C.A. Rasmussen, Inc., D/B/A Rasmussen Rail Group v. Linck, Joseph P., Global Stone, L.C. and Construction Linck

CourtCourt of Appeals of Texas
DecidedMarch 23, 2000
Docket13-98-00509-CV
StatusPublished

This text of C.A. Rasmussen, Inc., D/B/A Rasmussen Rail Group v. Linck, Joseph P., Global Stone, L.C. and Construction Linck (C.A. Rasmussen, Inc., D/B/A Rasmussen Rail Group v. Linck, Joseph P., Global Stone, L.C. and Construction Linck) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C.A. Rasmussen, Inc., D/B/A Rasmussen Rail Group v. Linck, Joseph P., Global Stone, L.C. and Construction Linck, (Tex. Ct. App. 2000).

Opinion

NUMBER 13-98-509-CV

COURT OF APPEALS

THIRTEENTH DISTRICT OF TEXAS

CORPUS CHRISTI

___________________________________________________________________

C. A. RASMUSSEN, INC., D/B/A

RASMUSSEN RAIL GROUP, Appellant,

v.

JOSEPH P. LINCK, INDIVIDUALLY AND D/B/A

GLOBAL STONE, L.C. AND CONSTRUCTION LINCK, Appellees.

___________________________________________________________________

On appeal from the 357th District Court

of Cameron County, Texas.

___________________________________________________________________

O P I N I O N

Before Chief Justice Seerden and Justices Dorsey and Chavez

Opinion by Chief Justice Seerden

This is a tortious interference with contract and negligence case. C.A. Rasmussen, Inc. ("Rasmussen"), appellant, appeals the judgment for Global Stone, L.C. ("Global"), appellee, awarding it compensatory and exemplary damages.

In 1995, the Port of Brownsville announced Phase II of its plan to construct a railroad line to the Port. Phase II called for nearly 45,000 tons of stone ballast to be placed underneath the rails and cross ties as a supporting bed. Global sold rock products which it received at its dock in the Port of Brownsville. Before the contract on Phase II was awarded, Global contacted all bidders, offering to supply the needed stone ballast. At the same time, it contacted Martin Marietta, a supplier of such ballast. Joseph Linck, owner of Global, sought to make his company Martin Marietta's exclusive sales agent for Phase II. The extent of the relationship between Global and Martin Marietta forms the basis for the present dispute.

The record indicates that Global offered to purchase ballast from Martin Marietta with hope to re-sell it to the project's contractor. The agreement between Martin Marietta and Global contemplated payment for the stone itself and delivery of same to Global's dock. Global also intended to profit by providing other services to the project's contractor. Those services were independent of the agreement between Global and Martin Marietta.

Rasmussen was awarded the contract on October 25, 1995. Between that date and February 2, 1996, Rasmussen and Global were involved in negotiations which proved fruitless. The record reflects that Rasmussen and Global could not agree on certain contractual terms related to "load out" of the ballast and storage. Needing the ballast to avoid costly delays, Rasmussen contacted Martin Marietta's representative, Dick Gage, and placed an order to purchase the ballast directly. Linck became aware of Rasmussen's efforts and faxed a letter to Gage confirming the validity of their exclusive agency agreement. There is evidence showing that Rasmussen was aware of the exclusive agency agreement when it purchased the ballast. However, the record also reflects that after selling the ballast to Rasmussen, Martin Marietta paid Global $2.70 per ton for receiving and handling the ballast. This price roughly corresponds to the difference between Martin Marietta's last quoted price to Linck ($12.50 per ton) and the price at which Linck would have sold the ballast to Rasmussen ($14.95 per ton). Martin Marietta acknowledged that it offered the money to make up Global's lost profit from the unrealized sale.

The ballast was delivered to Global's dock on March 6, 1996. The present litigation began at that point. Global refused to permit Rasmussen to enter onto its property to remove the ballast. Rasmussen subsequently filed suit and obtained a temporary restraining order to enter Global's property and remove the ballast. Rasmussen also sought damages for delays caused by Global's refusal to allow earlier access to the stone. However, during the loadout, Rasmussen removed some limestone from the Global dock and caused physical damage to Global's facility. Global then counterclaimed, alleging tortious interference with the Martin Marietta agency agreement and negligence. Global sought damages for lost profit on the resale of the ballast and also sought to recover for lost anticipated profits associated with its storage and loadout of the ballast for Rasmussen. Furthermore, Global sought to recover for the removed limestone and for physical damage to its facility.

