Calhoon v. Communications Systems Construction, Inc.

489 N.E.2d 23, 140 Ill. App. 3d 1012, 95 Ill. Dec. 71, 1986 Ill. App. LEXIS 1808
CourtAppellate Court of Illinois
DecidedFebruary 6, 1986
Docket5-85-0242
StatusPublished
Cited by7 cases

This text of 489 N.E.2d 23 (Calhoon v. Communications Systems Construction, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Calhoon v. Communications Systems Construction, Inc., 489 N.E.2d 23, 140 Ill. App. 3d 1012, 95 Ill. Dec. 71, 1986 Ill. App. LEXIS 1808 (Ill. Ct. App. 1986).

Opinion

JUSTICE WELCH

delivered the opinion of the court:

Plaintiffs Wayne and Shelbina Calhoon and Lawrence and Ina Fosse commenced this action against defendant Communications Systems Construction, Inc. (CSC), based on CSC’s construction of a cable television transmission line across real property owned by the Calhoons and Fosses. After a bench trial, the circuit court of Johnson County entered judgment for the Calhoons in the amount of $528, and for the Fosses in the amount of $507, and ordered that CSC raise its cable line at least four feet over both parcels of land. The Calhoons and the Fosses appeal seeking removal of CSC’s cable, poles and other equipment from their properties and damages for trespass. CSC cross-appeals from that portion of the judgment which requires CSC to raise its cable line.

The case arises from CSC’s construction of a cable television line along the west side of Illinois Route 37 in Johnson County north of Goreville. The Calhoons’ farm fronts the west side of Route 37 for about half a mile; the Fosses’ farm has about 531 feet of highway frontage north of the Calhoons’ farm. On or about February 20, 1984, CSC began suspending its cable from Central Illinois Public Service Company (CIPS) poles along Route 37, first along the Calhoon farm, then along the Fosse farm. There is no dispute that the poles are located on private property and not on the right-of-way. CIPS had the benefit of an easement with respect to the poles. CSC and CIPS entered into a “pole lease agreement” which permitted CSC to use the poles subject to various technical requirements. The pole lease agreement required CSC to furnish CIPS with evidence that CSC had secured the necessary easements. It is undisputed that neither the Calhoons nor the Fosses granted CSC any easement or permission to construct the lines in question.

Mr. Calhoon testified as follows: He first became aware that CSC was suspending its line from poles on his property on February 20, 1984, when he saw the work in progress. He telephoned CIPS to see whether CSC had an agreement with CIPS to do the work. Then he telephoned David Weatherly, president of CSC, who said he would be there in one hour to shut the job down. When Mr. Weatherly arrived, Mr. Calhoon repeated his demand that the work be stopped. Mr. Calhoon also telephoned his attorney for advice regarding the extent of damages. Mr. Calhoon and Mr. Weatherly then agreed that CSC would pay $500 for damages, and Mr. Weatherly paid Mr. Calhoon with a check which bore the notation “damages.” Mr. Calhoon deposited the check and was later notified that payment of the check was stopped. CSC’s construction of the line on the Calhoon farm lasted another three full working days after February 20. Mr. Calhoon spoke with Curtis Miller, a CSC foreman, after February 20, though Mr. Calhoon did not further specify the date: Mr. Miller told him the construction would continue the next day; Mr. Calhoon replied that he would have him arrested; the next day, the workmen arrived and Mr. Calhoon telephoned the sheriff, who said the State’s Attorney advised “that there was a statute *** and they advised me to let them go ahead and construct the line and *** I could file suit later.” The Calhoons’ catalpa tree was trimmed by CSC employees on February 20 before Mr. Calhoon realized workers were there. The tree had been trimmed previously by CIPS, but in Mr. Calhoon’s opinion CSC had cut it more severely and damaged it. According to Mr. Calhoon, cable-to-ground clearance was 16 feet 2 inches at the center of his driveway. He voiced concern that if he ever needed to load his combines on trucks they would not clear the cable. In very muddy weather the combines rode on “tracks” and were hauled to the field on a flatbed, which could pose a clearance problem. However, there had been no clearance problems as of the November 1, 1984, trial.

