Cadet Construction Company v. Archer Western Construction, LLC

Court of Appeals for the Fourth Circuit·Decided August 18, 2023·No. 22-1576·Unpublished

Opinion

UNPUBLISHED

UNITED STATES COURT OF APPEALS FOR THE FOURTH CIRCUIT

No. 22-1576

CADET CONSTRUCTION COMPANY, Plaintiff - Appellant,

v.

ARCHER WESTERN CONSTRUCTION, LLC; TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA,

Defendants - Appellees.

Appeal from the United States District Court for the Middle District of North Carolina, at Greensboro. Catherine C. Eagles, Chief District Judge. (1:20-cv-00737-CCE-LPA)

Submitted: April 26, 2023 Decided: August 18, 2023

Before GREGORY, AGEE, and WYNN, Circuit Judges.

Vacated and remanded by unpublished per curiam opinion.

ON BRIEF: Todd A. Jones, ANDERSON JONES, PLLC, Raleigh, North Carolina, for Appellant. Andrew P. Atkins, Mark M. Rothrock, SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P., Raleigh, North Carolina, for Appellees.

Unpublished opinions are not binding precedent in this circuit.

PER CURIAM:

Cadet Construction Company (“Cadet”) appeals from the district court’s judgment dismissing its claims with prejudice for failure to prosecute. In finding that dismissal with prejudice was necessary, the district court focused on Cadet’s failure to assist with efforts to schedule and complete arbitration over a period of several months. We hold that the dismissal constitutes an abuse of discretion because the district court did not properly account for extenuating circumstances that contributed to the delays—namely, severe health issues that Cadet’s Senior Vice President suffered during the period of time in question. We therefore vacate the judgment below and remand for further proceedings.

I.

Cadet initiated this action against Archer Western Construction, LLC (“AWC”) and Travelers Insurance Company (“Travelers”) (collectively, “Defendants”) in August 2020, alleging causes of action for claim on a payment bond, breach of contract, and quantum meruit. Cadet claimed that AWC, the contractor on a construction project, and Travelers, AWC’s surety, failed to pay Cadet, a subcontractor, over $1 million for work it performed. AWC filed a counterclaim against Cadet for breach of contract.

In December 2020, Cadet and Defendants jointly moved to refer the claims to arbitration. The district court granted their motion and stayed the proceedings until January 3, 2022. Pursuant to an arbitration agreement, the parties first engaged in mediation in February 2021, but mediation did not result in a settlement. From March to August, they

participated in discussions about selecting an arbitrator, mutually agreeing to extend the deadline for naming an arbitrator several times.

In May 2021, Jimmy Dillahunt, Cadet’s Senior Vice President, was diagnosed with cancer. Dillahunt underwent surgery in July and “spent most of the remainder of 2021” in recovery. J.A. 228. In an affidavit Cadet later submitted to the district court, Dillahunt explained that his diagnosis, treatment, and recovery “required [him] to take time away from the business of Cadet, including the direction of legal action . . .[,] to care for [his] personal health.” Id. He further explained that he is the “only office personnel” at the company and is “solely responsib[le] for the business decisions of Cadet, including those which pertain to legal action.” J.A. 227–28.

The parties tentatively selected an arbitrator in August 2021. Their arbitration agreement required them to split the costs of arbitration equally. After the arbitrator provided his hourly rate, Defendants formally approved his selection, but Cadet did not.

On September 8, 2021, Cadet’s counsel filed a motion to withdraw on the ground that Cadet had failed to pay reasonable attorneys’ fees for more than six months. Cadet’s counsel also asked the court to extend the end date of the stay from January 3, 2022, to June 3, 2022. Defendants did not object to the motion to withdraw or the motion to extend the stay.

On October 13, the district court granted Cadet’s counsel’s motion to withdraw. It directed Cadet to obtain new counsel and have them file a notice of appearance within thirty days, noting that “[f]ailure to do so may result in dismissal of this case without prejudice.” J.A. 168. The court denied Cadet’s motion to extend the stay; in its view, “an

extension of that length would cause an unwarranted delay,” and Cadet had failed to offer any “valid reason for such a lengthy extension.” J.A. 169.

