Cajun Contractors, Inc. v. Lafayette Consolidated Government

715 So. 2d 588, 1998 WL 315538
CourtLouisiana Court of Appeal
DecidedJune 17, 1998
DocketNo. 98-180
StatusPublished
Cited by1 cases

This text of 715 So. 2d 588 (Cajun Contractors, Inc. v. Lafayette Consolidated Government) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cajun Contractors, Inc. v. Lafayette Consolidated Government, 715 So. 2d 588, 1998 WL 315538 (La. Ct. App. 1998).

Opinion

I THIBODEAUX, Judge.

This appeal involves a dispute between Cajun Contractors, Inc. (hereinafter “Cajun”) and Lafayette City-Parish Consolidat[589]*589ed Government — Lafayette Utilities Systems (hereinafter “LUS”) regarding delay damages associated with the construction of improvements to a water treatment plant. Pursuant to the provisions of a contract between the parties, Cajun requested that LUS submit the matter to arbitration to resolve the dispute. LUS refused to enter arbitration, asserting that the 12arbitration provision in the construction contract was invalid and nonbinding as between the parties.

Cajun subsequently filed a petition to enforce arbitration against LUS. After a hearing on the matter, the trial court entered judgment in favor of Cajun compelling both parties to submit their contractual claims and disputes to arbitration. It also awarded $250.00 in attorney fees to Cajun. From this judgment, LUS appeals. Cajun answers the appeal and requests damages against LUS for filing a frivolous appeal.

Based on the following reasons, we affirm the judgment requiring Cajun and LUS to arbitrate and reverse the award of attorney fees. We further conclude that this is a frivolous appeal filed by LUS. We, therefore, assess attorney fees against LUS in favor of Cajun in the amount of $5,000.00 and award damages against LUS and remand to the district court for a hearing on the appropriate amount of damages.

I.

ISSUES

We shall consider:

1. whether the trial court erred in determining that the arbitration clause in the construction contract was valid and enforceable, in light of La.R.S. 38:2217 and La.R.S. 38:2243;
2. whether the trial- court erred in finding that the arbitration clause in the construction contract mandated the arbitration of claims for “sums due under the contract,” as well as, the arbitration of claims for “damages;”
3. whether the trial court erred in its assessment of attorney fees against LUS; and
4. whether the appeal of LUS is a frivolous one and, if so, the appropriate sanctions and damages for filing this frivolous appeal.

J3II.

FACTS

On October 16, 1993, Cajun entered into a construction contract with LUS for the purpose of constructing improvements to a municipal water treatment plant. The contract was drafted by LUS and signed by Jerome Ducote, on behalf of Cajun, and by Mayor Kenny Brown, on behalf of the City of Lafayette.

After construction had commenced, a dispute arose between Cajun and LUS as to delay damages associated with the construction project. Cajun asserted that LUS and its engineers were solely accountable for the delays in construction and that Cajun was entitled to additional compensation for increased costs which resulted from such delays. Conversely, LUS alleged that Cajun and its subcontractors were primarily responsible for the deláys and that delay damages should be assessed against Cajun and withheld therefrom.

In light of the dispute over construction delays and in accordance with the arbitration clause of the construction contract, Cajun requested that LUS agree to submit the dispute to binding arbitration. LUS rejected Cajun’s request for arbitration and asserted that the arbitration clause was invalid and unenforceable under La.R.S. 38:2217 and 38:2243. Thereafter, Cajun filed a petition to enforce arbitration against LUS. On September 22, 1997, after reviewing the matter, the trial court granted judgment in favor of Cajun and ordered both parties to submit to arbitration for the resolution of their dispute over construction delays and related damages.

J4IIL

LAW & DISCUSSION

The Validity of the Arbitration Clause

LUS contends that the arbitration clause of the construction contract is contrary to the statutory intent and purpose of [590]*590La.R.S. 38:2217 and 38:2243. The clause is, thereby, invalid and unenforceable as between the two parties, LUS and Cajun. Specifically, LUS alleges that the arbitration clause does not provide either party with the authority to select or name the arbitrator(s) in accordance with La.R.S. 38:2217 and that such an omission must be judicially redressed. The defendant argues that an order requiring binding arbitration, in light of the alleged omission in the-clause, would constitute a denial of its nonwaiveable right of judicial review under La.R.S. 38:2217.

Further, LUS asserts that the arbitration clause is violative of La.R.S. 38:2243 because the clause inhibits the statutory provisions which mandate that a public body must file a concursus proceeding to adjudicate the claims of its lien claimants. Thus, it argues that neither LUS nor Cajun should be ordered to submit to binding arbitration. We disagree and find that the arguments of LUS lack merit.

The arbitration clause of the construction contract between Cajun and LUS reads as follows:

ARTICLE 12 DAMAGES

Any claim for damages arising under the Contract shall be made in writing to the party liable within a reasonable time of the first observance of such damage and not later than the time of final payment, except as expressly stipulated otherwise in the case of faulty work or material, and shall be adjusted by agreement or arbitration insofar as allowed by law. (Any damages to public or private property shall be immediately reported by the Contractor to the Owner or its assigned representative and to the owners of said property).

| sBased on our interpretation of this provision, any damages claim arising during the course of construction are to be resolved within a reasonable period after initial notice thereof, but prior to final payment. The clause further provides that in the event of a claim for damages, such a claim shall be resolved either by arbitration or by agreement between the parties.

Louisiana jurisprudence holds that “[a]ny contract entered into for the construction of a public work which is contrary to the provisions of La.R.S. 38:2211 through 38:2225 shall be null and void.” Bristol Steel & Iron Works, Inc. v. State, DOTD, 504 So.2d 941, 945 (La.App. 1 Cir.), reversed on other grounds, 507 So.2d 1233, 1236 (La.1987). Louisiana Revised Statute 38:2243, which governs petitions filed by authorities against contractors, provides:

A. If at the expiration of the forty-five days any filed and recorded claims are unpaid, the public entity shall file a petition in the proper court of' the parish where the work was done, citing all claimants and the contractor, subcontractor, and surety on the bond and asserting whatever claims it has against any of them, and shall require the claimants to assert their claims. If the governing authority fails to file the proceeding any claimant may do so.
B. All the' claims shall be tried in con-eursus and the claims of the claimants shall be paid in preference to the claims of the public entity.

Moreover, La.R.S. 38:2217, which governs independent arbitration and a party’s right to judicial review, states:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

E.C. Durr Heavy Equipment Co. v. Board of Commissioners
719 So. 2d 136 (Louisiana Court of Appeal, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
715 So. 2d 588, 1998 WL 315538, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cajun-contractors-inc-v-lafayette-consolidated-government-lactapp-1998.