Calhoun v. Bennett

236 P.3d 745, 236 Or. App. 206, 2010 Ore. App. LEXIS 730
CourtCourt of Appeals of Oregon
DecidedJuly 7, 2010
Docket060443660; A136708
StatusPublished
Cited by4 cases

This text of 236 P.3d 745 (Calhoun v. Bennett) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Calhoun v. Bennett, 236 P.3d 745, 236 Or. App. 206, 2010 Ore. App. LEXIS 730 (Or. Ct. App. 2010).

Opinion

*208 ARMSTRONG, J.

Plaintiffs, who are licensed construction contractors, appeal a judgment denying their claim for foreclosure of a construction lien and awarding them damages for breach of contract or quantum meruit in the amount of $40,000. 1 They assert two assignments of error. First, they argue that the trial court erred in concluding that their construction lien was invalid because they had failed to deliver the “Information Notice to Owner” as required under ORS 87.093. 2 Second, they challenge the amount of damages awarded by the trial court on their breach of contract claim, contending that the trial court improperly reduced the amount of damages on that claim. We reject plaintiffs’ first assignment of error without discussion. With respect to plaintiffs’ second assignment of error, we reverse the award of damages and remand with instructions for the trial court to enter an award of damages in the amount of $63,113.05 in favor of plaintiffs on their breach of contract claim. Otherwise, we affirm.

*209 We relate only the facts necessary to provide context for our discussion of plaintiffs’ second assignment of error; those facts are undisputed. In May 2005, defendants Rusty and Liana Bennett (the Bennetts) 3 contracted with plaintiffs for construction of a house and other improvements on the Bennetts’ property in Cove, Oregon. The contract price was $251,000. To finance the construction, the Bennetts entered into a construction loan agreement with defendant SunTrust Mortgage, Inc. (SunTrust or defendant); the loan was secured by a deed of trust recorded on August 8,2005. The loan agreement provided that SunTrust would advance money for construction as work was completed and accepted by the Bennetts (also referred to as “draws”).

Construction on the property proceeded and, in September 2005, the Bennetts received a draw of $27,610.99 from SunTrust, which they paid to plaintiffs. A second draw of $65,262.34 was advanced by SunTrust to the Bennetts on December 5, 2005; that money was not paid to plaintiffs. Instead, a dispute arose between plaintiffs and the Bennetts, and, on December 9, 2005, the Bennetts notified plaintiffs that they were terminating the contract. A subsequent letter from the Bennetts’ lawyer to plaintiffs indicated that the Bennetts were terminating the contract due to “substantial nonperformance.” On December 22, 2005, plaintiffs recorded a construction lien claim against the Bennetts’ property in the amount of $73,996, plus interest from that date. They subsequently filed this action.

In an amended complaint, plaintiffs alleged seven claims for relief. It is the first two of those claims that are pertinent to this appeal. The first claim for relief was untitled and alleged three separate “counts.” Count one alleged construction lien foreclosure; in the alternative, and as to the Bennetts only, plaintiffs alleged breach of contract (count two) and quantum meruit (count three). On each of those “counts,” plaintiffs sought damages in the amount of $63,113.05, based on the unpaid balance of the materials, labor, and services provided by plaintiffs under the contract *210 through December 9, 2005, together with costs and attorney fees. 4

Plaintiffs’ second claim for relief was labeled “Breach of Contract” and alleged that the Bennetts had breached the construction contract by unilaterally terminating it and that plaintiffs were thus entitled to “lost profits” from the Bennetts in the amount of $40,000. 5

In response, the Bennetts and SunTrust each asserted a variety of affirmative defenses. The Bennetts also counterclaimed for breach of contract against plaintiffs, alleging that plaintiffs had materially breached the contract “by not completing the work in a timely fashion and in a workman like manner pursuant to the terms of the Contract,” and for intentional interference with economic relations. SunTrust asserted a counterclaim for a declaratory judgment that plaintiffs’ lien claim is invalid or, in the alternative, that SunTrust’s deed of trust has priority over that claim.

The case was tried to the court. On May 4, 2007, the court issued an opinion, ruling in favor of the Bennetts and SunTrust on the construction lien claim and awarding plaintiffs $40,000 in damages against the Bennetts under either a breach of contract or quantum meruit theory.

As to determination of damages, the trial court understood plaintiffs to have alleged that the Bennetts had breached the contract by (1) “failing and refusing to pay Plaintiffs the balance due them under the construction agreement” (“count two” of plaintiffs first claim for relief); and (2) by “wrongfully terminating the contract, precluding Plaintiffs from completing the agreement causing Plaintiffs *211 $40,000 in lost profits” (plaintiffs second claim for relief). The court explicitly found that defendants had breached the contract and that plaintiffs had not breached the contract; thus, there was no basis for “reducing Plaintiffs’ damages by the amount of the alleged construction defects.” Ultimately, however, the court awarded plaintiffs $40,000, reasoning that, although plaintiffs claimed compensatory damages of $63,113.05, the amount awarded could not exceed the amount that plaintiffs had pleaded in lost profits under their second claim for relief.

After the court had issued its opinion, but before it entered judgment, plaintiffs challenged the court’s calculation of damages. Specifically, plaintiffs argued that the court had incorrectly “limit[ed] the plaintiffs’ recovery on their first claim for relief [counts two and three] because of lost profit damages pleaded in the plaintiffs’ second claim for relief.” The court rejected that argument and entered a general judgment consistent with, and incorporating, the court’s earlier opinion. This appeal followed. 6

On appeal, plaintiffs reassert their argument that the court erred in awarding them $40,000 in damages rather than $63,113.05 on their first claim for relief. Defendant responds, first, that the claim of error is not preserved for our review. On the merits, defendant contends that the trial court’s award of $40,000 in compensatory damages to plaintiff is supported by evidence in the record and, thus, must be affirmed. See, e.g., Eden Gate, Inc. v. D&L Excavating & Trucking, Inc., 178 Or App 610, 619, 37 P3d 233 (2002).

As an initial matter, we disagree with defendant that plaintiffs’ claim of error was not adequately preserved. “[W]e have held that, when a trial court issues a memorandum opinion that is predicated on a legally erroneous determination of damages, it is incumbent upon the party disadvantaged by that error to bring it to the trial court’s attention before the entry of judgment.” Northwest Country Place v. NCS Healthcare of Oregon,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
236 P.3d 745, 236 Or. App. 206, 2010 Ore. App. LEXIS 730, Counsel Stack Legal Research, https://law.counselstack.com/opinion/calhoun-v-bennett-orctapp-2010.