Camden Iron Works v. City of New York

104 A.D. 272, 93 N.Y.S. 754
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 15, 1905
StatusPublished
Cited by3 cases

This text of 104 A.D. 272 (Camden Iron Works v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Camden Iron Works v. City of New York, 104 A.D. 272, 93 N.Y.S. 754 (N.Y. Ct. App. 1905).

Opinions

Ingraham, J. :

. The plaintiff filed a lien upon'an amount due to the defendant Masterson under a contract by which the plaintiff was to supply to Masterson certain iron pipe to be used by him in the performance of a contract with the city of New York. The plaintiff, after furnishing some pipe under the contract for which it was paid, refused to complete the contract upon the ground that the inspectors appointed by the city to inspect the pipe before delivery had acted unjustly and arbitrarily in rejecting pipe that the plaintiff proposed to deliver, and stated that it would not continue supplying the pipe under the contract unless this complaint was remedied. After considerable correspondence Masterson gave the plaintiff notice that, unless it complied with its contract within a specified time, he would procure the pipe elsewhere, and the plaintiff not complying with this notice, Masterson procured other pipe and so completed his contract with the city. After this notice was given the plaintiff shipped certain pipe to Masterson which he declined to accept, and it was to recover for this pipe so shipped that this action was brought.

The contract between the plaintiff and Masterson was dated December 24, 1900,and recited that Masterson had, on the 16th day of November, 1900, entered into a contract with the city of New York to furnish and lay certain cast iron pipe and special castings, all as set forth in the specifications in said contract between the city and Masterson specifically referred to, and that the plain-. tiff agreed to furnish and deliver to said Masterson “ One-third (-J) [274]*274of the Cast Iron Pipes, and one-half (£) of the Special Castings named on page nine (9) of said specifications, and to ■ deliver them on cars at Aqueduct and Baldwin Stations and at stations between them, on the. Long Island Railroad, and the said William H. Master-son does hereby agree to receive the pipes and special castings at the above-named stations, and' to pay for them at the rate of Twenty-five dollars and forty cents ($25.40) per ton of 2,240 pounds for the straight pipes; three cents (3c) per pound for ordinary special castings’ and six cents (6c) per pound for such breeches pipes, as ’ may be needed. All of the1 said pipes and special castings are to be made in accordance with the specifications and plans of the Department of Water Supply, New York City, and are to be delivered by hot later than the first day of July, A. D. Nineteen hundred and two.” Subsequently, on February 5,-1901, by a subsequent contract, it was agreed that the plaintiff should furnish and deliver to Masterson one:half instead of one-third of the cast iron pipes therein mentioned. The contract between Masterson and the city of New York specified the quality of pipe and castings that were required and provided for certain tests to determine the quality of the pipe to be delivered under the contract. These tests were to be made by inspectors appointed by the city of New York at the cost and expense of Masterson. The specifications upon .which this contract was made between the city and Masterson provided for the- tests to-be made. One clause of these specifications provided: “ -The castings shall be free from scoria, scabs, cold shuts, sand holes, blow gates, gate shrinks, checks and core cuts, together with any and all imperfections ■ caused by cracked or crushed cores, or other defects- or imperfections caused by improper materials or manipulation. No plugging, cementing or other stopping up of the holes and flaws will be allowed, and no painting shall be done until after the castings have been inspected by the authorized agent.” Another clause provided : All the 48 inch pipe and special' castings shall be subjected to a proof by water pressure of 200 pounds to the square inch; all of the 36 in. and 30 in. pipe and special castings shall be subjected to' a proof by water pressure of 250 pounds to the square inch; all the pipe and special castings. of a smaller diameter than 30 in. shall be subjected to a proof by water pressure of 300 pounds to' the square inch. Each pipe while under the [275]*275required pressure shall be rapped with a hand hammer from end to-end to discover whether any defects.have been overlooked. Any pipe or special casting which fails under this test shall be rejected.. This inspection and test shall be made at the foundry under the direction of the Inspector and at the expense and risk of the Contractor.” Another clause provided: “ The Contractor shall notify the 'Engineer at léast seven (7) days previous to the commencement, of the manufacture of the castings, of the time and place where the; manufacture is to commence, in order that the Inspector may be present and supervise tile same; any or all castings which may be made without complying in every respect with the terms of this paragraph shall be rejected.”

On the 3d of January, 1901, Masterson inquired of the plaintiff’s agent when the plaintiff would be' ready for the inspector of pipes,, and the plaintiff’s agent answered that it would require the inspector-in one or two weeks. Subsequently, on January 15, 1901, the-plaintiff wrote to Masterson, saying that it would be ready for-the inspector on the seventeenth. Shortly after the plaintiff commenced to complain of -the inspectors, and stated that the experience that it had had with this inspector in the past was such as-to warrant it in strongly objecting to his selection for this part of the work; that it was impossible to make pipes which were absolutely perfect in all points, and that the inspector referred to, on previous work, made it a practice to reject thoroughly good pipe fully coming up to the spirit of the specifications, and pipes that would be accepted by other inspectors. Again, on January 24, 1901, the plaintiff asked whether Masterson had been able to secure “ satisfactory inspection.” And on January twenty-fourth Masterson wrote to the plaintiff to say that he hoped to be able to give definite information in regard to having the inspector transferred. Again, on February twenty-sixth, Masterson wrote to the plaintiff stating that he had endeavored .to obtain instructions for the inspector to accept certain pipes which he had rejected. On September 18 and 23, 1901, the plaintiff again' complained that certain of its pipes had been rejected for unimportant defects, and that the work had been stopped because of impracticable inspection. During all this time Masterson was insisting upon the plaintiff’s complying with its contract; that he had not the control of the inspector, and that. [276]*276plaintiff should supply pipe in accordance with- the contract that it had made, and there were constant promises by the plaintiff to Comply with these demands.

In July and August, Masterson was insisting, upon the plaintiff-complying with its contract, and complaining of lack of pipe ■required for the work, to which plaintiff replied by constant complaint as to inspection, with promises to ship the pipe; and finally, on September 16, .190.1, the plaintiff wrote .the defendant: “We have been doing our utmost to furnish the needed castings on your order in spite, of most unreasonable, retarding and exceedingly ■costly Inspection. Rejections of large expensive pieces have been made steadily, for most trivial reasons, until now we are compelled to advise you Jhat until ,the difficulty is remedied, we shall’ be obliged to cease making any further pieces, either of specials or of pipe. It is impossible to work under the unprecedented treatment which we have suffered under this present inspection.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Duffy Bros. v. Bing & Bing, Inc.
217 A.D. 10 (Appellate Division of the Supreme Court of New York, 1926)
Estes v. Curtiss Aeroplane & Motor Corp.
191 A.D. 719 (Appellate Division of the Supreme Court of New York, 1920)
Willson & Adams Co. v. Mack Paving & Construction Co.
147 A.D. 141 (Appellate Division of the Supreme Court of New York, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
104 A.D. 272, 93 N.Y.S. 754, Counsel Stack Legal Research, https://law.counselstack.com/opinion/camden-iron-works-v-city-of-new-york-nyappdiv-1905.