Butler v. Ramco-Gershenson, Inc

542 N.W.2d 912, 214 Mich. App. 521
CourtMichigan Court of Appeals
DecidedDecember 15, 1995
DocketDocket 149453, 149454
StatusPublished
Cited by18 cases

This text of 542 N.W.2d 912 (Butler v. Ramco-Gershenson, Inc) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Butler v. Ramco-Gershenson, Inc, 542 N.W.2d 912, 214 Mich. App. 521 (Mich. Ct. App. 1995).

Opinion

Smolenski, P.J.

In these consolidated appeals, plaintiff Joseph H. Butler appeals as of right an order of summary disposition in favor of defendants Ramco-Gershenson, Inc., Pontiac Mall Limited Partnership, and Wineman Investment Company. * 1 We affirm in part and reverse in párt.

Plaintiff was an employee of Western Waterproofing Company, Inc. (wwc), an independent contractor that entered into a contract with defendant Pontiac Mall for brick replacement work on the north elevation of Hudson’s three-story department store at Summit Place Mall. The mall is owned by defendants Pontiac Mall and Wineman Investment and managed by defendant Ramco-Gershenson.

To perform the brick restoration work, a frame scaffolding was erected on Hudson’s roof to rise above the top of the building’s parapet wall. 2 The *524 parapet wall was capped with precast concrete coping block. Booms or outriggers were mounted on the frame scaffolding to suspend spider scaffolding on which wwc employees performed the brick restoration work. On May 9, 1988, plaintiff was standing on the spider scaffolding when two pieces of coping block fell and hit him. Plaintiff sued defendants, among others, for his injuries. The trial court subsequently granted defendants’ motion for summary disposition. Plaintiff appeals as of right.

Plaintiff first argues that the trial court erred in granting summary disposition of his claim premised on a theory of inherently dangerous activity. We note that although defendants’ motion for summary disposition was premised on MCR 2.116(C)(8) and (10), the trial court did not specify the ground for its grant of summary disposition of this claim. However, because both parties relied on matters outside the pleadings in their arguments in opposition to and in support of this claim, we review this issue pursuant to MCR 2.116(C)(10).

On appeal, a trial court’s determination concerning a motion for summary disposition is reviewed de novo. A motion for summary disposition pursuant to MCR 2.116(0(10) tests the factual sufficiency of a claim. This Court must independently determine, giving the benefit of doubt to the nonmovant, whether the movant would have been entitled to judgment as a matter of law. Lytle v Malady, 209 Mich App 179, 183-184; 530 NW2d 135 (1995).

"The inherently dangerous activity doctrine is an exception to the general rule that an employer of an independent contractor is not liable for the contractor’s negligence or the negligence of his employees.” Bosak v Hutchinson, 422 Mich 712, *525 724; 375 NW2d 333 (1985). This exception extends to employees of the contractor performing the dangerous work. Id. Thus, as stated in Bosak:

[A]n employer is liable for harm resulting from work "necessarily involving danger to others, unless great care is used” to prevent injury, Inglis [v Millersburg Driving Ass’n, 169 Mich 311, 331; 136 NW 443 (1912),] or where the work involves a "peculiar risk” or "special danger” which calls for "special” or "reasonable” precautions. 2 Restatement Torts, 2d, §§ 416, 427. It must be emphasized, however, that the risk or danger must be "recognizable in advance,” i.e., at the time the contract is made, for the doctrine to be invoked. Thus, liability should not be imposed where a new risk is created in the performance of the work which was not reasonably contemplated at the time of the contract. [Id. at 727-728.]

After reviewing the record in this case, we conclude that unlike in Oberle v Hawthorne Metal Products Co, 192 Mich App 265, 269; 480 NW2d 330 (1991), which plaintiff cited, plaintiff has failed to produce any evidence that the risk or danger, i.e., that the coping would fall, was contemplated when the parties entered into the original contract or the first addendum thereto. Rather, giving the benefit of doubt to plaintiff, the evidence indicates that defendants knew only that the coping had been exposed to water and that the brickwork had been damaged.