Cadet retained new counsel, who filed a notice of appearance on November 12, exactly thirty days after the court’s order. Defendants claim that Cadet’s counsel did not respond to their emails about the case until the third week of December, when Cadet asked if Defendants would agree to a status report stating that the parties had formally selected the arbitrator and were moving forward. Cadet and Defendants filed a joint status report on January 3, 2022, which informed the district court that they had selected an arbitrator and were “working to establish a definite schedule for the arbitration.” J.A. 171. They also asked the court to continue the stay, which was set to end on January 3.

On January 5, the district court entered an order that extended the stay through April 14, 2022. The order stated that the court “expect[ed] the parties to immediately schedule the arbitration for a time within the first quarter of this year and to timely complete it.” J.A. 174. The court explained that it would dismiss the case “without prejudice” around April 15, 2022, if the parties did not file a motion by March 31 that showed “good cause for why a continued stay rather than dismissal is appropriate.” Id.

Defendants assert that in early January, its attorneys twice contacted Cadet’s attorneys to try to move the arbitration forward, but Cadet’s attorneys did not respond. On March 15, after receiving no communication from Cadet, Defendants filed a motion to lift the stay so they could file a Rule 41(b) motion to dismiss with prejudice. Cadet’s attorneys contacted Defendants’ attorneys only after Defendants filed the motion to lift the stay. The court lifted the stay for that limited purpose, and Defendants filed a motion to dismiss. In

its response to that motion, Cadet conceded that dismissal without prejudice was appropriate, but argued that the court should not dismiss with prejudice. Cadet did not ask the court to extend the stay beyond April 14.

Cadet submitted Dillahunt’s affidavit along with its response to the motion to dismiss. In addition to recounting his cancer diagnosis and treatment, Dillahunt explained that he struggled with a severe case of COVID-19 at the turn of the year. He experienced severe respiratory symptoms and was ultimately diagnosed with COVID pneumonia on January 11. Dillahunt received several forms of treatment for the illness and “suffered from continued severe respiratory symptoms” through early March. J.A. 229. Cadet’s response to the motion to dismiss was the first time the company argued that Dillahunt’s illness had prevented it from proceeding with the arbitration. 1 On April 27, the district court granted Defendants’ motion and dismissed the case with prejudice. To determine whether dismissal with prejudice was an appropriate sanction, the court applied the four-factor test the Fourth Circuit has articulated, looking to: “(1) the degree of personal responsibility on the part of the plaintiff, (2) the amount of prejudice to the defendant caused by the delay, (3) the presence or absence of a drawn out history of deliberately proceeding in a dilatory fashion, and (4) the effectiveness of sanctions less drastic than dismissal.” J.A. 244 (quoting Davis v. Williams, 588 F.2d 69, 70 (4th Cir. 1978)) (internal quotation marks omitted).

1

Defendants note that “Dillahunt’s medical condition was briefly mentioned near the time of the withdrawal of Cadet’s prior counsel” in September 2021, J.A. 232, but neither party provides further information about that disclosure.

Free access — add to your briefcase to read the full text and ask questions with AI

Cadet Construction Company v. Archer Western Construction, LLC, (4th Cir. 2023).

Cadet Construction Company v. Archer Western Construction, LLC (Cadet Construction Company v. Archer Western Construction, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Link v. Wabash Railroad
370 U.S. 626 (Supreme Court, 1962)
Paris Reizakis v. Albert E. Loy
490 F.2d 1132 (Fourth Circuit, 1974)
Homer Bush v. The United States Postal Service
496 F.2d 42 (Fourth Circuit, 1974)
Pauline McCargo v. Oley G. Hedrick
545 F.2d 393 (Fourth Circuit, 1977)
Davis v. Williams
588 F.2d 69 (Fourth Circuit, 1978)
Herbert v. Saffell
877 F.2d 267 (Fourth Circuit, 1989)
Ballard v. Carlson
882 F.2d 93 (Fourth Circuit, 1989)
United States v. Vidacak
553 F.3d 344 (Fourth Circuit, 2009)
United States v. Mario Ahlazshuna Dillard
891 F.3d 151 (Fourth Circuit, 2018)
Sharyl Attkisson v. Eric Holder, Jr.
925 F.3d 606 (Fourth Circuit, 2019)