C & A Construction Company v. DHC Development

CourtCourt of Appeals for the Tenth Circuit
DecidedNovember 5, 2012
Docket11-4139
StatusUnpublished

This text of C & A Construction Company v. DHC Development (C & A Construction Company v. DHC Development) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C & A Construction Company v. DHC Development, (10th Cir. 2012).

Opinion

FILED United States Court of Appeals Tenth Circuit

November 5, 2012 UNITED STATES COURT OF APPEALS Elisabeth A. Shumaker Clerk of Court FOR THE TENTH CIRCUIT

C & A CONSTRUCTION COMPANY, a Utah corporation; LYNN A. GILBERT, as Trustee of the Black Diamond Construction Trust; BLACK DIAMOND CONSTRUCTION 1 BUSINESS TRUST,

Plaintiffs-Appellants,

v. No. 11-4139 (D.C. No. 2:08-CV-00258-BSJ) DHC DEVELOPMENT, a Nevada (D. Utah) limited liability company; STEVEN P. DANKO; ZIONS FIRST NATIONAL BANK,

Defendants-Appellees.

ORDER AND JUDGMENT *

Before TYMKOVICH and BALDOCK, Circuit Judges, and BRORBY, Senior Circuit Judge.

* After examining the briefs and appellate record, this panel has determined unanimously to grant the parties’ request for a decision on the briefs without oral argument. See Fed. R. App. P. 34(f); 10th Cir. R. 34.1(G). The case is therefore ordered submitted without oral argument. This order and judgment is not binding precedent, except under the doctrines of law of the case, res judicata, and collateral estoppel. It may be cited, however, for its persuasive value consistent with Fed. R. App. P. 32.1 and 10th Cir. R. 32.1. This appeal involves a dispute over a construction contract. As is often the

case in such disputes, each party to the contract--owner DHC Development

(“DHC”) and general contractor C&A Construction Company (“C&A”)--contends

that the other breached the contract and was responsible for the resulting

damages. 1 The district court entered two orders designed to dispose of all of the

parties’ claims and counterclaims. In its first order, it granted DHC partial

summary judgment on certain claims involving a mechanic’s lien asserted by

C&A. In its second, final order, it estimated the value of each party’s remaining

claims, then offset the estimated value of these claims against one another. The

district court accompanied this second order with a judgment awarding DHC the

difference remaining after the offset.

In its appellate briefing, C&A points to several alleged deficiencies in each

of these orders, and urges that both orders be reversed on the merits. DHC

responds that the district court’s orders are soundly reasoned and should be

affirmed. But having carefully reviewed the challenged orders and the

1 There are actually three appellants: C&A, and two trusts that putatively hold an interest in C&A’s claims against DHC. The relationships between these three entities, and the problems this poses for the parties’ standing on appeal, are explored further in the analysis section of this decision, infra. Throughout this order and judgment, we refer to all three entities, collectively, as “C&A.” Similarly, Steven P. Danko, a principal of DHC, is named as an appellee, but we generally refer to him and DHC collectively as “DHC.” The other appellee, Zions First National Bank, which served as escrow agent under the Agreement, has not participated in this appeal.

-2- voluminous record, 2 we find ourselves unable to reach a disposition on the merits

for either party on the issues presented. Simply put, the unusual procedural path

the district court followed in this case leaves us without an adequately reviewable

final decision.

The problems with this case are illustrated by the fact that the parties

cannot agree on what the district court did. Although the parties do not expressly

challenge the form of the district court’s judgment, preferring instead to argue

about its substance, we find that its disposition failed to resolve so many essential

issues in this complex case that it simply cannot be upheld in its present format. 3

Although in general we may affirm the district court’s order on any basis that

finds adequate record support, the state of the record here does not permit us to

undertake a de novo review of the evidence and enter summary judgment with

proper findings and conclusions for the first instance on appeal. We may

certainly not establish a specific amount of damages on summary judgment

review, and thus, the district court’s order granting a judgment for a specific

2 The appellate record is nearly 2,400 pages long. 3 Oddly, C&A reserves its only real appellate challenge to the procedural aspects of the district court’s disposition for its appellate motion seeking our blessing to include certain materials in its appendix and supplemental addendum. There, it launches a strongly-worded attack on the district court’s improper grant of what it characterizes as summary judgment entered without proper notice. Such a procedural challenge is notably absent from C&A’s appellate briefing, though C&A does ask us to apply a more stringent standard of review because summary judgment was entered sua sponte, and contends that the district court improperly resolved disputed factual questions on summary judgment.

-3- dollar figure cannot be sustained. With some regret for the considerable time and

effort already expended in this case, we therefore find it necessary to vacate the

challenged final order and to remand to the district court for further proceedings.

BACKGROUND

1. The Agreement

The dispute involves the construction of the Black Diamond Project

(“Project”), a condominium development in Brian Head, Utah. C&A and DHC

entered into a Construction Agreement (“Agreement”) governing construction of

the Project. Phase I of the Agreement called for C&A to construct 21

condominium units in three buildings, for which DHC agreed to pay the Contract

Price of $6,661,633. 4 Payment for additional services or materials beyond the

Contract Price was to be made by DHC in accordance with the Agreement’s

change order procedures. See Aplt. App., Vol. 1 at 166.

As portions of Phase I were completed, C&A was entitled to receive

progress payments. The Project’s architect was responsible for evaluating C&A’s

progress-payment applications and the work performed. Within 20 calendar days

of its receipt of an application for payment approved by the architect, DHC was

required to make the appropriate progress payment to C&A. C&A requested such

4 Though the Agreement refers to 21 units, see Aplt. App. at 164, both DHC and the district court used a figure of 23 units. Any discrepancy on this point is immaterial to our result.

-4- progress payments by certifying that C&A had completed the work specified in

accordance with the Agreement, that C&A had paid all amounts due to

subcontractors and suppliers of materials for which DHC had previously paid

moneys to C&A, and that the current payment shown was now due.

Occasionally, upon receiving a progress payment, C&A would also execute

a waiver and release, releasing DHC from C&A’s right to a mechanic’s lien and

to any claim for the amount paid. But C&A asserts that these releases were never

intended to release DHC’s responsibility to pay for change orders.

The Agreement required C&A to finish Phase I within 210 calendar days

from its start date. The parties disagree concerning to what extent the completion

date was extended by the parties, and whether C&A failed to complete the Project

in a timely manner.

During construction, DHC was free to order minor changes to the Project

that did not involve adjustments to the contract price or additional completion

time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)
Arizonans for Official English v. Arizona
520 U.S. 43 (Supreme Court, 1997)
Sines v. Wilner
609 F.3d 1070 (Tenth Circuit, 2010)
Shannon v. Graves
257 F.3d 1164 (Tenth Circuit, 2001)
Ashby v. McKenna
331 F.3d 1148 (Tenth Circuit, 2003)
Wesley Rhea v. Massey-Ferguson, Inc.
767 F.2d 266 (Sixth Circuit, 1985)
Russell Curtis Simon v. City of Clute, Texas
825 F.2d 940 (Fifth Circuit, 1987)
Turner Ex Rel. Kiowa Tribe v. McGee
681 F.3d 1215 (Tenth Circuit, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
C & A Construction Company v. DHC Development, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-a-construction-company-v-dhc-development-ca10-2012.