C. B. Chittim v. Texas Pacific Coal and Oil Company, a Corporation

317 F.2d 81, 19 Oil & Gas Rep. 280, 1963 U.S. App. LEXIS 5284
CourtCourt of Appeals for the Tenth Circuit
DecidedMay 16, 1963
Docket7206_1
StatusPublished
Cited by3 cases

This text of 317 F.2d 81 (C. B. Chittim v. Texas Pacific Coal and Oil Company, a Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. B. Chittim v. Texas Pacific Coal and Oil Company, a Corporation, 317 F.2d 81, 19 Oil & Gas Rep. 280, 1963 U.S. App. LEXIS 5284 (10th Cir. 1963).

Opinion

HILL, Circuit Judge.

C. B. Chittim, appellant, commenced this action in the state court against Texas Pacific Coal and Oil Company, appellee, for the alleged breach of what is commonly known in the oil and gas industry as a farmout agreement, providing for the drilling of an oil and gas well in Crook County, Wyoming. Texas Pacific, with a corporate existence in the State of Texas, removed the same to the Federal court, where trial was had to the court, without a jury, resulting in a judgment against appellant. Judgment was also entered allowing appellee recovery against Chittim on a counterclaim for money expended as attorney fees in contesting lien claims against the oil and gas well in question. Chittim’s appeal followed.

In pertinent part, the farmout agreement provided: Chittim was to commence the actual drilling of a test well upon the lease belonging to Texas Pacific on or before October 5, 1959; he was to complete the same, without cost to Texas Pacific, within 60 days; the drilling must continue to a depth of 3500 feet, or to a sufficient depth to test the Minnelusa formation, or to a depth where conditions made drilling impracticable; the judgment of Texas Pacific was conclusive as to identity of all formations, the depth at which such formations were encountered, the sufficiency of tests and whether or not any fluid recovered was in conclusive quantities; if a producing well was drilled, Chittim, at his sole expense, was to complete and fully equip the well for production into tanks; if a dry hole was drilled, Chittim was to properly plug and abandon the same at his sole expense; if a dry hole was timely drilled and completed, Texas Pacific was to execute and deliver to Chittim an assignment of an undivided one-half interest in the lease; and if the well was completed as a producer in commercial quantities, the parties agreed to enter into a joint operating agreement, with the precise terms of that prospective agreement set out. Also, under the agreement, Chittim agreed to indemnify and hold Texas Pacific harmless from loss by reason of any claim arising out of the operations; he agreed to pay an equal share of all delay rentals and minimum royalties; and Texas Pacific agreed to pay Chittim the sum of $3800.-00 as dry hole money because of a dry hole previously drilled as an offset well to the lease involved and known as the Barton No. 2.

The complaint alleged: The execution of the farmout agreement; Chittim had fully performed, or. was ready and willing at all times to perform, all of the provisions of the agreement; after repeated demands Texas Pacific failed and refused to perform its part of the contract; and by reason of such breach, he was entitled to recover damages in the amount of $1,465,000.00. Appellee’s answer and counterclaim denied any breach on its part and alleged: Chittim failed to complete either a producing well or a dry hole within 60 days or without cost to it; Chittim failed to make satisfactory production tests; he failed to furnish defendant with drilling reports or copies of the required State of Wyoming forms as provided for in the agreement; he failed to reimburse it for delay rentals paid, and did not indemnify and hold it harmless because of claims arising out of the drilling operations. Appellee also pleaded estoppel and waiver as affirmative defenses and set up three counterclaims, the only one with which we are concerned being for attorney fees paid by Texas Pacific in defending against lien claims made by third parties against the lease because of Chittim’s drilling operations.

*83 The test well, known as the State No. 6 well, was timely commenced by Chittim and drilling operations were continued to a depth of about 3900 feet. It was apparently assumed by Chittim at that time that the well could be completed as a commercial producer as production casing was then set. This drilling depth met the depth requirements of the agreement. Various tests were made upon the well at this point in the drilling efforts and the well was swabbed at the rate of 5 barrels of oil per hour. On about December 1, 1959, a pump was installed on the well and connected with a temporary tank installation. From this time on, difficulties were encountered in producing oil in commercial quantities from the well. A permanent tank battery was ordered by Chittim to replace the temporary tank and was delivered to the well site, but it is undisputed that the permanent tanks were never set or used and were eventually repossessed by the vendor. Chittim’s experts testified that the well was completed as a producer, but experts on behalf of Texas Pacific disagreed and testified that the well was not completed because the permanent tanks had not been set in cement and connected to the pump by Chittim as called for by the farmout agreement. Between December 1, 1959, and January 1, 1959, some oil, together with other fluids, was pumped from the well, but, on or about the later date, Chittim caused the well to be shut down and did nothing thereafter to complete the well, under the terms of the agreement, as either a commercial producer or as a dry hole.

In December, Chittim first asked Texas Pacific to pay him the $3,800.00 dry hole money for his drilling of the Barton No. 2, which he had drilled prior to the commencement of the well in question. The evidence is clear that he was in financial difficulties and Texas Pacific did, on January 15, 1960, make this payment to him. Chittim, after shutting down the well in question, made several futile attempts to procure a new farmout agreement with Texas Pacific. In March, 1960, Chittim requested an assignment of a part of the lease under the “dry 'hole” provision of the farmout agreement, which demand was refused. Eventually both materialmen’s and mechanics’ liens were filed by Chittim’s creditors against the drill site of State No. 6, and Texas Pacific was compelled to later go into court and defend foreclosure suits involving these liens in order to protect its lease. During the course of this lien litigation, one of the lien holders, by agreement with Texas Pacific, pulled and salvaged the well casing, and plugged the well in accordance with requirements of the State of Wyoming relating to the abandonment of a dry hole. In the defense of these lien suits, Texas Pacific paid $1,128.28 as attorney fees. The evidence also shows that Chittim failed to pay his share of the delay rentals upon the lease and admitted to Texas Pacific his bad financial condition and financial inability to do anything more on the well.

With these evidentiary facts before him, the trial judge found that Chittim failed to sustain his burden of proof; that Texas Pacific did not breach the agreement; that Chittim failed to perform his part of the agreement in that he did not complete a producing well at his sole expense or at all and failed to perform under the alternatives available in the event of a non-producer; and that Texas Pacific was entitled to recover $1,128.28 for attorney fees paid defending the lien claims.

Appellant argues seven points of error on this appeal. However, as we view the case, it is primarily one of fact, and a determination of the sufficiency of the evidence to support the trial court’s findings will adequately dispose of all questions raised here. And, of course, those findings must be accepted upon appeal if they are supported by the record. Wise v. United States, 10 Cir., 297 F.2d 822, cert. denied, 369 U.S. 876, 82 S.Ct. 1148, 8 L.Ed.2d 279.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
317 F.2d 81, 19 Oil & Gas Rep. 280, 1963 U.S. App. LEXIS 5284, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-b-chittim-v-texas-pacific-coal-and-oil-company-a-corporation-ca10-1963.