Byers v. Coppel, Unpublished Decision (8-24-2001)

CourtOhio Court of Appeals
DecidedAugust 24, 2001
DocketNo. 01CA2586.
StatusUnpublished

This text of Byers v. Coppel, Unpublished Decision (8-24-2001) (Byers v. Coppel, Unpublished Decision (8-24-2001)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Byers v. Coppel, Unpublished Decision (8-24-2001), (Ohio Ct. App. 2001).

Opinion

DECISION AND JUDGMENT ENTRY
Jill and William Byers appeal the judgment of the Ross County Court of Common Pleas. They argue that the jury's verdict is against the manifest weight of the evidence. Because there is some competent, credible evidence supporting the jury's verdict, we disagree. They next argue that the trial court erred in finding that the Ohio Consumer Sales Practices Act ("OCSPA") was not applicable to this action. Because we find that the OCSPA applies to a contract to construct a new home, we agree. Accordingly, we reverse the judgment of the trial court in part and remand this case for further proceedings consistent with this opinion.

I.
In 1996, Jill and William Byers filed a complaint against Richard W. Coppel dba Coppel Construction ("Coppel") alleging that Coppel breached their contract and violated the OCSPA. The Byers attached a copy of a building contract signed by Richard Coppel and the Byers to their complaint. The contract provided that Coppel would build a home in Chillicothe for "$151,000 (subject to any additions or deletions hereafter made by agreement of the parties) * * *" on a lot that the Byers owned. The contract also provided that "[i]f any variance or conflict appears between the specifications and the working drawings (plans) the specifications shall take precedence and control." The contract did not contain an integration clause.

In his answer, Coppel filed a counterclaim against the Byers alleging that the Byers had not paid him approximately seven thousand dollars for work he performed under the contract.

At the jury trial, Mrs. Byers testified that she contracted Coppel to build a home for her parents to live in. She asserted that she did not meet Coppel until after the parties signed the contract. She agreed that she requested changes that were worth six thousand three hundred and fifty-five dollars over the contract price, but denied ever discussing with Coppel the substitution of less expensive replacements for microlam headers, TJI joists,1 steel beams, and trusses. She testified that she moved her parents into the home in November 1994. In January 1995, she returned to the home with the blueprints to inspect the basement and noticed that the microlam header that was in the blueprints was not present in the basement. Over the next few months, Mrs. Byers noticed cracks in the wall and that the floors made noise when walked on. She also noticed that the microlam header was missing from the attic over the garage. Mrs. Byers allowed Coppel to add two steel posts to the basement, but then called in AKM Building Systems, Inc. ("AKM") to assess the property and perform repairs. She paid over seventeen thousand dollars to have AKM repair her house. Mrs. Byers testified that C.K. Satyapriya, a licensed engineer, informed her that her home needs approximately ten thousand dollars in further repairs.

On cross-examination, Mrs. Byers admitted that she authorized some changes in the plans after the contract was signed. Mrs. Byers admitted that AKM put steel posts in where the plans called for wooden posts and that she had okayed changes made to the plans during construction that were never reduced to writing.

Satyapriya testified that he inspected the Byers' home in September 1998 and October 1998. His company prepared a report ("Satyapriya's report") outlining the problems with the home. He identified the following deficiencies of the home compared to the plans: (1) rafters instead of trusses; (2) rafters nailed insufficiently; (3) missing ridge board; (4) two by twelve boards instead of TJI joists. He explained that these inadequacies will cause the walls to crack over time. Satyapriya also testified that the deficiencies in the basement caused the house to settle inward, thereby further cracking the walls. He explained that the floors in the home were not level, varying as much as three fourths of an inch within one room. In his opinion, the home needs new steel I-beams in the basement; re-nailing of its rafters to a new ridge board; and additional roof vents.

On cross-examination, Satyapriya explained that AKM Construction's use of perforated drainpipe caused the moisture in the basement. He also testified that AKM Construction had to jack up the floor to put in the steel beam in the basement, which can cause squeaky floors.

Gerald Ater, president of AKM, testified that Mrs. Byers asked him to inspect her home once it was built. He found the same deficiencies as Satyapriya did. Upon the request of Mrs. Byers, AKM attempted to remedy these deficiencies. Ater testified that the walls on the second floor of the home were cracked before AKM started working. He explained in detail the repair work AKM performed on the home.

