C. R. Fedrick, Inc. v. State Board of Equalizer

204 Cal. App. 3d 252, 251 Cal. Rptr. 305, 101 Oil & Gas Rep. 628, 1988 Cal. App. LEXIS 851
CourtCalifornia Court of Appeal
DecidedAugust 11, 1988
DocketC002267
StatusPublished
Cited by3 cases

This text of 204 Cal. App. 3d 252 (C. R. Fedrick, Inc. v. State Board of Equalizer) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. R. Fedrick, Inc. v. State Board of Equalizer, 204 Cal. App. 3d 252, 251 Cal. Rptr. 305, 101 Oil & Gas Rep. 628, 1988 Cal. App. LEXIS 851 (Cal. Ct. App. 1988).

Opinion

Opinion

BLEASE, J.

The State Board of Equalization (Board) appeals from a judgment granting a recovery of sales taxes as having been erroneously collected (Rev. & Tax. Code, § 6933). The matter arises out of a contract between C. R. Fedrick, Inc. (Fedrick), and the United States for modification of facilities for separation and distribution of petroleum and natural gas extracted at the Naval Petroleum Reserve No. 1, Elk Hills, California. The question is whether or not property Fedrick purchased for use in the performance of the contract is subject to sales tax under Revenue and Taxation Code section 6384. Section 6384 provides that purchases of prop *255 erty so used are subject to the tax if the contract is “for the construction of improvements on or to real property in this state.” The Board contends that the trial court erred in finding the purchases outside the scope of section 6384. We agree.

Factual and Procedural Background

In January 1981, Fedrick contracted for the approximate sum of $18.5 million to perform the following work: “General Description— The work consists of modification of 32 existing Stevens Zone tank setting facilities, the installation of three new gage settings and connecting well flow lines, a new common oil surge facility with vapor recovery compressors, a new low pressure gas gathering compressor plant, Shallow Zone Gas field collection piping, Zero Pressure Casing Gas field collection piping, and a Zero Pressure Casing gas compressor facility. This project is sub-divided into two construction phases. The first phase shall include modifications to the 16 eastern tank settings, installation of three new gage settings with connecting well flow lines, a new oil surge facility with vapor recovery compressors in the Northern R area, a new low pressure gas gathering compressor plant. Shallow Zone Gas field collection piping. Zero Pressure Casing field collection piping and Zero Pressure Casing Gas compressor facility. The second phase will be limited to modification of the 16 western tank settings. For exact list of modified tank settings, see Section 01100-30, paragraph 24 of this specification. The work comprises furnishing all materials, their handling, transportation, installation, assembly, alignment, testing and check out of equipment, instruments, and piping as defined by these Specifications and accompanying Drawings. The work includes the furnishing of new oil, gas and hydrocarbon condensate piping in the new areas and the installation of loop lines paralleling certain of the existing lines serving modified locations. Government-Furnished Materials listed in this section consists of existing equipment and new long delivery materials and equipment such as the compressors, pumps, separators, and part of instruments for the first four of the tank settings to be modified. The work includes transportation, installation, assembly, alignment, testing and check out of the new and surplus equipment and instruments and the furnishing of necessary materials to install this Government-Furnished Material as complete and operable systems. Work to be done by others is also listed in this section.” Change orders resulted in final compensation to Fedrick in an amount exceeding $23 million. The amount of tax which Fedrick claims was erroneously collected is $302,359.38.

The tank setting facilities are collection facilities for the output of a number of oil wells. The output of the wells is piped as much as a mile to the tank setting where gas is separated from oil. The gas is then routed to *256 processing plants for processing and sale or is recirculated to the oil wells to assist in the production of more oil. The oil is stored in a holding tank and later pumped to a central location from half a mile to 12 miles away for further processing. Fedrick installed new pipelines from the wells to the tank settings. At the tank settings are various components or vessels connected by pipes for processing, storing, and pumping. Most components were installed by placing them on concrete foundations in which bolts are embedded. These bolts are similar in nature to those used to bolt a house to its foundation. The components are then fastened by means of nuts or nuts and clips. Some of the foundations were poured by Fedrick and some were in existence already.

Charles Fedrick, the president of Fedrick, described the work at the tank settings as follows: “Oh, well we take 32 facilities what were existing, we came in and we removed the facilities and set them off to the side, demolished them. And then we reinstalled portions of the old facilities and actually some of the vessels were stayed [szc] right in place. And then we added vessels and changed all new piping and all new valves and instrumentation and separators and then tied in the system into the gas wells coming as well as running lines from the gas wells into them.” Fedrick also installed some components from the oil field’s “surplus yard.” In addition to installation of components, Fedrick “brought electricity” to the sites and converted pumps from gasoline power to electricity.

The largest components of the tank settings are 500- to 1,000-barrel tanks. The testimony at trial was that all such tanks were actually supplied by the United States rather than by Fedrick. The contract specifications had called for Fedrick to furnish two 1,000-barrel tanks.

Everything that was installed that is a subject of this lawsuit is readily removable as units. The various components or vessels are connected to the pipes by flanges. The flange consists of two trumpet-shaped segments presenting matching disks with holes which are bolted together sandwiching a gasket between them. One side is connected to the component, the other is welded to the piping. Flanges allow easy disconnection of the components. However, as a practical matter, flanges would be the means of coupling whether the installation were permanent or temporary.

Fedrick removed quite a bit of pipe. This is accomplished by cutting the pipe with a cutting torch or unbolting a flange. The same procedure could be used to relocate pipe. The pipe sections running from well to pump setting and from pump setting to the central location are welded together. These pipe runs lie on wooden sleepers like railroad ties. The ties are staked into the ground with steel stakes that project a couple of feet into the *257 ground. The stakes project above the sleepers and help keep the pipe from slipping off of the sleepers. At some points pipelines cross underneath roads. Where this occurs the pipe is normally inside of a larger piece so that the interior pipe could be removed at any time. The pipe is unpainted. The area is arid and an unpainted pipe could last 40 years without rusting out. Charles Fedrick opined that removal of the pipe would damage neither the pipe nor the realty.

Fedrick also completed two new compressor stations. A compressor station is necesssary to transport gas to the central location where it is refined. The compressors “usually” come in about three pieces to facilitate lifting for weight and are mounted on skids. They sit on concrete slabs and are attached to the concrete by anchor bolts.

The Elk Hills reserve is approximately 90 square miles in area. There are perhaps 200 tank settings. Charles Fedrick testified that wells run dry and new wells are employed at Elk Hills all the time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brink Electric Construction Co. v. Arizona Department of Revenue
909 P.2d 421 (Court of Appeals of Arizona, 1995)
Overhead Electric Co. v. State Board of Equalization
227 Cal. App. 3d 1230 (California Court of Appeal, 1991)
Associated Beverage Co. v. Board of Equalization
224 Cal. App. 3d 192 (California Court of Appeal, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
204 Cal. App. 3d 252, 251 Cal. Rptr. 305, 101 Oil & Gas Rep. 628, 1988 Cal. App. LEXIS 851, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-r-fedrick-inc-v-state-board-of-equalizer-calctapp-1988.