Bunge S.A. v. ADM International Sarl

CourtCourt of Appeals for the Third Circuit
DecidedJune 2, 2023
Docket22-1276
StatusUnpublished

This text of Bunge S.A. v. ADM International Sarl (Bunge S.A. v. ADM International Sarl) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bunge S.A. v. ADM International Sarl, (3d Cir. 2023).

Opinion

NOT PRECEDENTIAL

UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT _______________

No. 22-1276 _______________

BUNGE, S.A., Appellant

v.

ADM INTERNATIONAL SARL; AMERICAN PETROLEUM TANKERS X LLC; ARCHER-DANIELS-MIDLAND COMPANY; ASHLAND SPECIALTY INGREDIENTS G.P.; CROWLEY GLOBAL SHIP MANAGEMENT, INC.; MOSAIC FERTILIZER, LLC _______________

On Appeal from the United States District Court for the District of Delaware (D.C. No. 1:22-cv-00026) U.S. District Judge: Honorable Richard G. Andrews _______________

Argued: January 23, 2023

Before: BIBAS, NYGAARD, and FUENTES, Circuit Judges

(Filed: June 2, 2023)

J. Stephen Simms [ARGUED] Simms Showers 201 International Circle Suite 230 Baltimore, MD 21030 Counsel for Appellant Amanda D. Price Squire Patton Boggs 600 Travis Street Suite 6700 Houston, TX 77002

John J. Reilly [ARGUED] Squire Patton Boggs 1211 Avenue of the Americans 26th Floor New York, NY 10036 Counsel for Appellee

_______________

OPINION* _______________

BIBAS, Circuit Judge.

Litigation involves uncertainty. There is always a risk that after judgment is entered,

the other side will not pay. Security is sometimes available to mitigate this risk, but even

admiralty’s powerful attachment procedure has limits.

Bunge has tested those limits. It sought to attach ADM’s property on two claims. One

is expressly, voluntarily contingent on external events. That claim does not meet the stand-

ard for maritime attachment. But the other claim, although contingent, is a complete cause

of action under the relevant law and has been asserted. It thus supports maritime attach-

ment. So we will reverse the District Court’s order vacating the writ of maritime attachment.

* This disposition is not an opinion of the full Court and, under I.O.P. 5.7, is not binding precedent. 2 I. FACTS AND HISTORY

The M/V Orient Rise is a cargo ship. In late 2018, Tongli Shipping chartered it to

Bunge, which chartered it to ADM International. Tongli and Bunge had a time charterparty:

Bunge got to use the vessel for a fixed amount of time. Bunge and ADM, by contrast, had

a voyage charterparty: ADM got to use the vessel for a specific trip. It was to carry fertilizer

from Saudi Arabia to the Mississippi River.

But when the Orient Rise arrived off the Mississippi River in February 2019, things

went awry: it lost two anchors, had issues offloading cargo, and spent time at the repair

berth. This was all expensive and time-consuming, and no one picked up the bill. So when

the Orient Rise finished offloading, the berth’s owner arrested it. The vessel’s owners

posted a $10 million bond to free it. The owners eventually settled the dispute with the

berth’s owner, paying it $3.25 million.

In July 2019, Tongli filed a London arbitration against Bunge. Tongli claimed that the

time charterparty required Bunge to indemnify it for the settlement. Bunge counterclaimed,

saying that Tongli owed it money for loss of hire under a safe-port warranty in the time

charterparty.

At the same time, Bunge filed a London arbitration against ADM. This arbitration was

Bunge’s Plan B: if Bunge lost on Tongli’s claim or its own counterclaim, it would then try

to get that money from ADM. Bunge argued that if it had to indemnify Tongli for the

settlement, then ADM must in turn indemnify it. And if Tongli did not pay Bunge for loss

of hire, then ADM had to do so under a safe-port warranty in the voyage charterparty. The

3 former claim is for more than $7 million (after interest), and the latter is for roughly

$480,000.

Little has happened in these arbitrations. So in January 2022, Bunge filed a complaint

in the District of Delaware. The complaint alleged breach of contract and sought to attach

and garnish some of ADM’s funds under Supplemental Rule B as security for an eventual

judgment. The District Court issued a writ of maritime attachment; but then, after a hearing,

it issued an order vacating the writ. The court reasoned that Bunge had not met its burden

of showing a valid prima facie admiralty claim because both of its claims were contingent

on the outcome of its arbitration against Tongli. Bunge filed this interlocutory appeal of

that order.

This case sounds in admiralty. The District Court had jurisdiction under 28 U.S.C.

§ 1333(1). We have jurisdiction under 28 U.S.C. § 1291, as orders vacating maritime at-

tachments are appealable collateral orders. Swift & Co. Packers v. Compania Colombiana

Del Caribe, S.A., 339 U.S. 684, 689 (1950). We review an order vacating a writ of maritime

attachment for abuse of discretion and the legal conclusions supporting the order de novo.

ProShipLine Inc. v. Aspen Infrastructures Ltd., 609 F.3d 960, 966 (9th Cir. 2010).

II. RULE B ATTACHMENT AND CHOICE OF LAW

We start with some background on maritime attachment. Under Supplemental Rule B,

if a defendant cannot be found within a district, a plaintiff can garnish and attach the de-

fendant’s property there after filing a complaint. Fed. R. Civ. P. Supp. R. B(1)(a). This

complaint is subject to a heightened pleading standard: it must “state the circumstances

from which the claim arises with such particularity that the defendant or claimant will be

4 able, without moving for a more definite statement, to commence an investigation of the

facts and to frame a responsive pleading.” Fed. R. Civ. P. Supp. R. E(2)(a). Once the court

issues a writ of maritime attachment, the defendant gets a hearing. Fed. R. Civ. P. Supp.

R. E(4)(f). At this hearing, the plaintiff bears the burden of showing, among other things,

“a valid prima facie admiralty claim against the defendant.” Aqua Stoli Shipping Ltd. v.

Gardner Smith Pty Ltd., 460 F.3d 434, 445 (2d Cir. 2006), abrogated on other grounds by

Shipping Corp. of India Ltd. v. Jaldhi Overseas Pte Ltd., 585 F.3d 58 (2d Cir. 2009); see

also Fed. R. Civ. P. Supp. R. B, advisory comm. nn., 1985 amend. (“The rule envisions

that the order will issue when the plaintiff makes a prima facie showing that he has a mar-

itime claim against the defendant … .”).

The requirement of a valid prima facie admiralty claim has two components: it must be

a valid prima facie claim and it must sound in admiralty. We agree with the Second Circuit

“that federal maritime law governs whether a claim sounds in admiralty and that the rele-

vant substantive law governs whether a plaintiff has alleged a valid prima facie claim.”

Blue Whale Corp. v. Grand China Shipping Dev. Co., 722 F.3d 488, 495 (2d Cir. 2013).

As the Second Circuit explained:

Admiralty law provides the remedy; substantive law defines the right to the remedy. Assessing the prima facie validity of a claim is a substantive inquiry that should be governed by the relevant substantive law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Bunge S.A. v. ADM International Sarl, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bunge-sa-v-adm-international-sarl-ca3-2023.