C & A, S.E. v. Rio Mar North Zone Development Corp.

CourtUnited States Bankruptcy Court, D. Puerto Rico
DecidedOctober 28, 2008
Docket05-00234
StatusUnknown

This text of C & A, S.E. v. Rio Mar North Zone Development Corp. (C & A, S.E. v. Rio Mar North Zone Development Corp.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C & A, S.E. v. Rio Mar North Zone Development Corp., (prb 2008).

Opinion

IN THE UNITED STATES BANKRUPTCY COURT FOR THE DISTRICT OF PUERTO RICO In re: : : C & A, S.E., : Case No. 05-5297 (GAC) : Debtor : Chapter 11 ___________________________________: : C & A, S.E., : : Plaintiff : : v. : Adv. No. 05-00234 : RIO MAR NORTH ZONE : DEVELOPMENT CORP., : : Defendants : ___________________________________: DECISION AND ORDER The debtor filed this adversary proceeding against Rio Mar North Zone Development Corporation (“North Zone”) seeking damages for breach of a construction contract. The debtor claims the amount of $920,000.00 for monies retained under the contract, $950,000.00 for claims made against the debtor by service and material suppliers as a consequence of change orders and unspecified damages in the amount of $1,000,000.00, for a total of $2,870,000.00. North Zone filed a counterclaim alleging that the debtor breached the contract, by failing to complete the project and that the debtor’s abandonment caused North Zone damages in the amount of $2,849,541.44, including direct costs, liquidated damages, construction taxes and additional inspection costs. North Zone subsequently received the sum of $1,250,000.00 from the surety company and thus limits the damages claim to $1,599,541.44. Three witnesses testified on behalf of the debtor, including the operation’s manager for the project, the project engineer and the President of the debtor corporation, related to the extensive change orders and the delays in the project and as to North Zone’s unwillingness to release retainage funds to allow the debtor to complete the project. Two witnesses, the developer and the project inspector, testified on behalf of North Zone regarding the nature and extent of the project, the debtor’s obligations and performance, the debtor’s alleged default and abandonment of the project and the expenses incurred by North Zone to complete the project. After hearing the extensive testimony and after reviewing more than 700 pages of transcripts and exhibits of an even more voluminous nature, the Court concludes that both the debtor and North Zone suffered damages under the contract. However, based on the evidence submitted, the Court cannot conclude that either party caused the damages suffered by the other. The Court cannot conclude that it is more likely than not that either side is

responsible for the financial loss suffered by the other. Accordingly, for the reasons set forth below, the Court will enter judgment in favor of North Zone on the debtor’s complaint and judgment in favor of the debtor on North Zone’s counterclaim.

2 BACKGROUND On January 24, 2000, the debtor entered into a lump sum contract, in the amount of $20,373,490.00, with North Zone to construct two apartment complexes or “clusters” and a parking lot in Rio Grande, Puerto Rico. The contract term was 547 days, with an expected completion date of July 24, 2001. Pursuant to the terms of the contract, North Zone was responsible for the adequacy of the construction documents, while the debtor had the obligation to furnish all labor, equipment, material and services for the total construction of the project. Subsequent to the commencement of the work, the construction plans were modified and changed through numerous change orders. In total, there were seventy-three change orders, with some being additive and causing additional work and others being deductive and decreasing the required work. The project completion date was extended from 547 days to 1,710 days and the cost of the project increased. On August 31, 2004, the debtor sent a letter to North Zone informing it of the debtor’s interest in finishing the project, but indicating that the extension of the contract and the change orders

resulted in an additional cost to debtor of $2,600,000.00. In the letter, the debtor contended that North Zone had abandoned the original contract. The debtor sought an advance of $496,925.00 to conclude the project. Notwithstanding that North Zone advanced monies to the debtor on two previous occasions in order to finish 3 the construction, on September 1, 2004, North Zone sent a letter to the debtor declining the proposal and ordering the debtor to leave the project on September 7, 2004, indicating that North Zone would take over the project on September 8, 2004. North Zone ultimately completed the project in December of 2005 at an approximate cost of $25,000,000.00. DISCUSSION The leading case in Puerto Rico on the contractual rights of parties pursuant to a construction contract is Levy, Hijo, Inc. v. Public Buildings Authority, 1994 JTS 32, 135 D.P.R. 382, 1996 WL 724959 (P.R.), 1996 P.R.-Eng. 724,959 (publication page references are not available for the English translation of this document). In Levy, the Supreme Court of Puerto Rico attempted to harmonize the authority of the owner of a construction project to issue change orders, granted by a contractual clause, with the rights of the contractor. The Court determined that delays in the time originally agreed upon in these types of projects are common and that they should be anticipated. Yet, the Court also determined that a general contractor is entitled to delay damages when the

owner orders excessive or an unreasonable number of change orders, beyond those contemplated in the contract. The Court opined that a contractor should be compensated for industrial overhead and profit for unforeseeable work and for the unforseen major costs of planned works. Likewise, damages can be awarded to a contractor if 4 the delay in the project caused by the owner exceed normal construction industry practices. A contractor’s right to indemnification results from obstruction of the contractor’s performance with extraordinary delays, which disrupt the contractor’s work, constituting a breach of contract. The Court also indicated that a construction contract can be annulled or revised by the Court. The Court concluded that the intention of the parties must be considered taking into account the contract, the parties actions, their expertise and industry practices. In Levy, an expert witness testified as to the normal length of construction delay in the building of regional hospitals and opined that a 45% delay was foreseeable based on change orders and work stoppage orders. The Court considered this testimony and concluded that each case has its own peculiarities and must be resolved individually. Nonetheless, the Court concluded that nothing bars the parties from contractually stipulating to avoid judicial adjudication. In summary, the Court in Levy held that a contractor is

entitled to recover from the owner, the additional costs associated with change orders, that exceed the completion date beyond a reasonable period of time. The contractor is also entitled to have the delivery date extended for a reasonable period of time, in spite of a contractual clause providing that “time is of the 5 essence.” The owner is not liable for the indirect costs incurred by the contractor for the reasonable time delay in delivery resulting from change orders. The reasonableness of the time delay and the forseeability of the delay depends on the nature and complexity of the work and the prevailing practice in the construction industry. In the present case, the debtor alleges that the change orders and time delays were due to design errors and/or delay in the decision making process and that the change orders interrupted the sequence of construction. And while the debtor argued that the completion date was unreasonably extended based on excessive change orders, the debtor failed to produce evidence as to the reasonableness of the time delay, except testimony that it was unreasonable. The project engineer testified that he had never participated in a project in which the completion date was tripled and that generally the contract would be in default before the project completion date was tripled.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Levy v. Autoridad de Edificios Públicos
135 P.R. Dec. 382 (Supreme Court of Puerto Rico, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
C & A, S.E. v. Rio Mar North Zone Development Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-a-se-v-rio-mar-north-zone-development-corp-prb-2008.