Butch Levy Plumbing & Heating, Inc. v. Sallblad

126 N.W.2d 380, 267 Minn. 283, 1964 Minn. LEXIS 639
CourtSupreme Court of Minnesota
DecidedFebruary 7, 1964
Docket39,128
StatusPublished
Cited by12 cases

This text of 126 N.W.2d 380 (Butch Levy Plumbing & Heating, Inc. v. Sallblad) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Butch Levy Plumbing & Heating, Inc. v. Sallblad, 126 N.W.2d 380, 267 Minn. 283, 1964 Minn. LEXIS 639 (Mich. 1964).

Opinion

Nelson, Justice.

Defendant appeals from an order of the Hennepin County District Court denying his motion for a new trial, following a determination *284 that he owed plaintiff, Butch Levy Plumbing and Heating, Inc., $5,285.50 for labor and material furnished him under a contract between the parties.

Sometime during the first half of 1960 defendant undertook the erection of an apartment building at 1800 Fremont Avenue North in Minneapolis. Specifications and drawings of mechanical installations for the building were prepared by Ralph D. Thomas & Associates, Inc., and the defendant requested bids on the basis of these plans. Plaintiff was not among those submitting bids but later independently submitted a proposal to furnish and install a plumbing, heating, and ventilating system. The testimony of Sheldon Rein, who represented the plaintiff as an estimator in submitting its proposal, indicates that although he had seen the specifications of the Thomas firm, the proposal as accepted by defendant was not necessarily based upon those plans.

What has been termed a “contract agreement” between the parties herein was entered into June 10, 1960, although it was not actually reduced to writing and signed until January 1961. This written agreement incorporates “change orders” dated June 21 and July 20, 1960, by which the contract price, originally $27,660, was increased to $29,100 to cover changes found necessary after plaintiff’s original proposal had been accepted.

Plaintiff commenced work about July 13, 1960, and with the exception of some minor corrections, alterations, and additions, the work was substantially performed by January 1961 and fully completed by March 1, 1961. Disputes arose from time to time while the work was in progress. Without going into detail, suffice it to say that complaints were lodged by defendant, some of which plaintiff agreed to, and did, satisfy. Others, it did not.

Plaintiff began billing the defendant no later than August 1960 for the work done and materials furnished during July and August 1960. It was not until December 16, after plaintiff’s outlay for labor alone had exceeded $8,000, that defendant paid $12,000. The check by which this payment was made contained on its face the following printed statement:

*285 “By Endorsement This Check When Paid Is Accepted In Full Payment Of The Following Account.”

Below this statement is typewritten the following:

“Apply.on 1800 1806 Fremont Ave. No.”

On the reverse side of the check the following printed statement appears:

“This Check When Endorsed Is Considered A Lien Waiver Satisfactory In Full For Any Or All Labor And Materials.”

Plaintiff continued pressing requests for additional payments, but defendant continued to refuse payment for one reason or another. On one occasion defendant promised to pay if plaintiff would provide a one-year service warranty on materials and installation. On December 29, 1960, plaintiff furnished a warranty effective from February 1, 1961, to January 31, 1962. Defendant, nevertheless, continued to withhold payments.

In January 1961 plaintiffs president, Leonard B. Levy, negotiated with defendant in an attempt to secure further payment. Defendant then promised to continue making payments if plaintiff would sign the written contract, which Mr. Levy did. The written contract required that the materials and labor furnished by plaintiff be as specified in the plan prepared for defendant by the Thomas firm but stated that this condition was modified by the proposal submitted by plaintiff and accepted by defendant on June 10, 1960. On January 13, 1961, defendant issued another check for $10,000 to plaintiff. This check also contained on its face the printed statement:

“By Endorsement This Check When Paid Is Accepted In Full Payment Of The Following Account.”

Below this statement was typewritten the following:

“1800 Fremont Ave. No. In full for all plumbing Heating and Ventilating. to-date.”

On the reverse side of this check also, the following printed statement appeared:

*286 “This Check When Endorsed Is Considered A Lien Waiver Satisfactory in Full for Any Or All Labor And Materials.”

This statement has been stricken with a pen. There is no testimony in the record indicating who may have stricken the statement.

At defendant’s request plaintiff’s president, upon receipt of the check of January 13, signed an instrument which recited in part:

“Receipt of the above amount is hereby acknowledged in Plumbing and Heating payment of all Labor and Materials including all Ventilating * * * by the undersigned delivered or furnished to 1800 Fremont Ave. No. Minneapolis, Minn., and, for value received, hereby waives all rights which may have been acquired by the undersigned to file mechanics’ liens against said premises for labor, skill or material furnished to said premises. Balance Due $ None.”

Following Mr. Levy’s signature was a paragraph which reads:

“Notice: Receipt of lien waiver required for material furnished.”

The record shows that defendant brought into court a document entitled “Damages To Defendant,” listing 19 items encompassing his complaints, and testified with regard to each item. Mr. Levy testified in opposition to defendant’s claims, as did Elmer Earl Hagberg, whose occupation is putting in sewer and water installations, and Sheldon Rein, the construction supervisor. Their testimony indicated that such installations had been properly made, contrary to defendant’s claim, and conformed to city requirements. The testimony concerning these items presented fact questions for the court to determine as the trier of facts, a function which necessarily included passing upon the credibility of the testimony. The only other evidence offered by defendant to support these items of damages was his testimony that the apartment building would have been worth an additional $12,000 to $14,000 if plaintiff’s work “had been properly done.” We must, however, take note of the fact that such testimony by the owner, while permitted, can only be given such weight as all the circumstances warrant when it is not supported by other expert testimony on that issue.

While the defendant contends that the recitals on the check and lien waiver of January 13, 1961, support his claim that these constitute *287 the basis for an accord and satisfaction between the parties, it is clear from the record that both plaintiff’s president and other employees, including the office secretary, continued to demand payment of the balance on the contract, now reduced to $7,100. Defendant offered no proof of any discussions between the parties indicating that they in-téndéd to compromise or that they mutually agreed to reduce the contract price.

It appears that about February 10 plaintiff’s president and defendant discussed payment of the balance due on the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. Swanson v. 3M Co.
845 N.W.2d 808 (Supreme Court of Minnesota, 2014)
Rasmussen v. Two Harbors Fish Co.
832 N.W.2d 790 (Supreme Court of Minnesota, 2013)
Means v. Nelle Gertrude Berger Trust
799 S.W.2d 556 (Court of Appeals of Arkansas, 1990)
State Farm Mutual Automobile Insurance Co. v. Levinson
438 N.W.2d 110 (Court of Appeals of Minnesota, 1989)
Quality Care Nursing Services, Inc. v. Coleman
728 S.W.2d 1 (Tennessee Supreme Court, 1987)
ACTON CONST. CO., INC. v. State
363 N.W.2d 130 (Court of Appeals of Minnesota, 1985)
Action Instruments Co., Inc. v. Hi-G, Inc.
359 N.W.2d 664 (Court of Appeals of Minnesota, 1984)
Crawford Door Sales Co. v. Cross
223 N.W.2d 395 (Supreme Court of Minnesota, 1974)
Bloomer v. Bloomer
185 N.W.2d 520 (Supreme Court of Minnesota, 1971)
Don Kral Incorporated v. Lindstrom
173 N.W.2d 921 (Supreme Court of Minnesota, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
126 N.W.2d 380, 267 Minn. 283, 1964 Minn. LEXIS 639, Counsel Stack Legal Research, https://law.counselstack.com/opinion/butch-levy-plumbing-heating-inc-v-sallblad-minn-1964.