Bungalow Revival, LLC v. Jose Cruz, Jr. and Sarah Cruz

CourtCourt of Appeals of Texas
DecidedOctober 31, 2025
Docket01-23-00415-CV
StatusPublished

This text of Bungalow Revival, LLC v. Jose Cruz, Jr. and Sarah Cruz (Bungalow Revival, LLC v. Jose Cruz, Jr. and Sarah Cruz) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bungalow Revival, LLC v. Jose Cruz, Jr. and Sarah Cruz, (Tex. Ct. App. 2025).

Opinion

Opinion issued October 31, 2025

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-23-00415-CV ——————————— BUNGALOW REVIVAL, LLC, Appellant V. JOSÉ CRUZ, JR. AND SARAH CRUZ, Appellees

On Appeal from the 61st District Court Harris County, Texas Trial Court Case No. 2017-45154

MEMORANDUM OPINION

José Cruz, Jr. and his wife Sarah Cruz sued Bungalow Revival, LLC for

breach of an oral contract for home remodeling services, alleging that the work

was of poor quality and required thousands of dollars in repair. Bungalow Revival

counterclaimed for breach of the same contract, alleging that the Cruzes failed to pay the final invoice—a fact which they conceded. A jury found that both the

Cruzes and Bungalow Revival breached the contract, neither breach was excused,

and actual damages for both parties ($75,000 for the Cruzes and $36,424.45 for

Bungalow Revival). After offsetting the amount of the final invoice, the trial court

entered judgment on the verdict in favor of the Cruzes for $38,575.55 in actual

damages, along with pre- and post-judgment interest.

In its first two issues on appeal, Bungalow Revival argues that it was entitled

to attorney’s fees and prejudgment interest. In its third and final issue, it argues the

evidence was legally insufficient to support the jury’s finding that the Cruzes had

$75,000 in actual damages.

We conclude that the evidence of the Cruzes’ damages is not legally

insufficient simply because the jury’s reasoning is unclear, and the $75,000

damages award is within the range of evidence presented at trial. Because

Bungalow Revival prevailed on its claim for breach of contract, it was entitled to

attorney’s fees under Chapter 38 of the Civil Practice and Remedies Code.

However, because it failed to segregate its attorney’s fees, we will remand this

portion of the case to the trial court for a determination of the amount of fees to be

awarded. Finally, we conclude that Bungalow Revival was not entitled to

prejudgment interest.

2 We affirm the trial court’s judgment except as to Bungalow Revival’s claim

for attorney’s fees, which we remand for further proceedings.

Background

The Cruzes were good friends with Gilbert Perez, the sole owner of

Bungalow Revival. When the Cruzes decided to move to the Houston area where

José grew up, they asked Perez to take on a construction project to update and

customize their million-dollar new home in West University Place.1 Perez had

done this kind of project on a home the Cruzes previously owned in the Houston

area. Based on this experience and their good friendship with Perez, the Cruzes

entered into an oral agreement with Bungalow Revival to complete the work as

requested by Sarah in exchange for the Cruzes paying “cost plus 25%.”

The Cruzes were eager to move into their house, which they bought in

September 2015. As the work progressed, the Cruzes and their three minor

children lived in a two-bedroom apartment. Working with Sarah, Perez created

design plans for the house. The Cruzes initially hoped to move into the house in

January, but as the work progressed, the completion date slipped multiple times.

Perez and Nick Eronko, a Bungalow Revival employee who worked closely with

Perez, testified at trial that the delays were caused by numerous changes to the

1 José Cruz, Jr. is a former major league baseball player, who currently coaches the Rice University men’s baseball team. Due to his work, the family lived in several cities before moving back to Houston. 3 scope and design details that were requested by Sarah, as well as subcontractor

availability and scheduling, material delivery, a flood in Houston, and the need to

redo some of the work as issues arose. Sarah and José believed that Perez did not

prioritize the work on their house and that the changes to the scope of work that

Sarah requested could not account for any delays.

As the project progressed from demolition in early November 2015 through

completion in July 2016, Sarah frequently communicated with Perez and Eronko,

who principally handled billing. Some of the communications were light-hearted

and friendly and reflected the continued good relationship among them, including

sharing meals and holidays together.

