five lots as lot 1, lot 1A, lot 2, lot 2A and lot 2B. [ROR, Item 4: August 15, 1994 subdivision map]. Camp alleges in his complaint, and the Commission does not contest in its brief, that "Lots 1A, 2A and 2B as shown on the proposed subdivision map each contain a residence with frontage on Greenwood Avenue, and comply with the minimum lot size requirement in the zoning regulations of 10,000 square feet. Those parcels were separate lots in Bethel prior to the enactment of zoning regulations, and have the status of nonconforming uses as to their width and shape . . . ." Complaint ¶ 5; Camp v. Planning and Zoning Commission, Superior Court, judicial district of Danbury, Docket no. 27 29 12, at 1-2 (April 12, 1982, Lavery, J.). Proposed lot 1 is vacant and has an area CT Page 11788 of 10,138 square feet with 80.74 feet of frontage on Topstone Drive. [ROR, Item 4]. The Commission does not contend that lot 1 as shown on the map violates any regulations. Proposed lot 2 has an area of 23,399 square feet and a passway to Topstone Drive with only 20.18 feet of frontage. [ROR, Item 4]. Proposed lot 2 does not, on its face, comply with the zoning regulations which require 80 feet of frontage. Bethel Code § 118-24F. It is this noncompliance that concerned the Commission.

On December 8, 1978, however, the Bethel Zoning Board of Appeals (Board) granted a variance, reducing the frontage requirement of proposed lot 2 "from 80' to 20.18' on Topstone Drive to allow access to the rear lot. The variance becomes effective at such time it is filed in the land records with the Town Clerk." [ROR, Item 6: December 8, 1978 notice of variance approval]. The granting of the variance was never appealed and was properly recorded on December 14, 1978. [Certified Copy of December 8, 1978 variance].

In 1979, subsequent to the granting of the variance, Camp applied for a six lot subdivision of the property. Camp v.Planning and Zoning Commission, supra, 1. The Commission determined that the Board had improperly granted the frontage variance and therefore, the Commission refused to honor the 20.18 foot recorded variance. Id., 5-8. The Commission modified Camp's application and thereafter approved it, reducing the number of lots from six to five. Id., 3. Camp appealed to the Superior Court from the Commission's modified approval of the subdivision application. The action was not an appeal from the independent granting of the variance by the Board. Id. In its memorandum of decision, the court, Lavery, J., wrote that "[t]he key issue is whether the Bethel Zoning Board of Appeals had the power to grant the variance to reduce the frontage on the third new lot to 20 feet more or less and in effect create an interior lot and bind the defendant Commission in its consideration of the plaintiff's application. The answer is no." Id., 5. As a result, the court dismissed Camp's appeal, thereby sustaining the Commission's modified approval of the application. Id. Thereafter, Camp never constructed the subdivision and the approval expired as a matter of law. See General Statutes § 8-26c(c) (construction must be completed within five years from the granting of subdivision approval or the approval expires).

In deciding Camp's present application, the Commission was concerned about the effect of Judge Lavery's decision on the CT Page 11789 variance so they solicited the opinion of their counsel, Attorney Gallagher, as to the viability of the variance. [ROR, Item 21: November 3, 1994 letter from Commission to Attorney Gallagher]. On November 21, 1994, Attorney Gallagher responded, opining that "[s]ince no appeal was taken from the granting of the variance, his decision could not overturn it . . . ." [ROR, Item 25: November 21, 1994 letter from Attorney Gallagher to Commission]. He further opined that "[i]f there is an application before the commission containing the lot as allowed by the variance, I do not believe the commission can deny the subdivision because the lot does not meet zoning regulations because the terms of the variance in effect become the zoning regulations for that lot." [ROR, Item 25].

