RIGGS, J.

Petitioners seek review of LUBA’s decision remanding the City of Hillsboro’s disposition of respondent Prendergast’s (respondent) application to alter a historical site and to relocate historical structures now located on the site, known as the Imbrie Farmstead.1 Respondent filed its application in February, 1989. On April 11, the planning commission decided to delay approval for 60 days, and it imposed certain conditions for obtaining earlier approval. Petitioners appealed that decision to the city council, which affirmed it. Both the council and the commission concluded that, under section 132(5) of the city’s Cultural Resource Management Ordinance, they had no authority to deny an application to alter, demolish or move a cultural resource. LUBA rejected petitioners’ arguments that the ordinance should be construed to allow a denial or, alternatively, that it violates the city’s comprehensive plan and Goal 5 if it cannot be so construed. Petitioners assign error to LUBA’s rejection of those arguments.

Section 132(5) provides:

“Application for Alteration, Demolition or Moving a Designated Cultural Resource
“(a) No designated cultural resource shall be altered, demolished or moved without prior approval of the Planning Commission.
“(b) Cultural resource owners desiring to alter, demolish or move a cultural resource shall apply for a permit to the Planning Commission and shall provide all information considered necessary by the Planning Commission as part of the application.
“(c) The Planning Commission shall hold a public hearing and shall evaluate the application with reference to the following actions:
“1. the economic or structural necessity of the proposed action;
“2. the extent of visible modification to the resource;
[310]*310“3. the relationship of the proposed action to the resource’s original character;
“4. the possibility of any alternative action which would reduce negative impacts on the cultural resource; and
“5. in the case of moving or demolition, the scheduling of redevelopment of the resource site.
“(d) The Planning Commission shall work with the applicant, interested citizens and technical staff to minimize the negative impact of the proposed action, wherever possible.
“(e) Approval of an application for alteration or demolition may be delayed up to 60 days by the Planning Commission if it deems additional information or consideration with the applicant necessary. Approval of the application may be conditioned to secure interior and/or exterior documentation of the site prior to the proposed action, to preserve selected architectural features and to preserve site landscaping. The Planning Commission may, however, approve an alteration or demolition permit at any time within the 60 day period if it feels the applicant has made an effort in good faith to retain, document, and/or preserve the culturally significant characteristics of the resource.
“(f) The City Council may extend a demolition delay by an additional 60 days at the request of the Planning Commission or an interested party.
“(g) Applications for alteration, demolition, or moving permits for a designated cultural resource which are complete and which are in compliance with all other City regulations and ordinances shall not be denied outright. If no action on an application has been taken by the Planning Commission within 60 days of submission of the completed application, the application shall be considered approved.”

The substantive disagreement between the parties2 centers on the phrase “shall not be denied outright” in subsection (g). Respondent contends that the phrase has a clear literal meaning and does not permit the city to deny an application. Therefore, respondent argues, the city is restricted to the options, delineated in subsection (e), of [311]*311approving an application, with or without conditions, or of delaying approval for up to 60 days, with or without conditions. Petitioners argue that, when read in the context of the ordinance and together with provisions of the city’s comprehensive plan, the phrase does not preclude the city from denying an application. Petitioners also assert that respondent’s reading of the ordinance produces absurd results. Although subsection (a) makes planning commission approval a condition precedent to alteration, demolition or movement, under respondent’s interpretation subsection (g) would make it impossible for the commission to withhold approval. LUBA agreed with respondent. We agree with petitioners.

In our view, respondent and LUBA place undue emphasis on the phrase “shall not be denied outright” and seem to read that phrase in a vacuum. Subsection (g) does not contain an unqualified prohibition of “outright”3 denials of applications. It makes approval contingent, inter alia, on the compliance of the application “with all other City regulations,” which include the five criteria against which subsection (c) requires the planning commission to evaluate applications. They also include the comprehensive plan provision requiring the preservation, protection and maintenance of “open space, historic sites and structures” for “present and future residents of Hillsboro” and the surrounding community. It would be incompatible with that preservation policy for the city to be powerless to deny any application to demolish, alter or move a historical site or structure. See DLCD v. Yamhill County, 99 Or App 441, 783 P2d 16 (1989).

We therefore disagree with LUBA and respondent that subsection (g) prohibits the denial of applications. They also appear to have based their interpretation on the fact that subsection (e) does not enumerate the denial of an application as one of the courses available to the planning commission. However, we do not read that subsection as a comprehensive statement of dispositional options. It addresses the limited situations where approval of an application requires further consideration or further data and where approval is made subject to certain kinds of conditions. Indeed, to the extent [312]*312that subsection (e) is relevant to the question, it favors petitioners’ proffered interpretation. The city’s ability to attach conditions and to delay approval would be a blunt sword indeed, if, ultimately, the city had no power of denial. We conclude that the city has authority under section 132(5) to deny the application and that LUBA must expand the scope of its remand to the city accordingly.4

LUBA also considered a jurisdictional issue that respondent raised before it but does not renew here, at least in jurisdictional terms. Respondent argued that the decision from which petitioners appealed, the city council’s affirmance of the planning commission’s 60-day delay of approval, was not a final decision. Rather, the final decision was the effective approval of the application, which occurred without further formal action 60 days after the commission’s decision. LUBA disagreed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Byrnes v. City of Hillsboro
798 P.2d 1119 (Court of Appeals of Oregon, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
790 P.2d 552, 101 Or. App. 307, 1990 Ore. App. LEXIS 454, Counsel Stack Legal Research, https://law.counselstack.com/opinion/byrnes-v-city-of-hillsboro-orctapp-1990.