Richard Johnson, Jr., a registered professional engineer and surveyor, testified that he inspected the home. He testified that the work AKM did was not structurally necessary. In his opinion, the roof framing done by Coppel was adequate and was not failing. He also testified that the substitution of gusset plate for a ridge board in the rafters is an acceptable substitution. He then testified that the substitution of two by twelve boards for TJI Joists is an acceptable substitution. He asserted that the venting system Coppel installed has equal venting capacity to the system called for in the plans.

Through extensive testimony, Johnson outlined his disagreements with Satyapriya's report, analysis and testimony. Johnson explained that the Satyapriya's report, which criticized the structural integrity of the home, applied the wrong building code. Johnson testified that there were several causes of the failure of one of the support points at issue. He explained that AKM could have bent an existing support post while adding support posts. In Johnson's opinion, the structure in place before AKM's work was sufficient to carry the load of the home. He also testified that the beams installed by Coppel were able to carry the load of the home and that AKM's work was not necessary. Mr. Johnson then opined that the attic, as constructed by Coppel, was structurally capable of carrying the loads upon it.

Mike Putnam, a real estate broker and appraiser, testified that he inspected the home and appraised it and the lot at two hundred fifteen thousand dollars. He explained that he was aware of the Satyapriya's report, which criticized the construction of the home. He further explained that the house is in a very desirable area because it sits adjacent to a country club golf course.

Coppel's wife, Michelle Coppel, testified that Coppel met with Mrs. Byers two times before the contract was signed. She explained that she and her husband lived across the street from the house Coppel built for the Byers. Michelle Coppel testified that Mrs. Byers was at the house off and on during the building process and often had her set of plans with her checking over the house. She explained that Mrs. Byers walked through the whole house with the Coppels and asked them questions. She testified that she and Mrs. Byers went into the basement before the basement concrete floor was poured, and Mrs. Byers had an opportunity to observe the structure in the basement. When the Coppels moved from their house, Mrs. Byers put a sign in her parent's yard that read, "Thank God Richard Coppel is moving".

In his testimony, Coppel conceded that he did not build the house with the materials for which the plans called. Coppel testified that he had a meeting with Mrs. Byers at a McDonalds where they discussed changing specifications of the house before the parties signed the contract to build the home.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rose v. Zaring Homes, Inc.
702 N.E.2d 952 (Ohio Court of Appeals, 1997)
Pettett v. Cooper
24 N.E.2d 299 (Ohio Court of Appeals, 1939)
Keeton v. Telemedia Co. of Southern Ohio
648 N.E.2d 856 (Ohio Court of Appeals, 1994)
Keiber v. Spicer Construction Co.
619 N.E.2d 1105 (Ohio Court of Appeals, 1993)
Robinson v. McDougal
575 N.E.2d 469 (Ohio Court of Appeals, 1988)
Howell v. Dayton Power & Light Co.
656 N.E.2d 957 (Ohio Court of Appeals, 1995)
State v. Gordon
276 N.E.2d 243 (Ohio Supreme Court, 1971)
O'Day v. Webb
280 N.E.2d 896 (Ohio Supreme Court, 1972)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
Strother v. Hutchinson
423 N.E.2d 467 (Ohio Supreme Court, 1981)
Ruta v. Breckenridge-Remy Co.
430 N.E.2d 935 (Ohio Supreme Court, 1982)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)
State v. Lott
555 N.E.2d 293 (Ohio Supreme Court, 1990)
Shore West Construction Co. v. Sroka
572 N.E.2d 646 (Ohio Supreme Court, 1991)
Myers v. Garson
614 N.E.2d 742 (Ohio Supreme Court, 1993)
Broz v. Winland
629 N.E.2d 395 (Ohio Supreme Court, 1994)
Galmish v. Cicchini
734 N.E.2d 782 (Ohio Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Byers v. Coppel, Unpublished Decision (8-24-2001), Counsel Stack Legal Research, https://law.counselstack.com/opinion/byers-v-coppel-unpublished-decision-8-24-2001-ohioctapp-2001.