Calderone v. Mancino (In Re Calderone)

166 B.R. 825, 1994 Bankr. LEXIS 661, 1994 WL 178225
CourtUnited States Bankruptcy Court, W.D. Pennsylvania
DecidedApril 29, 1994
Docket19-20317
StatusPublished
Cited by3 cases

This text of 166 B.R. 825 (Calderone v. Mancino (In Re Calderone)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Calderone v. Mancino (In Re Calderone), 166 B.R. 825, 1994 Bankr. LEXIS 661, 1994 WL 178225 (Pa. 1994).

Opinion

MEMORANDUM OPINION

BERNARD MARKOVITZ, Bankruptcy Judge.

Debtor Frank A. Calderone, doing business as Frank A. Calderone Construction (hereinafter “debtor”), has brought this adversary action against Frank Mancino and Marian Mancino (hereinafter “defendants”) for breach of contract. He seeks to recover a final payment of $20,000.00 for constructing a residential dwelling for defendants plus an additional sum of $5,324.61 for “overages” incurred therein.

Defendants have conceded that debtor is entitled to a nominal amount for “overages” but steadfastly deny that he is entitled to the final payment of $20,000.00 because he breached the contract by refusing to complete the project. They seem to aver that as debtor never completed the project that he had no entitlement to the final payment and, therefore, said final payment held by the bank never became estate property. As they have ultimately fulfilled debtor’s incomplete task, defendants continue, they have a right to the res.

Defendants further assert that they have suffered damages as a result of debtors’ various breaches which considerably exceed the amount to which debtor is entitled in “overages”. They seek to set off the amount due and owing to debtor against a portion of their damages and have counterclaimed for a monetary judgment in their favor for the balance thereof.

In accordance with the reasoning set forth below, debtor’s request for a monetary judgment in his favor will be denied in its entirety. Additionally, defendants will be permitted to set off the amount to which debtor is entitled for “overages” against a portion of their damages which result from debtor’s breach of the contract. Defendants’ counterclaim for a monetary judgment in their favor for the remainder of their damages, however, will be rejected.

-I-

FACTS

Debtor is an architect and a contractor who hold himself out as an expert in the construction of single-unit residential dwellings. He avers he has designed approximately fifty (50) and has constructed approximately twenty (20) such units.

Defendants had been having problems with a contractor building another home for them and retained debtor in 1986 to complete the project. Defendants were satisfied with *827 debtor’s performance in connection with that project.

Several years later, defendants decided to have another home built. They ultimately retained debtor to construct a dwelling which debtor had designed for them.

On April 28, 1992, debtor and defendants executed a document entitled “Form Of Agreement Between The Owner And Contractor”, wherein debtor agreed to construct a two-story single-unit residential dwelling for defendants. The contract price was $200,000.00.

Work on the project was to commence within fourteen (14) days of the signing of the agreement or approval by the lending institution financing the construction. The project was to be completed “approximately by 180 days ... from commencement (weather permitting) and no unforseen delays”. The agreement contained the following provision:

All time limits in the Contract Documents are of the essence of the Contract.... If the Contractor is delayed at any time in progress of the work by.... causes beyond the contractor’s control, then the contract shall be extended for a reasonable commensurate period of time equal to the delay without further compensation.

Other documents also were executed at the same time and were integrated into the above agreement.

For instance, a document entitled “Allowance Schedule” provided that the total contract price of $200,000.00 included an allowance of $29,236.00 for certain specified fixtures which defendants were to select from vendors of their own choosing. The identified items included: kitchen cabinets; appliances; lighting and plumbing fixtures; carpets; ceramic tile; mirrors; draperies; landscaping; and security system. Any amount in excess of the total allowance was to be paid by defendants out of their own pocket and was not included in the contract price. If the total amount was less than $29,236.00, the difference was to be refunded to defendants.

On June 15,1992, after the lending institution from whom defendants obtained financing had approved the above agreement, debt- or and defendants executed a document entitled “Construction Agreement” wherein debtor again agreed to construct the above dwelling for defendants for the price of $200,-000.00. This latter document provided that debtor was to be paid according to the following schedule:

Foundation completed $ 20,000.00

Raised and sheathed 40,000.00

Rough plumbing, heating and roofing 36,000.00

Brickwork, siding and roofing 36,000.00

Plastering, concreting 20,000.00

Trimmed out and tile work 28,000.00

Completed 20,000.00

$200,000.00

Work on the project commenced on June 29, 1992, when debtor began digging trenches for the footers.

According to the time frame set forth in the initial agreement, the project should have been completed by no later than December 26, 1992. Debtor repeatedly assured defendants that “they would be in their new home by Christmas”. These assurances were without any foundation, as the project was beset with significant delays.

For instance, excavation of the lot and the laying of the footers fell well behind schedule. Only the footers and a few rows of concrete blocks were in place approximately six (6) weeks after debtor began the project. Nothing further had been done. Only the foundation and the shell of the house had been erected by October of 1992. The plumbing, electrical wiring, heating, brickwork, roofing, plastering, and tile work had not yet commenced.

During the course of construction, defendants exceeded the scheduled allowance of $29,236.00 by ordering more expensive fixtures.

Defendants were not able to move into the dwelling at the end of December of 1992, as provided for under the contract, due to several untold delays. The bricks on the exteri- or of the dwelling had not yet been laid and much of the interior had not been finished by then.

On March 30, 1993, more than ninety (90) days after the anticipated completion of the *828 project, defendants finally moved into the dwelling. A considerable portion of the work remained to be completed when they moved in. For instance, only one of the entrances to the dwelling had been completed. Debtor had not built the deck • provided for in the drawings; had not completed the concrete work; and had not installed a storm pit to collect water draining off the roof which complied with municipal regulations. In addition, the window grills and screens and air conditioner had not been installed.

Debtor had been paid a total of $180,000.00 of the contract price by April of 1993. He had not, however, been paid the final payment of $20,000.00 which was due upon completion of the project.

On April 17, 1993, debtor sent a letter to defendants demanding payment in the amount of $4,111.83 for “overages”.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
166 B.R. 825, 1994 Bankr. LEXIS 661, 1994 WL 178225, Counsel Stack Legal Research, https://law.counselstack.com/opinion/calderone-v-mancino-in-re-calderone-pawb-1994.