California Sportfishing Protection Alliance v. Federal Energy Regulatory Commission

472 F.3d 593
Court of Appeals for the Ninth Circuit·Decided December 11, 2006·No. 05-73064·Published·Cited by 8 cases

Opinion

SCHROEDER, Chief Judge:

This is a petition to review a decision of the Federal Energy Regulatory Commission (“FERC”) not to initiate formal consultation with the National Marine Fisheries Service (“NMFS”) about the operation of the DeSabla-Centerville hydroelectric project. The project is operated by respondent Pacific Gas and Electric (“PG & E”) under a 30-year license that FERC issued in 1980. The petitioners seek the consultation in order to protect Chinook Salmon that were declared a threatened species in 1999.

The petitioners include California Sport-fishing Protection Alliance and other environmental groups. The operative statute is section 7 of the Endangered Species Act (“ESA”) that provides for formal consultation with NMFS to insure that “agency action” does not jeopardize continued existence of an endangered species. 16 U.S.C. § 1536(a)(2). We have jurisdiction pursuant to the Federal Power Act, 16 U.S.C. § 825(Z)(b), to review the FERC orders denying petitioners’ petition for consultation and petition for rehearing.

The dispositive issue is whether there was any “action authorized, funded, or carried out” by a federal agency, that would have triggered the ESA’s consultation requirement in 1999. 16 U.S.C. § 1536(a)(2). Petitioners in essence are asking for consultation in order to determine whether PG & E should change the manner in which the project is operated pursuant to a license agreement issued by FERC in *595 1980. We conclude that the statutory language, the regulations promulgated pursuant to the statute, and our case law interpreting them compel the conclusion that the ESA imposes no duty to consult about activities conducted by PG & E pursuant to a previously issued, valid license from FERC.

FERC could unilaterally institute proceedings to amend the license if it so chose. This is because the license agreement itself contains provisions authorizing FERC to modify the license to reflect changing environmental concerns. The ESA and the applicable regulations, however, mandate consultation with NMFS only before an agency takes some affirmative agency action, such as issuing a license. See Tenn. Valley Auth. v. Hill, 437 U.S. 153, 186-88, 98 S.Ct. 2279, 57 L.Ed.2d 117 (1978); W. Watersheds Project v. Matejko, 456 F.3d 922, 930 (9th Cir.2006); Turtle Island Restoration Network v. Nat’l Marine Fisheries Serv., 340 F.3d 969, 977 (9th Cir.2003); 16 U.S.C. § 1536(a)(2); 50 C.F.R. § 402.02. Because FERC took no affirmative action concerning PG & E’s existing license, we must deny the petition for review.

BACKGROUND

The DeSabla-Centerville project is located in Butte County California. It consists of a system of dams, reservoirs, canals, and powerhouses that first divert water from two reservoirs and from Butte Creek into powerhouses for hydroelectric generation, before returning the water to Butte Creek down-stream. The operation of the dam system affects the flow of water in the creek, which provides spawning grounds for Chinook Salmon.

FERC may issue licenses to operate such projects for a term of up to 50 years. 16 U.S.C. § 799. PG & E operates this project under a 30-year license issued by FERC in 1980. The license allows FERC to require PG & E to make changes to operations to protect fish and wildlife. It states:

The Licensee shall, for the conservation and development of fish and wildlife resources, construct, maintain, and operate, or arrange for the construction, maintenance, and operation of such reasonable modifications of project structures and operation, as may be ordered by [FERC] upon its own motion or upon the recommendation of the Secretary of the Interior or the fish and wildlife agency or agencies of any state in which the project or part thereof is located, after notice and opportunity for hearing.

Nineteen years after FERC issued the license, the Chinook was declared a threatened species under the ESA. Endangered and Threatened Species; Threatened Status for Two Chinook Salmon Evolutionary Significant Units (ESUs) in California, 64 Fed.Reg. 50,394, 50,412 (Sept. 16, 1999).

After many fish died in Butte Creek in 2002 and 2003, NMFS requested FERC to initiate “formal consultation” regarding the project’s effects on the Chinook pursuant to 50 C.F.R. § 402.14(a). FERC did not do so. In April 2004, petitioner California Sportfishing petitioned FERC to initiate formal consultation, and FERC denied the petition in August 2004. That denial, as well as the denial of rehearing on March 23, 2005 are the subject of this petition for review.

A major component of formal consultation is the production of a “Biological Opinion.” 50 C.F.R. § 402.14(g)(4). In the Biological Opinion, NMFS must determine whether or not the action under review “is likely to jeopardize the continued existence of a listed species or result in the destruction or adverse modification of critical habitat.” 50 C.F.R. § 402.14(h)(3). If *596 NMFS concludes that jeopardy is likely, it must issue “reasonable and prudent alternatives” to the action under review. Id. Along with such alternatives, NMFS must issue an “incidental take” statement. Id. § 402.14(1). The “incidental take” statement constitutes a permit for the agency or licensee to take endangered species, so long as they implement the reasonable and prudent alternatives and comply with the conditions of the incidental take statement. Bennett v. Spear, 520 U.S. 154, 170, 117 S.Ct. 1154, 137 L.Ed.2d 281 (1997).

Free access — add to your briefcase to read the full text and ask questions with AI

California Sportfishing Protection Alliance v. Federal Energy Regulatory Commission, 472 F.3d 593 (9th Cir. 2006).

472 F.3d 593 (California Sportfishing Protection Alliance v. Federal Energy Regulatory Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related