The jury found that Rasmussen intentionally and wrongfully interfered with Global's exclusive sales contract with Martin Marietta and that the interference was not justified. The jury furthermore found that Rasmussen's negligence proximately caused damage to Global's facility. Based on these findings, the jury awarded Global $78,000 for past lost profits and lost sales of limestone, $10,000 future lost profits and lost sales of limestone, and $12,000 for physical damage done to Global's facility. Neither side contests either Rasmussen's liability for its negligence in damaging Global's dock or the extent of the damages awarded for that misfeasance.

By its first and second issues, Rasmussen contends that there was legally or factually insufficient evidence to support the jury's findings that it interfered with either an existing or prospective contract between Global and Martin Marietta. By its third issue, Rasmussen argues there was legally or factually insufficient evidence to support a finding of proximate cause related to the interference claim.

In conducting a legal sufficiency review, we may only consider the evidence and inferences tending to support the findings. This evidence must be viewed in a light most favorable to the findings and we must disregard any evidence or inferences to the contrary. Sherman v. First Nat'l Bank, 760 S.W.2d 240, 242 (Tex. 1988). So long as there is more than a scintilla of evidence supporting the finding, the challenge must be overruled. Id. By contrast, in a factual sufficiency review, we examine all of the evidence, regardless of its effect on the reviewed finding. Lofton v. Texas Brine Corp., 720 S.W.2d 804, 805 (Tex. 1986). We may reverse the challenged finding only if it is "so contrary to the overwhelming weight of the evidence as to be clearly wrong and unjust." Cain v. Bain, 709 S.W.2d 175, 176 (Tex. 1986).

In order to establish tortious interference with an existing contract, a plaintiff must prove: (1) the existence of a contract subject to interference; (2) a willful and intentional act of interference; and (3) that such interference proximately caused actual damages. Texas Beef Cattle v. Green, 921 S.W.2d 203, 210 (Tex. 1995). Once the existence of a contract is established, we must consider whether or not there was any interference with that contract. Holloway v. Skinner, 898 S.W.2d 793, 794-95 (Tex. 1995). Interference with a contract is tortious only if it is intentional. Southwestern Bell Tel. Co. v. John Carlo Tex., Inc., 843 S.W.2d 470, 472 (Tex. 1992).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Portlock v. Perry
852 S.W.2d 578 (Court of Appeals of Texas, 1993)
Lofton v. Texas Brine Corp.
720 S.W.2d 804 (Texas Supreme Court, 1986)
Texas Beef Cattle Co. v. Green
921 S.W.2d 203 (Texas Supreme Court, 1996)
Montgomery County Hospital District v. Brown
965 S.W.2d 501 (Texas Supreme Court, 1998)
Missouri Pacific Railroad v. Lemon
861 S.W.2d 501 (Court of Appeals of Texas, 1993)
Travis v. City of Mesquite
830 S.W.2d 94 (Texas Supreme Court, 1992)
Southwestern Bell Telephone Co. v. John Carlo Texas, Inc.
843 S.W.2d 470 (Texas Supreme Court, 1993)
Hill v. Heritage Resources, Inc.
964 S.W.2d 89 (Court of Appeals of Texas, 1998)
Sherman v. First National Bank in Center
760 S.W.2d 240 (Texas Supreme Court, 1988)
Holloway v. Skinner
898 S.W.2d 793 (Texas Supreme Court, 1995)
Exxon Corp. v. Allsup
808 S.W.2d 648 (Court of Appeals of Texas, 1991)
Browning-Ferris, Inc. v. Reyna
865 S.W.2d 925 (Texas Supreme Court, 1994)
Cain v. Bain
709 S.W.2d 175 (Texas Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
C.A. Rasmussen, Inc., D/B/A Rasmussen Rail Group v. Linck, Joseph P., Global Stone, L.C. and Construction Linck, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ca-rasmussen-inc-dba-rasmussen-rail-group-v-linck--texapp-2000.