Burkholder v. Peters

58 F. App'x 94
CourtCourt of Appeals for the Sixth Circuit
DecidedJanuary 9, 2003
DocketNo. 02-3394
StatusPublished
Cited by13 cases

This text of 58 F. App'x 94 (Burkholder v. Peters) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burkholder v. Peters, 58 F. App'x 94 (6th Cir. 2003).

Opinion

KENNEDY, Circuit Judge.

I.

The Ohio Department of Transportation (“ODOT”) plans to relocate a 16-mile section of U.S. Route 30 that runs between Bucyrus and Ontario, Ohio. Currently, this stretch of highway has only two lanes, and has access points from adjacent property and intersecting roads. The portions of U.S. Route 30 on either side of it have four lanes and are limited-access highways. ODOT desires to make the entire route uniform, in this case by constructing a new segment of four-lane, limited-access highway to replace the existing roadway. Part of this new highway segment will run directly through the family farm of plaintiffs, Donald and Marilyn Burkholder, which is located outside of Galion, Ohio.

This project is funded by the Federal Highway Administration (“FHWA”), subjecting it to the procedural requirements of the National Environmental Policy Act (“NEPA”), 42 U.S.C. § 4321, et seq. NEPA broadly requires all federal agencies to take into account the environmental effects of their actions, primarily by requiring an Environmental Impact Statement (“EIS”) for any “major Federal action significantly affecting the quality of the human environment.” 42 U.S.C. § 4332(2)(C). In order to decide whether a proposed federal action is likely to significantly impact the environment, thus triggering the need for an EIS, agencies must prepare a “concise public document” known as an Environmental Assessment (“EA”). 40 C.F.R. § 1508.9(a). Based on the EA, the federal agency either orders preparation of an EIS, or issues a “finding of no significant impact” (“FONSI”), which constitutes the agency’s determination that no EIS is required. 40 C.F.R. § 1508.13.

Agencies must follow certain federal regulations when preparing the EA. Until an agency has issued a record of decision concerning the environmental impact of the proposed project, regulations promul[97]*97gated by the Council on Environmental Quality (“CEQ”) prohibit taking any action that would “limit the choice of reasonable alternatives.” 40 C.F.R. § 1506.1(a)(2). To that end, FHWA regulations specifically prohibit “final design activities” prior to the issuance of a FONSI. 23 C.F.R. § 771.113(a)(l)(ii). Although federal regulations permit agencies to delegate responsibility for preparing an EA to a private contractor, such contractors must provide disclosure statements indicating that they have no “financial or other interest in the outcome of the project.” 40 C.F.R. § 1506.5(c). The CEQ has interpreted “financial or other interest” to include “a promise of future construction or design work on the project.” 40 Most Asked Questions Concerning CEQ’s National Environmental Policy Act Regulations, 46 F.R. 18031, March 23,1981.

On June 7, 1993, ODOT hired a private consulting firm, McCoy/Fok & Associates, Inc., to conduct a preliminary study of the project, including the EA. On July 29, 1997, ODOT entered into a second contractual agreement with McCoy/Fok to undertake the engineering, design and construction work for the final highway project. On February 11, 2000, appellants wrote a letter to FHWA complaining that the second contract violated federal timing regulations and created a conflict of interest. FHWA responded that it would continue to work with ODOT nonetheless, because the design work was financed solely by the state, no federal funds were committed to the project prior to the completion of the EA, and thus its ultimate review would be impartial. After seven years of preparation, ODOT issued an EA, prepared by McCoy/Fok, on November 27, 2000.

On April 12, 2001, after reviewing the EA, the underlying environmental evidence, and the transcripts of various public hearings, the FHWA issued a FONSI. This final agency action is subject to review in federal court pursuant to the Administrative Procedures Act (“APA”), 5 U.S.C. § 701, et seq. The Burkholders challenged the FONSI in federal court, seeking declaratory and injunctive relief prohibiting defendants from pursuing the project until a proper EIS was completed. The district court below granted summary judgment for the defendants. The Burk-holders appeal, arguing that ODOT’s violation of timing requirements and conflict of interest rules are legal errors that tainted the environmental assessment process and resulted in an arbitrary and capricious FONSI.

II.

A. Procedural Violations of NEPA Implementing Regulations

ODOT violated binding administrative regulations governing the process of making the environmental assessment under NEPA. The second contract with McCoy/Fok, which was a contract for final design work, was entered into on July 29, 1997, over three years before completion of the EA and the FONSI. This clearly violated CEQ and FHWA regulations prohibiting and “final design activity” and any action that would “limit the choice of reasonable alternatives.” 23 C.F.R. § 771.113(a)(l)(ii); 40 C.F.R. § 1506.1(a)(2).1 McCoy/Fok also failed to file a disclosure statement indicating a conflict of interest, despite the fact that the [98]*98second contract’s promise of final design work provided them with a “financial interest” in the project as defined by federal regulations. This clearly violated CEQ regulations. 40 C.F.R. § 1506.5(c).

B. The Oversight Test

The district court found that although defendants failed to comply with these federal regulations, their noncompliance was essentially harmless. Relying on a Tenth Circuit case, Associations Working for Aurora’s Residential Environment v. Colorado Dept. of Transp., 153 F.3d 1122,1129 (10th Cir.1998) (“AWARE”), the district court found that there was sufficient evidence of independent oversight by FHWA to cure the procedural misconduct committed by ODOT and McCoy/Fok.

In AWARE, the Colorado Department of Transportation (“CDOT”) contracted with a private company to provide final design work for a proposed highway project. CDOT later engaged the same contractor to complete the EIS for that project. The Tenth Circuit found that although the promise of future design work may have given rise to a conflict of interest and breached binding federal regulations, “the ultimate question for the court is ... whether the alleged breach compromised the ‘objectivity and integrity of the NEPA process.’ ” AWARE, 153 F.3d at 1129 (quoting

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lakes & Parks Alliance v. Federal Transit Administration
91 F. Supp. 3d 1105 (D. Minnesota, 2015)
Tennessee Environmental Council v. Tennessee Valley Authority
32 F. Supp. 3d 876 (E.D. Tennessee, 2014)
Shoreline Alliance v. Tennessee Valley Authority
961 F. Supp. 2d 890 (W.D. Tennessee, 2013)
Bullwinkel v. United States Department of Energy
899 F. Supp. 2d 712 (W.D. Tennessee, 2012)
Heartwood, Inc. v. Agpaoa
628 F.3d 261 (Sixth Circuit, 2010)
St. Vincent Mercy Medical Center v. Leavitt
484 F. Supp. 2d 746 (N.D. Ohio, 2007)
Save Our Cumberland Mountains v. Kempthorne
453 F.3d 334 (Sixth Circuit, 2006)
Wuliger v. Office of the Comptroller of Currency
394 F. Supp. 2d 1009 (N.D. Ohio, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
58 F. App'x 94, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burkholder-v-peters-ca6-2003.