Mr. Weatherly admitted writing and delivering the $500 check marked “damages” and stopping payment on advice of counsel. He testified that when the construction began he believed CSC had the benefit of the CIPS easements under the pole lease agreement and CSC’s franchise agreement with Johnson County. The afternoon of February 20, following the incident with Mr. Calhoon, Mr. Weatherly telephoned CIPS and was informed that CSC had no easement. Despite learning on February 20 that CSC had no easement on the Calhoon farm, Mr. Weatherly continued the construction on the advice of counsel that he was protected by a statute (Ill. Rev. Stat. 1983, ch. 34, par. 429.24.1).

Mr. Fosse also testified at trial. Mr. Fosse indicated no problems with cable-to-ground clearance. Mr! Fosse’s major concern was the increased difficulty of mowing his lawn in the vicinity of a new pole and guy wire erected by CSC on his property along the cable line.

Curtis Miller, a CSC foreman, testified at trial regarding his initial belief that CSC had an easement on plaintiffs’ property, and the information he thereafter received from Mr. Weatherly that CSC had no easement and that Mr. Weatherly believed CSC was protected by statute. Mr. Miller confirmed that he spoke with Mr. Calhoon after Mr. Weatherly had done so and that he informed Mr. Calhoon that CSC would continue to build despite his wishes.

Mr. Weatherly testified that CSC’s cable was suspended 40 inches below the CIPS cable pursuant to specifications in the pole lease agreement which incorporated safety standards contained in the National Electrical Code. According to Mr. Weaterly, it would cost CSC $15,000 to move CSC’s line and equipment across Route 37 or to bury it; other solutions would be even more costly.

The trial court entered judgment for the Calhoons for $528, and for the Fosses for $507, the difference apparently attributable to the testimony of Mr. Calhoon and Mr. Fosse regarding labor expended in cleaning the work sites. The court refused to order CSC to remove its equipment from the Calhoon and Fosse farms. After hearing plaintiffs’ post-trial motion, the court modified the judgment, requiring CSC to raise its cable line at least four feet above the Calhoon and Fosse farms. The Fosses and the Calhoons appeal, arguing that CSC should be required to remove all of its equipment from their property and that the cause should be remanded for a hearing to fix damages for trespass. CSC cross-appeals from that portion of the judgment which'requires it to raise its cable line.

CSC now concedes that it had no right to be on plaintiffs’ property. Should CSC have been required to remove its equipment from plaintiffs’ property? CSC argues that what plaintiffs seek is essentially injunctive relief, which should be granted only on plaintiffs’ showing of necessity and the inadequacy of any remedy at law, i.e., damages in this case. CSC relies on the proposition familiar to cases where one landowner’s construction encroaches upon the land of an adjoining landowner, that courts will refuse injunctive relief (i.e., tearing down the construction) and leave the complaining party to his remedy at law (i.e., damages), provided that the encroachment is slight and unintentional, the cost of removing it is great, and the corresponding benefit to the adjoining owner of removal is small. (Stroup v. Codo (1965), 65 Ill. App. 2d 396, 401, 212 N.E.2d 518

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Downing v. Somers
2023 IL App (4th) 220900 (Appellate Court of Illinois, 2023)
Whitlock v. Hilander Foods, Inc.
Appellate Court of Illinois, 1999
Lake Barrington Shore Condominium Ten Homeowners Ass'n v. May
553 N.E.2d 814 (Appellate Court of Illinois, 1990)
Crain Enterprises, Inc. v. City of Mound City
544 N.E.2d 1329 (Appellate Court of Illinois, 1989)
Tamalunis v. City of Georgetown
542 N.E.2d 402 (Appellate Court of Illinois, 1989)
Brinkley v. Brinkley
529 N.E.2d 70 (Appellate Court of Illinois, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
489 N.E.2d 23, 140 Ill. App. 3d 1012, 95 Ill. Dec. 71, 1986 Ill. App. LEXIS 1808, Counsel Stack Legal Research, https://law.counselstack.com/opinion/calhoon-v-communications-systems-construction-inc-illappct-1986.