Burke v. N. P. Clough, Inc.

78 A.2d 483, 116 Vt. 448, 1951 Vt. LEXIS 119
CourtSupreme Court of Vermont
DecidedFebruary 6, 1951
Docket1234
StatusPublished
Cited by9 cases

This text of 78 A.2d 483 (Burke v. N. P. Clough, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burke v. N. P. Clough, Inc., 78 A.2d 483, 116 Vt. 448, 1951 Vt. LEXIS 119 (Vt. 1951).

Opinion

Jeeeords, J.

On February 8,1947, the plaintiff and the defendant signed a contract, the material terms of which required the plaintiff to cut and pile on suitable skidways all the merchantable timber located on a certain described lot of land. He was to start work forthwith and prosecute the same with diligence until completed. The defendant was obligated to pay the plaintiff $15.00 per thousand feet, Greenleaf caliper measure, weekly for all logs trucked into a designated yard. $2.00 per thousand feet in addition to the $15.00 was to be paid upon satisfactory completion of the job.

The plaintiff started work in February, 1947, which was continued until about the first of June of that year, when it was stopped on the order of the defendant. Operations were resumed in November of that year and continued until about the middle of January, 1948, when the plaintiff stopped work. He then brought this action in contract for damages for the breach thereof. The grounds for the breach as alleged in the complaint are that he was ordered by the defendant to stop, to desist from cutting1 any further and that the defendant wholly prevented him from performing his part of the contract. A trial by jury was had which resulted in a verdict being directed for the defendant. The ground for the motion made at the close of the plaintiff’s case was, in substance, that there was no evidence in the case which would warrant the jury in reasonably finding that the defendant ordered the plaintiff to stop and desist from any further cutting or that the defendant wholly prevented the plaintiff from performing his part of the contract. The case is here on the exception of the plaintiff to the granting of the motion for a directed verdict.

The material facts are not in dispute. During the period from February to June there were some complaints by the plaintiff in regard to the claimed failure of the defendant to keep the skidways clear of logs and in regard to shortages in credit for the number of logs or board feet delivered to the defendant. The plaintiff did not wish to stop work in June when ordered to, but did, and it was agreed that operations would be resumed in the fall of 1947. No *450 time was set for the resumption of .operations and it was left that the defendant would notify the plaintiff when it wished him to start. The plaintiff was requested in July to start work. He was not able to do so at that time but did commence operations in November.

At times after the resumption of operations the skidways were so filled with logs that no more could be placed on them, with the result that logs which had been cut were buried in the snow and not hauled out as there was no place to put them. At the time the plaintiff stopped cutting, these logs amounted to- about fifty thousand feet. The trucks of the defendant did not draw away the logs from the skidways fast enough to take care of the congestion. Sometime in the middle of January, 1948, the plaintiff decided that he would not cut any more lumber and so notified the treasurer of the defendant who said he wished that the plaintiff would stay and complete the job. The skidway which was being used at the time of the stoppage of work had a capacity of 12,000 board feet. The defendant had four trucks, each with a capacity of from 2,000 to 2,400 board feet. As it had other similar jobs going at the time of the one here, usually only two of these trucks were used on this operation.

During the discussion between the court and counsel on the motion for a directed verdict the attorney for the plaintiff stated that he sought to recover only under the written contract above referred to which was set forth in the complaint and that his claim of prevention by the defendant of its fulfillment was based solely on the claimed shortages and the congestion of the skidways.

It is sufficient to say in regard to the claim that the shortages on the part of the defendant in giving credits to the plaintiff for the number of logs or board feet delivered to the defendant made it impossible for the plaintiff to complete his contract, that there was no evidence in the case which would have warranted the submission of this question to the jury. The plaintiff has not pointed out in his brief any evidence as to the amount of the claimed shortages in quantity or in value, nor have we discovered any such evidence in our reading of the transcript. A finding by the jury that the claimed shortages amounted to so much as to make it financially impossible for the plaintiff to continue under the contract would necessarily have been based upon speculation and conjecture and conjecture is no proof in him who is bound to make proof. Jacobs v. Clark, 112 Vt 484, 489, 28 A2d 369; Wellman, Admr. v. Wales, 97 Vt 245, 255, 122 A 659.

*451 The act of one party in preventing the other from performing a contract is a breach thereof. Peist v. Richmond, 97 Vt 97, 99, 122 A 420; Derosia v. Farland, 83 Vt 372, 385, 76 A 153, 28 LRANS 577; 12 Am Jur 961 § 386. The expression “breach of contract” is confined to wrongful conduct. Restatement of the Law of Contracts, Vol. 1, § 312, comment a. The defendant did not specifically, nor by implication, agree to keep the skidways free from congestion at all times and under all circumstances and conditions. It was only obligated to use reasonable effort and diligence to keep the skidways in such shape that the plaintiff would not be unduly hindered or prevented from keeping his part of the contract. The burden was on the plaintiff to prove that the defendant did not exercise such effort and diligence. Assuming that there was evidence reasonably tending to show that there was at times a congestion of logs on the skidways, it was incumbent on the plaintiff to prove that this congestion was due to wrongful conduct on the part of the defendant in order to justify a finding that the latter had “prevented” the plaintiff from completing his part of the contract. Peist v. Richmond, supra, at page 98. Such wrongful conduct could consist of a failure of the defendant to stop or relieve the congestion because of negligence on its part. Anvil Mining Co. v. Humble, 153 US 540, 14 S Ct 876, 38 L ed 814; Lynch v. Sellers & Co., 41 La Ann 375, 6 S 561, 5 LRA 682. It could also consist of a wilful or intentional purpose on the part of the defendant to have congestion so as to prevent the plaintiff from completing the contract, United States v. Behan, 110 US 338, 4 S Ct 81, 28 L ed 168; Billings v. Kitten, 111 W Va 551, 162 SE 892; Patterson v. Meyerhofer, 204 NY 96, 97 NE 472, 473. In the case last cited it is said: “In the case of every contract there is an implied undertaking on the part of each party that he will not intentionally and purposely do anything to prevent the other party from carrying out the agreement on his part.”

There was no evidence in the case from which the jury reasonably could have found wrongful conduct on the part of the defendant in any of the respects mentioned. In fact the evidence, taken as a whole, tended to show to the contrary.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Murphy v. Sentry Insurance
2014 VT 25 (Supreme Court of Vermont, 2014)
Davis v. Liberty Mut. Ins. Co.
19 F. Supp. 2d 193 (D. Vermont, 1998)
Logan v. Bennington College Corporation
72 F.3d 1017 (Second Circuit, 1996)
Logan v. Bennington College Corp.
72 F.3d 1017 (Second Circuit, 1995)
Multnomah County v. Howell
496 P.2d 235 (Court of Appeals of Oregon, 1972)
Marshall v. MILTON WATER CORPORATION
270 A.2d 162 (Supreme Court of Vermont, 1970)
Cushman v. Outwater
159 A.2d 89 (Supreme Court of Vermont, 1960)
Ireland v. Charlesworth
98 N.W.2d 224 (North Dakota Supreme Court, 1959)
Rice's Admr. v. Press
94 A.2d 397 (Supreme Court of Vermont, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
78 A.2d 483, 116 Vt. 448, 1951 Vt. LEXIS 119, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burke-v-n-p-clough-inc-vt-1951.