On December 13, 1994, after receiving the opinion letter from Attorney Gallagher and after several continuances, the Commission convened to hear and decide Camp's subdivision application. [ROR, Item 37, p. 2: Minutes for December 13, 1994 Commission meeting]. The Commission discussed Judge Lavery's decision and reviewed the materials filed by Camp, including a letter from his attorney. [ROR, Item 37, p. 2]. The Commission unanimously decided to approve the application with a modification. [ROR, Item 37, p. 2]. The modification was that lots 1 and 2 would be combined with a net result of a four lot subdivision being approved rather than a five lot subdivision. [ROR, Item 37, p. 2]. The reason given for the approval was that, as modified, the subdivision "meets our zoning regulations and does not create an interior lot in violation of our zoning regulations." [ROR, Item 37, p. 2]. On December 15, 1994, Camp's attorney received a notice from the Commission that the application had been approved as modified. [ROR, Item 28: December 15, 1994 letter from Commission to Attorney Tuozzolo]. The only reason given by the Commission for the modification was that the 20.18 feet of frontage does not comply with the zoning regulations since it creates an illegal interior lot. [ROR, Item 37, p. 2; Item 28]. There was no mention made in the decision of the effect of the variance. [ROR, Item 37, p. 2; Item 28]. The notice of decision was printed in TheBethel Home News on December 19, 1994. [ROR, Item 29: Certificate of Publication]. Thereafter, on December 23, 1994, this appeal was commenced by service of process on the Commission and the Bethel Town Clerk.

On March 14, 1995, Camp filed his brief. Therein he argues that the Commission's decision to disregard the variance and render a modified approval was arbitrary, illegal and contrary to CT Page 11790 law. Further, he argues that since the only reason offered for the modification was that the application did not conform to the zoning regulations, despite the existence of the variance, the court is required to determine the appeal based solely on the one ground for modification proffered by the Commission. On July 10, 1995, Camp filed a reply brief in further support of his appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

North Rollingwood Property Owners Assn. v. City Plan Commission
209 A.2d 177 (Supreme Court of Connecticut, 1965)
Robinson v. Unemployment Security Board of Review
434 A.2d 293 (Supreme Court of Connecticut, 1980)
Town of Westport v. City of Norwalk
355 A.2d 25 (Supreme Court of Connecticut, 1974)
Talarico v. Conkling
362 A.2d 862 (Supreme Court of Connecticut, 1975)
Beach v. Planning & Zoning Commission
103 A.2d 814 (Supreme Court of Connecticut, 1954)
Whittaker v. Zoning Board of Appeals
427 A.2d 1346 (Supreme Court of Connecticut, 1980)
Wright v. Zoning Board of Appeals
391 A.2d 146 (Supreme Court of Connecticut, 1978)
Pascale v. Board of Zoning Appeals
186 A.2d 377 (Supreme Court of Connecticut, 1962)
DeMaria v. Enfield Planning & Zoning Commission
271 A.2d 105 (Supreme Court of Connecticut, 1970)
Langbein v. Planning Board
146 A.2d 412 (Supreme Court of Connecticut, 1958)
Forest Construction Co. v. Planning & Zoning Commission
236 A.2d 917 (Supreme Court of Connecticut, 1967)
Lombardo v. Planning and Zoning Commission
663 A.2d 1128 (Connecticut Superior Court, 1994)
Eustace v. Adley Express Co.
1 Conn. Super. Ct. 58 (Connecticut Superior Court, 1935)
RK Development Corp. v. City of Norwalk
242 A.2d 781 (Supreme Court of Connecticut, 1968)
Simko v. Zoning Board of Appeals
538 A.2d 202 (Supreme Court of Connecticut, 1988)
Schwartz v. Planning & Zoning Commission
543 A.2d 1339 (Supreme Court of Connecticut, 1988)
Winchester Woods Associates v. Planning & Zoning Commission
592 A.2d 953 (Supreme Court of Connecticut, 1991)
Upjohn Co. v. Zoning Board of Appeals
616 A.2d 793 (Supreme Court of Connecticut, 1992)
Property Group, Inc. v. Planning & Zoning Commission
628 A.2d 1277 (Supreme Court of Connecticut, 1993)
Central Bank for Savings v. Planning & Zoning Commission
537 A.2d 510 (Connecticut Appellate Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
1995 Conn. Super. Ct. 11786, Counsel Stack Legal Research, https://law.counselstack.com/opinion/camp-v-planning-zoning-commission-no-cv95-0319318s-oct-13-1995-connsuperct-1995.