Burton & Co. v. United States

51 Ct. Cl. 362, 1916 U.S. Ct. Cl. LEXIS 20, 1916 WL 1119
CourtUnited States Court of Claims
DecidedJune 5, 1916
DocketNo. 31662
StatusPublished

This text of 51 Ct. Cl. 362 (Burton & Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burton & Co. v. United States, 51 Ct. Cl. 362, 1916 U.S. Ct. Cl. LEXIS 20, 1916 WL 1119 (cc 1916).

Opinion

Downey, Judge,

delivered the opinion of the court.

The claimants in this case seek recovery on 11 different items which are all the outgrowth of contracts entered into between them and the United States for work in connection with the excavation and construction of the approaches to the lock connecting the Mississippi River and Bayou Plaque-mine at Plaquemine, La. The several contracts are referred to in the findings of which they are made a part, and since to review them as a whole would very much lengthen this opinion without apparent profit, they will be discussed only as may be regarded necessary in the separate consideration of the various claims presented.

Claimants first seek to recover $4,815.22 deducted as expenses of superintendence and inspection under the contract of June 6,1905. (Findings I, II, and IV.)

Under this contract dated June 6,1905, approved and contractor notified of approval June 19, 1905, work was to commence within 60 days after notification of approval and be completed within five months thereafter. About the time the contractor was ready to commence or had begun work [377]*377an epidemic of yellow fever broke out, scattering the force employed, and on their application an extension of time was granted for “ a reasonable time.” The contractors proceeded with their preparations for the doing of the work, and, the epidemic having abated, they commenced or resumed work on the 10th day of October, 1905. The fact that they voluntarily commenced work on this date is sufficient to warrant the conclusion that the elapsed time was all the extension necessary on account of the cause stated and was reasonable. The contract was therefore to be completed within five months from that date, or before the 10th day of March, 1906.

Beginning with the 10th day of March, 1906, expenses of superintendence and inspection were charged against the contractor monthly until completion of the contract except that it was not fully completed until a few days after February 1, 1908, and no charge was made after the month of January, 1908. The expenses charged and deducted were first certified in itemized form by the assistant engineer on the work and then certified on the vouchers drawn as deductions by the engineer officer in charge, and the contractors then certified that the vouchers as drawn were correct and, so far as appears, made no objection to the deductions.

The contract provided that if the contractors should fail to complete the contract within the time limited it might be annulled, or in lieu of annulling the time limit might be waived and the contractor permitted to finish the work, in which event all expenses for superintendence and inspection due to the delay beyond the time originally fixed for completion should be determined by the party of the first part and deducted from any payments due or to become due the party of the second part.

The party of the first part in this contract was “ Clinton B. Sears, lieutenant colonel, Corps of Engineers, United States Army,” but he was contracting, as recited, “ for and in behalf of the United States of America.” If in course he was succeeded at any time by another officer as engineer in charge, representing the United States, questions for determination, under the contract, by the contracting officer were for the determination of the officer in charge as the [378]*378representative of the United States, and it can not be held, as contended by claimants, that they were, during the entire progress of the work, entitled to the individual determination of Col. Sears even though he may have been succeeded by another engineer officer as officer in charge.

Since it appears from the facts found that the contractors encountered some difficulties in the prosecution of the work in the bayou approach and excavated much more than the estimated amount of material, it is contended that there should have been an extension of time on that account, and that therefore a part of the charge for superintendence and inspection was improper; but we find no right under the contract to an extension of time for the reasons stated, and, indeed, it does not appear that any was then asked. It is also contended that it does not appear that the United States was actually put to the expense for superintendence and inspection as charged, and it is asserted that the employees for whose time charges are made were otherwise employed and in outside enterprises. It was not necessary, in our view of the situation, that it should be specifically proven, outside of the official certificates, that the United States was actually put to the expense charged, and there is no evidence which we can regard as even approximately sufficient to impeach the integrity of the official certificate of the engineer officer in charge. We conclude that there is no sufficient basis for a recovery on this item.

Claim is made for 7,910 yards of excavating, at 40 cents per yard, $3,164. This is the material which these contractors diverted to the purposes of the McGee contract, as shown in detail in Finding Y. There is nothing involved except a pure question of fact as to whether this excavating was paid for, and in the finding referred to it is said that this material was included in estimates made for which the contractors were paid. There is apparent in the presentment of the case some tendency to confusion as between the material taken by Burton & Co. for the purposes of the McGee contract and material taken from the area of the river approach by McGee & Co. before Burton & Co. entered into their contract, but it is not worth while to enter [379]*379into any discussion of the matter, since the finding is conclusive on the question. There can be no recovery on this item.

Claim is also made for excavating 16,914 cubic yards of material, under the contract of August 7, 1906 (Finding VII), at $1.05 per yard. This claim is disposed of by the findings, but it is perhaps proper to say that it is based on a calculation made by Prof. Dougherty from data furnished and made for the purpose of a presentation of the facts to this court. Prof. Dougherty’s skill as a mathematician has not been questioned by the court, but he was evidently laboring under difficulties, and it appears from the evidence that some matters essential to correct conclusions were not considered by him, possibly not presented properly. However that may be, the findings (Finding XIII) determine the quantities of material excavated under this contract and that, except as therein stated, the contractors were paid therefor. The conclusion on this item is against the claimants.

The next item is a claim for anticipated profits on 5,464 yards of excavating at 90 cents per yard, $4,917.60. The facts on which this claim is predicated are found in Finding XIV and, if entitled to recover, the amount claimed is found to be correct. It is the difference between the price the United States would have been compelled to pay for this excavating if these contractors had been permitted to do it and the price at which it is shown they could have procured it to be done by a subcontractor. That the profit would have been comparatively enormous probably does not affect the rights of the claimants.

It appears that when the water was let into the river approach inside the temporary levee for the purpose of testing the lock gates there was some washing from the banks and a deposit of sediment carried in with the river water.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Camden Iron Works v. United States
50 Ct. Cl. 191 (Court of Claims, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
51 Ct. Cl. 362, 1916 U.S. Ct. Cl. LEXIS 20, 1916 WL 1119, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burton-co-v-united-states-cc-1916.