C & A Construction Company v. DHC Development

Court of Appeals for the Tenth Circuit·Decided November 5, 2012·No. 11-4139·Unpublished

Opinion

FILED

United States Court of Appeals Tenth Circuit

November 5, 2012

UNITED STATES COURT OF APPEALS Elisabeth A. Shumaker

Clerk of Court

FOR THE TENTH CIRCUIT

C & A CONSTRUCTION COMPANY, a Utah corporation;

LYNN A. GILBERT, as Trustee of the Black Diamond Construction Trust;

BLACK DIAMOND CONSTRUCTION 1 BUSINESS TRUST,

Plaintiffs-Appellants,

v. No. 11-4139 (D.C. No. 2:08-CV-00258-BSJ)

DHC DEVELOPMENT, a Nevada (D. Utah)

limited liability company; STEVEN P.

DANKO; ZIONS FIRST NATIONAL BANK,

Defendants-Appellees.

ORDER AND JUDGMENT *

Before TYMKOVICH and BALDOCK, Circuit Judges, and BRORBY, Senior Circuit Judge.

*

After examining the briefs and appellate record, this panel has determined unanimously to grant the parties’ request for a decision on the briefs without oral argument. See Fed. R. App. P. 34(f); 10th Cir. R. 34.1(G). The case is therefore ordered submitted without oral argument. This order and judgment is not binding precedent, except under the doctrines of law of the case, res judicata, and collateral estoppel. It may be cited, however, for its persuasive value consistent with Fed. R. App. P. 32.1 and 10th Cir. R. 32.1.

This appeal involves a dispute over a construction contract. As is often the case in such disputes, each party to the contract--owner DHC Development (“DHC”) and general contractor C&A Construction Company (“C&A”)--contends that the other breached the contract and was responsible for the resulting damages. 1 The district court entered two orders designed to dispose of all of the parties’ claims and counterclaims. In its first order, it granted DHC partial summary judgment on certain claims involving a mechanic’s lien asserted by C&A. In its second, final order, it estimated the value of each party’s remaining claims, then offset the estimated value of these claims against one another. The district court accompanied this second order with a judgment awarding DHC the difference remaining after the offset.

In its appellate briefing, C&A points to several alleged deficiencies in each of these orders, and urges that both orders be reversed on the merits. DHC responds that the district court’s orders are soundly reasoned and should be affirmed. But having carefully reviewed the challenged orders and the

1 There are actually three appellants: C&A, and two trusts that putatively hold an interest in C&A’s claims against DHC. The relationships between these three entities, and the problems this poses for the parties’ standing on appeal, are explored further in the analysis section of this decision, infra. Throughout this order and judgment, we refer to all three entities, collectively, as “C&A.” Similarly, Steven P. Danko, a principal of DHC, is named as an appellee, but we generally refer to him and DHC collectively as “DHC.” The other appellee, Zions First National Bank, which served as escrow agent under the Agreement, has not participated in this appeal.

voluminous record, 2 we find ourselves unable to reach a disposition on the merits for either party on the issues presented. Simply put, the unusual procedural path the district court followed in this case leaves us without an adequately reviewable final decision.

The problems with this case are illustrated by the fact that the parties cannot agree on what the district court did. Although the parties do not expressly challenge the form of the district court’s judgment, preferring instead to argue about its substance, we find that its disposition failed to resolve so many essential issues in this complex case that it simply cannot be upheld in its present format. 3 Although in general we may affirm the district court’s order on any basis that finds adequate record support, the state of the record here does not permit us to undertake a de novo review of the evidence and enter summary judgment with proper findings and conclusions for the first instance on appeal. We may certainly not establish a specific amount of damages on summary judgment review, and thus, the district court’s order granting a judgment for a specific

2 The appellate record is nearly 2,400 pages long.

3 Oddly, C&A reserves its only real appellate challenge to the procedural aspects of the district court’s disposition for its appellate motion seeking our blessing to include certain materials in its appendix and supplemental addendum. There, it launches a strongly-worded attack on the district court’s improper grant of what it characterizes as summary judgment entered without proper notice. Such a procedural challenge is notably absent from C&A’s appellate briefing, though C&A does ask us to apply a more stringent standard of review because summary judgment was entered sua sponte, and contends that the district court improperly resolved disputed factual questions on summary judgment.

dollar figure cannot be sustained. With some regret for the considerable time and effort already expended in this case, we therefore find it necessary to vacate the challenged final order and to remand to the district court for further proceedings.

BACKGROUND

1. The Agreement The dispute involves the construction of the Black Diamond Project (“Project”), a condominium development in Brian Head, Utah. C&A and DHC entered into a Construction Agreement (“Agreement”) governing construction of the Project. Phase I of the Agreement called for C&A to construct 21 condominium units in three buildings, for which DHC agreed to pay the Contract Price of $6,661,633. 4 Payment for additional services or materials beyond the Contract Price was to be made by DHC in accordance with the Agreement’s change order procedures. See Aplt. App., Vol. 1 at 166.

As portions of Phase I were completed, C&A was entitled to receive progress payments. The Project’s architect was responsible for evaluating C&A’s progress-payment applications and the work performed. Within 20 calendar days of its receipt of an application for payment approved by the architect, DHC was required to make the appropriate progress payment to C&A. C&A requested such

4 Though the Agreement refers to 21 units, see Aplt. App. at 164, both DHC and the district court used a figure of 23 units. Any discrepancy on this point is immaterial to our result.

progress payments by certifying that C&A had completed the work specified in accordance with the Agreement, that C&A had paid all amounts due to subcontractors and suppliers of materials for which DHC had previously paid moneys to C&A, and that the current payment shown was now due.

Occasionally, upon receiving a progress payment, C&A would also execute a waiver and release, releasing DHC from C&A’s right to a mechanic’s lien and to any claim for the amount paid. But C&A asserts that these releases were never intended to release DHC’s responsibility to pay for change orders.

The Agreement required C&A to finish Phase I within 210 calendar days from its start date. The parties disagree concerning to what extent the completion date was extended by the parties, and whether C&A failed to complete the Project in a timely manner.

During construction, DHC was free to order minor changes to the Project that did not involve adjustments to the contract price or additional completion time. But in the event of more substantial changes, C&A was entitled to “additional consideration for time, labor, equipment, material and a Contractor’s fee of 10%.” Id. at 173. Such changes also required a written change order signed by both parties, and it was recognized they would result in modifications to the contract price and additions to the completion time for the Project.

Free access — add to your briefcase to read the full text and ask questions with AI

C & A Construction Company v. DHC Development, (10th Cir. 2012).

C & A Construction Company v. DHC Development (C & A Construction Company v. DHC Development) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)
Arizonans for Official English v. Arizona
520 U.S. 43 (Supreme Court, 1997)
Sines v. Wilner
609 F.3d 1070 (Tenth Circuit, 2010)
Shannon v. Graves
257 F.3d 1164 (Tenth Circuit, 2001)
Ashby v. McKenna
331 F.3d 1148 (Tenth Circuit, 2003)
Wesley Rhea v. Massey-Ferguson, Inc.
767 F.2d 266 (Sixth Circuit, 1985)
Russell Curtis Simon v. City of Clute, Texas
825 F.2d 940 (Fifth Circuit, 1987)
Turner Ex Rel. Kiowa Tribe v. McGee
681 F.3d 1215 (Tenth Circuit, 2012)