In early November 2015, Eronko sent the Cruzes a conceptual budget

showing the anticipated costs for material and labor, plus 25%, based on the scope

of work that Bungalow Revival understood Sarah had requested. That estimate was

approximately $230,000. However, José testified that he did not want to spend that

much money on this project because of the large investment he had already made

in the house. He and Sarah testified that they had told Perez that their budget was

$140,000. According to Eronko, he sent the Cruzes requests for payment by email,

attaching a spreadsheet and the supporting the invoices or emailing or hand

delivering them separately. The Cruzes, however, said that they saw the

spreadsheet but not the invoices.

4 Some problems appeared throughout the project. First, Sarah had requested

that the floors be refinished because she did not like the reddish color of the

Brazilian cherry wood floors that were installed by the seller not long before the

Cruzes bought the home. The floors were sanded and refinished to an ebony color,

but they had to be redone after the Cruzes moved into the house due to a chemical

reaction that affected the appearance of the floors. The Cruzes temporarily left the

house while the floors were redone. The Cruzes were concerned about dust

mitigation during the flooring work because they had separately contracted for air

conditioning work, and they did not want the dust from the floor work to clog the

air conditioning system.

When the Cruzes finally moved in, Bungalow Revival still had to complete

the punch list—a final list of small changes, corrections, or completions to be made

to the house. Although the Cruzes, particularly Sarah, repeatedly indicated that

they were pleased with the appearance and the quality of the work in the home,

when they moved in, that changed. The primary issues of concern were the

Brazilian cherry wood floors, the work in an upstairs bathroom, particularly the

shower, and the air conditioning system.2 Although Perez said the floors were in

good condition when the Cruzes moved in, they underwent what he described as a

2 Sarah testified about other problems with Bungalow Revival’s work, including a broken water line to an ice machine, electrical outlet problems, floor issues, and a broken toilet seat. 5 chemical reaction in the weeks just after the Cruzes moved in. Sarah also testified

that she believed the floors were scratched by subcontractors performing other

work. The family left the house temporarily and the floors were refinished again.

Sarah testified that they stayed in a hotel for about a week, which cost $1,547.82.

By the time of trial, the Cruzes had not done any other work on the floors.

The Cruzes also maintain that the upstairs shower leaked, causing damage to

a downstairs ceiling. Sarah testified that she spent more than $13,000 to repair the

shower and about $3,000 to repaint the ceiling. Sarah testified that sawdust from

the projects done in the house got into the air ducts and clogged the air conditioner

drain, necessitating emergency repair.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ford Motor Co. v. Ridgway
135 S.W.3d 598 (Texas Supreme Court, 2004)
Interstate Contracting Corp. v. City of Dallas
135 S.W.3d 605 (Texas Supreme Court, 2004)
Pringle v. Moon
158 S.W.3d 607 (Court of Appeals of Texas, 2005)
French v. Moore
169 S.W.3d 1 (Court of Appeals of Texas, 2004)
Mayo v. State
17 S.W.3d 291 (Court of Appeals of Texas, 2000)
McKinley v. Drozd
685 S.W.2d 7 (Texas Supreme Court, 1985)
Croucher v. Croucher
660 S.W.2d 55 (Texas Supreme Court, 1983)
Stewart Title Guaranty Co. v. Sterling
822 S.W.2d 1 (Texas Supreme Court, 1992)
Gulf States Utilities Co. v. Low
79 S.W.3d 561 (Texas Supreme Court, 2002)
Johnson & Higgins of Texas, Inc. v. Kenneco Energy, Inc.
962 S.W.2d 507 (Texas Supreme Court, 1998)
Holland v. Wal-Mart Stores, Inc.
1 S.W.3d 91 (Texas Supreme Court, 1999)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Kroger Texas Ltd. Partnership v. Suberu
216 S.W.3d 788 (Texas Supreme Court, 2006)
Wayne Ventling v. Patricia M. Johnson
466 S.W.3d 143 (Texas Supreme Court, 2015)
Southwestern Energy Production Co. v. Berry-Helfand
491 S.W.3d 699 (Texas Supreme Court, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Bungalow Revival, LLC v. Jose Cruz, Jr. and Sarah Cruz, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bungalow-revival-llc-v-jose-cruz-jr-and-sarah-cruz-texapp-2025.