Burke County v. Askin

755 S.E.2d 747, 294 Ga. 634, 2014 Fulton County D. Rep. 351, 2014 WL 818937, 2014 Ga. LEXIS 166
CourtSupreme Court of Georgia
DecidedMarch 3, 2014
DocketS13A1360
StatusPublished
Cited by5 cases

This text of 755 S.E.2d 747 (Burke County v. Askin) is published on Counsel Stack Legal Research, covering Supreme Court of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burke County v. Askin, 755 S.E.2d 747, 294 Ga. 634, 2014 Fulton County D. Rep. 351, 2014 WL 818937, 2014 Ga. LEXIS 166 (Ga. 2014).

Opinion

Thompson, Chief Justice.

Burke County, its Board of Commissioners, and members of the Commission (“the Count/’) appeal the superior court’s grant of a writ of mandamus requiring the County to repair, maintain and construct certain roads dedicated to the County. 1 This is the second appearance of this case before the Court. See Burke County v. Askin, 291 Ga. 697 *635 (732 SE2d 416) (2012) (“Burke County I”). In the prior appeal and cross-appeal, this Court vacated the superior court’s grant of mandamus relief and remanded the case with direction for the court to reconsider under the proper legal standard that portion of its ruling requiring the County to construct and maintain a previously unopened section of roadway. On remand, the superior court again issued a writ of mandamus granting the relief requested and the County appeals. For the reasons discussed below, we affirm the decision of the superior court.

The evidence shows that in 1962 five roads shown on a plat of Pineview, a proposed subdivision located in Burke County, were dedicated by deed to, and accepted by, the County, which thereafter passed a resolution to “cut or build” the roads. At some point, three of the roads were constructed as unpaved roads. Pineview’s proposed main thoroughfare, Frances Avenue, was one of the roads constructed, although the last few hundred feet remained unfinished. The two remaining roads on the plat appear never to have been built. 2

In 2004, Otis F. Askin, Sr., and Tiger, Inc., appellees, purchased a large amount of undeveloped property in the county fronting on Frances Avenue. While only some of appellees’ property is located within the Pineview subdivision, all of it fronts on Frances Avenue which provides sole access to the property. Appellees divided the property into lots and prepared a new subdivision plat, which the County approved. Subsequently, appellees asked the County to repair and maintain all the county roads in Pineview, but the County refused. Appellees filed suit, and the Burke County Superior Court issued a writ of mandamus ordering the County to repair and maintain the existing three roads, including building the final segment of Frances Avenue which provided access to lots on the north end of the road. The superior court denied mandamus relief with respect to the remaining two subdivision roads, finding the County had no obligation to construct and maintain these unopened roads.

On appeal, this Court determined, among other things, that with respect to its grant of mandamus relief requiring the County to build and maintain the previously unopened section of Frances Avenue, the superior court failed to apply the proper legal standard for relief, i.e., that the County’s decision not to construct the entire road had been *636 arbitrary, capricious, and unreasonable, or a gross abuse of discretion. Burke County I, supra at 701. Accordingly, we vacated the superior court’s order and remanded the case with instructions for the court to reconsider its ruling as to the unfinished segment of Frances Avenue under the proper standard of review. Id. On remand, the superior court again found in favor of appellees and granted a writ of mandamus requiring, in part, that the County repair, maintain and construct Frances Avenue in its entirety. In the present appeal, the County challenges the trial court’s order only insofar as it requires the County to construct the unopened portion of Frances Avenue. 3

1. The County first argues that the superior court erred in granting relief compelling the County to construct and maintain a previously unopened segment of roadway because in the context of requests for road maintenance, mandamus relief is limited to requests regarding existing public roads. In the first appearance of this case before this Court, however, we determined that the decision whether to open the unopened portion of Frances Avenue was a discretionary act to which mandamus relief would be available under certain limited circumstances. See Burke County I, 291 Ga. at 700. As this issue was decided by this Court in the prior appeal, the County may not relitigate it here. See OCGA § 9-11-60 (h) (“[A]ny ruling by the Supreme Court or the Court of Appeals in a case shall be binding in all subsequent proceedings in that case in the lower court and in the Supreme Court or the Court of Appeals. . . .”). Accordingly, the County’s first enumeration of error lacks merit.

2. In its remaining enumerations of error, the County challenges the superior court’s determination on remand that the County’s failure to construct a road over the full length of Frances Avenue was arbitrary, capricious, unreasonable and a gross abuse of discretion. The grant or denial of mandamus relief in cases such as this one lies *637 largely in the discretion of the presiding judge. See Van Valkenburg v. Stone, 172 Ga. 642, 647 (158 SE 419) (1931). 4 This Court will not interfere with a trial court’s decision granting mandamus relief absent a showing that the court manifestly abused its discretion. Id. at 647-648.

Here, the only question before us is whether the superior court manifestly abused its discretion and erred in granting mandamus relief to appellees with respect to the unfinished segment of Frances Avenue. The superior court found that regardless of whether the County previously built the existing road or simply accepted the road as built, it had agreed under the 1962 resolution and deed to build the entirety of Frances Avenue, and completion of the entire road remained a necessity because the final few hundred feet provided sole access to certain lots in the Pineview subdivision. Accordingly, the superior court concluded the County’s failure to finish the construction of Frances Avenue was arbitrary, capricious, unreasonable, and a gross abuse of discretion. 5

(a) The County asserts that a decision is arbitrary and capricious if it lacks a rational basis and argues that its refusal to construct and maintain the entirety of Frances Avenue was rationally related to the governmental purpose of maintaining the county road system and directing road funds in the most effective and efficient manner. The only evidence on which the County relies, however, is evidence showing that the final segment of Frances Avenue was not constructed during the original development of the subdivision, as well as evidence showing that the existing development on Frances Avenue is minimal and that all the parcels platted on the unfinished segment *638 are undeveloped and owned by appellees.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
755 S.E.2d 747, 294 Ga. 634, 2014 Fulton County D. Rep. 351, 2014 WL 818937, 2014 Ga. LEXIS 166, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burke-county-v-askin-ga-2014.