Busch Bros. Elevator Co. v. Unit Building Services

190 Ohio App. 3d 413, 2010 WL 4324433
CourtOhio Court of Appeals
DecidedNovember 3, 2010
DocketNo. C-100069
StatusPublished
Cited by4 cases

This text of 190 Ohio App. 3d 413 (Busch Bros. Elevator Co. v. Unit Building Services) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Busch Bros. Elevator Co. v. Unit Building Services, 190 Ohio App. 3d 413, 2010 WL 4324433 (Ohio Ct. App. 2010).

Opinion

Sylvia S. Hendon, Judge.

(¶ 1} Busch Brothers Elevator Company (“Busch”) sued Unit Building Services (“Unit”) and RCHP for breach of contract, alleging that it had not been paid for elevator repair services that it had rendered. Following a bench trial, the court found in favor of Busch. RCHP was ordered to pay Busch $18,254. Unit was ordered to pay Busch $75,945.08. Unit now appeals.

{¶ 2} RCHP owned a Sheraton Hotel. It hired Unit as the construction manager on a hotel renovation project. In this capacity, Unit contacted Busch to perform elevator repair work. Unit and Busch never executed a written contract for any of their dealings. At issue below was whether Unit or RCHP should pay five of Busch’s invoices dated September through November 2005. The court determined that RCHP had contracted with Busch for one project but that Unit had contracted with Busch for the remaining work. It therefore held that RCHP was responsible for one of the invoices and that Unit was liable for the remaining four. In its first assignment of error, Unit claims that the trial court erred when it determined that a contract had existed between Unit and Busch whereby Unit was responsible for paying Busch. Unit is correct.

{¶ 3} Our standard of review is twofold. We must accept the trial court’s findings of fact if they are supported by competent, credible evidence.1 But we [415]*415review de novo whether, based on the properly supported findings, the trial court correctly determined that a contract existed.2

The Trial Court’s Findings

{¶4} The trial court concluded that Unit had “a contractual obligation to compensate Busch” based on “the terms and conditions established and ratified through the [parties’] course of dealings.” The court found that Busch had completed elevator repair work “at the direction and request” of Unit. The court also found that prior to the time of the disputed invoices — from September 2004 through August 2005 — Busch had submitted eight invoices to Unit and that Unit had forwarded these invoices to RCHP. Each invoice had been paid, and each payment had been “tendered and received by checks issued by RCHP.” These findings were supported by competent, credible evidence, and we therefore accept them as established facts. They were insufficient, however, to establish that Unit was contractually liable to Busch for payment.

The Agreement Lacked Consideration

{¶ 5} A contract is a promise that is actionable upon a breach.3 The elements of a contract are an offer, acceptance, contractual capacity, consideration, a manifestation of mutual assent, and legality of object and of consideration.4

{¶ 6} The trial court in this case found that an oral contract existed between Unit and Bush. Oral contracts are disfavored.5 And an oral agreement is enforceable only if there is “sufficient particularity to form a binding contract.” 6 Its terms are determined from the “words, deeds, acts, and silence of the parties.”7

{¶ 7} Here, Busch failed to prove the existence of a contract. The record is clear that, throughout Busch and Unit’s course of dealings, Unit never [416]*416paid Busch for its services — RCHP did. And there is no testimony in the record that Unit ever explicitly promised that it would pay Busch for its work. Unit and Busch’s “words, deeds, acts and silence,” therefore, were not sufficiently particular to establish the element of consideration necessary to form a binding contract. Consideration is a benefit to the promisor or a detriment to the promisee.8 And while Unit presumably received some incidental benefit from having the elevator work performed, the consideration Busch sought was payment for its services. “Consideration for a contract can only be that which the parties intended to be the consideration. It must be that which was ‘bargained for and given in exchange for the promise.’ ”9

{¶ 8} Based on the trial court’s findings, there was no contract between Busch and Unit as a matter of law. The trial court erred in holding that Unit was liable to Busch for payment. Unit’s first assignment of error is sustained.

{¶ 9} In its second assignment of error, Unit contends that because Busch had failed to mitigate its damages, it could not recover from Unit. Given our resolution of Busch’s first assignment of error, this argument is moot, and we decline to address it.10

{¶ 10} We therefore reverse the judgment of the trial court as to Unit, and remand this case for further proceedings consistent with this decision.

Judgment reversed in part and cause remanded.

Cunningham, P.J., and Mallory, J., concur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Subel v. AMD Plastics, L.L.C.
2023 Ohio 1139 (Ohio Court of Appeals, 2023)
Bakhshi v. Baarlaer
2021 Ohio 13 (Ohio Court of Appeals, 2021)
Widok v. Estate of Wolf
2020 Ohio 5178 (Ohio Court of Appeals, 2020)
Watts v. Fledderman
2018 Ohio 2732 (Ohio Court of Appeals, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
190 Ohio App. 3d 413, 2010 WL 4324433, Counsel Stack Legal Research, https://law.counselstack.com/opinion/busch-bros-elevator-co-v-unit-building-services-ohioctapp-2010.