Thomas Olson, a wwc foreman, testified at his deposition that before attaching the outriggers he had inspected all of the coping visually and by attempting to pick up the coping, and that the coping was not loose. The original contract (dated March 25, 1988) concerned replacement only of *526 "spalled,[ 3 ] shalling, loose and otherwise defective brick masonry” on lower areas of the wall. The March 31, 1988, "Scope of Work” memorandum from Louis Ciotti of wwc instructed wwc employees to take care in preventing brick masonry from dropping to the ground and injuring people or landscaping. This memo did not refer to coping falling from above onto employees working on the scaffolding.

Ciotti testified that after work had commenced on the lower wall pursuant to the original contract, problems in the upper wall were discovered, i.e., "rusted tie bars, the shelf angles down below and the bulges in the masonry wall where the brick had separated,” and that these problems indicated that the upper portion of the wall was in "kind of a deteriorated state.” Again, this evidence concerns only deterioration of the brickwork.

On April 22, 1988, the consulting engineers of Ehlert-Bryan, Inc., visited the building at defendant Ramco-Gershenson’s request to review the brick restoration work. Although Ehlert-Bryan’s April 26, 1988, letter to defendant Ramco-Gershenson concerning this visit recognizes that the coping was subject to water infiltration, it does not indicate that Ehlert-Bryan realized that the coping would be likely to fall. Rather, the letter discusses extending the life of the coping by applying silicone sealer.

The first addendum (dated May 5, 1988) to the original contract concerned only removal and replacement of "all brick veneer masonry between the coping and the existing steel shelf angle approximately 4 feet below the top of the wall.” 3 4

*527 A May 19, 1988, letter from Mark Michener, a roofing consultant from Soil and Materials Engineers, Inc. (sme), to Ruth McCarthy, general manager of Summit Place Mall, provided in part as follows:

On May 6, 1988, we visited the Summit Place Mall in Waterford Township, Michigan. The purpose of our visit was to determine rehabilitation strategies for the precast coping parapet detail at various locations of the Mall (see separate report). Mr. Louis Ciotti of Western Waterproofing was also present to provide input from his recent experience with the Hudson’s masonry restoration.

First, although Michener’s inspection occurred before plaintiff was injured, the letter transmitting the information discerned by Michener was not dated until after plaintiff was injured.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S Baxter Jones v. Esurance Insurance Company
Michigan Court of Appeals, 2025
David Stallworth v. Entertainment Managers LLC
Michigan Court of Appeals, 2024
Roberto Trevino v. Pulaski Civic Club
Michigan Court of Appeals, 2022
James S Rahaim v. Leet Denton
Michigan Court of Appeals, 2019
Ismael Olivan v. Jose Olivan
Michigan Court of Appeals, 2019
Leys v. Lowe's Home Centers, Inc.
664 F. Supp. 2d 828 (W.D. Michigan, 2009)
Tingley v. 900 Monroe, LLC
731 N.W.2d 427 (Michigan Court of Appeals, 2005)
Pickering v. Pickering
659 N.W.2d 649 (Michigan Court of Appeals, 2003)
Amoco Pipeline Co. v. Herman Drainage Systems, Inc.
212 F. Supp. 2d 710 (W.D. Michigan, 2002)
People v. Herron
628 N.W.2d 528 (Michigan Supreme Court, 2001)
Stitt v. Holland Abundant Life Fellowship
614 N.W.2d 88 (Michigan Supreme Court, 2000)
Ottaco, Inc v. Guaze
574 N.W.2d 393 (Michigan Court of Appeals, 1998)
Hughes v. Pmg Building, Inc
574 N.W.2d 691 (Michigan Court of Appeals, 1998)
VanGessel v. Lakewood Public Schools
558 N.W.2d 248 (Michigan Court of Appeals, 1997)
Weisman v. U S Blades, Inc
552 N.W.2d 484 (Michigan Court of Appeals, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
542 N.W.2d 912, 214 Mich. App. 521, Counsel Stack Legal Research, https://law.counselstack.com/opinion/butler-v-ramco-gershenson-inc-michctapp-1995.